Resolved
Decision To note the Capital Plan position as at 31 December 2006. (Reference: Report by Head of Strategic Finance dated 23 January 2007, submitted).
Strategic Policy Committee noted this item on Thursday 22 March 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision To note the Capital Plan position as at 31 December 2006. (Reference: Report by Head of Strategic Finance dated 23 January 2007, submitted).
2.1The capital plan position report is noted.
3 DETAIL
3.1Appendix 1 summarises financial performance in terms of expenditure on the capital plan following the September monitoring exercise. Appendix 2 summarises overall project performance in terms of cost, timescale, benefits and risk. Project performance is summarised based on a red, amber and green traffic light analysis, where red requires corrective action, amber is a warning that there are performance issues but these are manageable and green is no significant performance issues.
3.2The individual projects with red classifications are reported in the relevant head of service report with comments on what the red issue is, what has caused it, the action proposed to correct it and the implications of the action.
3.3The table below summarises the overall financial position on the capital plan.
Previous Years Full Year This Future Years Total Project Year Actual Budget Forecast Budget Forecast Budget Forecast Budget Variance £000’s £000’s £000’s £000’s £000’s £000’s £000’s £000’s £000’s 37,242 37,198 27,862 28,222 78,162 73,923 143,266 139,343 -3,923
The main projects contributing to the variance are Campbeltown Community Project £1,083,000, Rothesay Harbour Ferry Berth Improvements £903,000, Argyll Air Services £775,000 and Campbeltown Harbour £600,000. The variance for the Campbeltown Community Project is primarily as a result of increased provision for contractual claims, and provision, for specialist consultant’s fees in defending such claims. The variance for the Rothesay Harbour Ferry Berth Improvements resulted from increased tender costs, reflecting the general increase in costs for the construction sector and slippage due to the Scottish Executive‘s delay in providing a formal offer of grant. Increased costs for Argyll Air Services was as a result of consultancy and additional works. In respect of Campbeltown Harbour, unexpected ground conditions have been encountered and the present contract will require to be varied to permit completion.
3.4The table below summarises project performance using traffic light analysis (Red, Amber, Green) in respect of cost, timescale, benefits and risk. 27 projects are classified as red out of a total of 306 project lines.
Spend This Project Total Project Project Project Risk Year Cost Timescale Benefits R A G R A G R A G R A G R A G 29 52 225 20 35 251 6 37 262 0 9 292 1 25 279
For further information please contact Bruce West, Head of Strategic Finance 01546- 604220
Bruce West Head of Strategic Finance 23 January 2007 CAPITAL PLAN MONITORING REPORT AT 31 DECEMBER 2006 - FINANCIAL SUMMARY APPENDIX 1
Service Previous Years Full Year This Year Future Years Total Project Actual Spend Full Year Actual % Actual Budget Forecast Budget Forecast Budget Forecast Budget Variance Dec-06 Budget Budget £000's £000's £000's £000's £000's £000's £000's £000's £000's £000's £000's £000's Head of Democratic Services & Governance 132 132 73 205 282 150 487 487 0 16 205 8%
Head of Legal & Protective Services 182 182 32 32 0 0 214 214 0 0 32 0%
Head of ICT & Financial Services 1,046 1,046 291 713 2,610 2,176 3,947 3,935 -12 95 713 13%
Head of Primary Education 783 783 3,768 4,811 12,174 11,028 16,725 16,622 -103 2,192 4,811 46%
Head of Secondary Education 202 202 1,163 1,133 5,304 5,246 6,669 6,581 -88 743 1,133 66%
Head of Community Regeneration 5,544 5,544 551 -532 291 191 6,386 5,203 -1,183 39 -532 -7%
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CAPITAL PLAN MONITORING REPORT: 31 DECEMBER 2006Agenda | 119 KB | DownloadRead as text |
Follow Strategic Policy Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Apr 2007 | Leader's reportDecision To note the contents of the report for the period 14 March to 10 April 2007. (Reference: Report by Leader of... | Noted | Open |
| 19 Apr 2007 | North of scotland local authorities - revenues and benefits projectDecision Agreed that delegated authority be given to the Head of ICT and Financial Services to sign a Memorandum of U... | Agreed | Open |
| 19 Apr 2007 | Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue... | Noted | Open |
| 19 Apr 2007 | Argyll and bute design awards scheme and sustainable design forumAgreed to have a single Council wide Planning Award Scheme to be administered centrally by the Design Forum and; 3. T... | Agreed | Open |
| 19 Apr 2007 | Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.