Resolved
Decision To note the progress made to date on the Improvement and Development Plan. (Reference: Report by Chief Executive, submitted).
Strategic Policy Committee noted this item on Thursday 22 March 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision To note the progress made to date on the Improvement and Development Plan. (Reference: Report by Chief Executive, submitted).
ARGYLL AND BUTE COUNCIL STRATEGIC POLICY COMMITTEE CHIEF EXECUTIVE’S
BEST VALUE IMPROVEMENT PLAN - PROGRESS REPORT 22/3/2007
1. SUMMARY The Council adopted the Best Value Improvement and Development Plan on May 4th 2006. This report summarises progress to the end of December 2006.
2. RECOMMENDATIONS It is recommended that the Strategic Policy Committee notes the progress made to date on the Improvement and Development Plan.
3. DETAIL 3.1 This progress report indicates that most of the Improvement and Development Plan is on track. This table provides an overall summary.
Last This Current Status quarter quarter position
Actions completed by 31st Dec 12 26 45
Actions progressing as planned 39 20 19 Actions delayed but with plans in place 21 14 13 to ensure progress Actions delayed and not rescheduled 0 0 0
3.2There are now 45 out of 77 actions completed .This equates to approximately 58% completion as opposed to 22% at the end of July to September reporting period. Any delayed actions have been rescheduled.
4. IMPLICATIONS FINANCIAL none PERSONNEL none EQUALITIES none POLICY none
For further information contact:
David Hanley, Best Value Officer Policy and Strategy Telephone 01546 604307 Email: [email protected]
1 Improvement and Development Plan – Progress Report Oct-Dec 2006
Argyll and Bute Council Best Value Improvement and Development Plan
Audit Apr-Jun 2006 Jul-Sept 2006 Oct-Dec 2006 Jan-Mar 2007 Due Lead Ref Report Action Evidence Progress Progress Progress Progress Date Responsibility Paras (Comp,A,B,C) (Comp,A,B,C) (Comp,A,B,C) (Comp,A,B,C) A: Leading rural Area A1 34 Develop the "Leading Jul-06 Chief Corporate Rural Area" aspiration, Executive, Plan including measures of Leader completed A A Comp - progress, targets and timescales A2 39, 41, Develop shared priorities Jul-06 Chief Corporate 98 with Community Executive, Plan A A A Planning Partners Leader completed A3 39, 41, Identify the Council’s Jul-06 Chief Corporate 92 share of responsibility for Executive, Plan delivery of Community Leader completed B A B Planning Partnership (June 07) work. A4 34 Include comparative Jul-06 Chief Corporate measures in the Executive, Plan A Comp - - Corporate Plan Leader completed
Progress: Comp=Action Completed A=progress as planned B=progress delayed but rescheduled C=progress delayed/not rescheduled 1 Improvement and Development Plan – Progress Report Oct-Dec 2006
Audit Apr-Jun 2006 Jul-Sept 2006 Oct-Dec 2006 Jan-Mar 2007 Due Lead Ref Report Action Evidence Progress Progress Progress Progress Date Responsibility Paras (Comp,A,B,C) (Comp,A,B,C) (Comp,A,B,C) (Comp,A,B,C B: Corporate Plan B1 34 Transform the Jul-06 Chief Corporate Corporate Plan through Executive, Plan A Comp - seminars and Leader completed - workshops. B2 36, 37, Identify a limited Jul-06 Chief Corporate 39, 41, number of Corporate Executive, Plan 137 priorities linked to the Leader completed Comp - - - Community Planning priorities B3 35, 80 Develop clear Jul-06 Chief Executive Corporate objectives and specific Plan - A Comp - actions to deliver the completed corporate priorities B4 40, 41, Include measurable Jul-06 Chief Executive Corporate 76 strategic targets with Plan - A Comp - timescales to deliver completed the corporate priorities B5 57, 81 Explain the Jul-06 Head Strategic Report relationships between Finance submitted capital planning, asset to Council, management and SPC, Area A A Comp - options appraisal; link Committees. this to Area Committees B6 81 Develop a system to Sep- Head Strategic Report on determine capital 06 Finance proposed spending priorities approach A A Comp submitted - to Council, SPC
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
BEST VALUE IMPROVEMENT PLAN: PROGRESS REPORTReport | 207 KB | DownloadRead as text |
Follow Strategic Policy Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Apr 2007 | Leader's reportDecision To note the contents of the report for the period 14 March to 10 April 2007. (Reference: Report by Leader of... | Noted | Open |
| 19 Apr 2007 | North of scotland local authorities - revenues and benefits projectDecision Agreed that delegated authority be given to the Head of ICT and Financial Services to sign a Memorandum of U... | Agreed | Open |
| 19 Apr 2007 | Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue... | Noted | Open |
| 19 Apr 2007 | Argyll and bute design awards scheme and sustainable design forumAgreed to have a single Council wide Planning Award Scheme to be administered centrally by the Design Forum and; 3. T... | Agreed | Open |
| 19 Apr 2007 | Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.