Resolved
Decision A PAN 41 Hearing is to be held to consider this application, this hearing to be held in Dunoon. (Reference: Report by the Head of Planning Services dated 10 th April 2007 – submitted)
Bute and Cowal Area Committee decided this item on Wednesday 11 April 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision A PAN 41 Hearing is to be held to consider this application, this hearing to be held in Dunoon. (Reference: Report by the Head of Planning Services dated 10 th April 2007 – submitted)
DEVELOPMENT SERVICES Local Members Councillor B. Chennell & Councillor B. Marshall th PLANNING APPLICATION REPORT Date of Validity - 16 February 2007 Bute and Cowal Area Committee Date - 11th April 2007
th 10 April 2007
Reference Number: 07/00373/DET Applicants Name: Cowal Leisure Ltd. Application Type: Detailed Application Description: Retention of 31 static caravans (amended 'as-built' layout previously approved under 00/01899/DET), temporary caravan transit parking; and the erection of 8 chalet lodges, installation of new water storage tank and septic tank. Location: Hunter’s Quay Holiday Village, Hunter’s Quay, Dunoon
SUPPLEMENTARY REPORT
(A ) THE APPLICATION
Development Requiring Express Planning Permission.
• retention of 31 static caravans (amended 'as-built' layouts previously approved under 00/01899/DET); • retention of temporary caravan transit parking area; • the erection of 8 chalet lodges on three sites with associated drainage within the existing chalet park area; • formation of vehicular access; • installation of new 100,000 litre water storage tank (6 x 6 x 3 metres) adjacent to existing water tank; • installation of new 54,000 litre septic tank to supplement existing two tanks.
Other Specified Operations
• connection to existing private sewer and public water system • tree planting;
(B ) RECOMMENDATION
Given the outstanding consultation responses concerning issues of a visual and ecological nature, the number of representations received (28 letters of objection) and a request from Hunter’s Quay Community Council to have the application continued, it is recommended that, subject to a discretionary hearing, planning permission be Granted subject to the standard condition and reason and the following conditions and reasons together with ‘notes to the applicant’ set out overleaf.
(C) DETERMINING ISSUES AND MATERIAL CONSIDERATIONS
The proposal is for the retention of 31 static caravans (amended 'as-built' layouts previously approved under 00/01899/DET) and temporary caravan transit parking, the erection of 8 new chalet lodges, the installation of new water storage tank and septic tank within Hunters Quay Holiday Park. st Planning permission (ref. 00/01899/DET) was granted on 21 December 2001 for an extension to the holiday village for five new villages which included Village D Iona, Village E Burnside and Village C Tiree. Work commenced on these villages around Spring 2001, prior to the conclusion of a Section 75 Agreement that was concluded on 21st December 2001. Potential enforcement action on the as-built layouts was ‘deferred’ due to discussions between the applicant and his agents and the department on the method to deliver a ‘masterplan’ proposal for the holiday park which involved large scale expansion and regularising outstanding matters. th However, following refusal of such a detailed masterplan scheme (ref. 04/02439/DET) on 5 September 2006 for an additional 9 new villages with a total of 291 caravan stances (which included the current proposal), the applicant has reviewed his proposal for expansion and has lodged a separate application for the formation of 3 new villages (proposed in accompanying application ref. 07/00379/DET) and deal with ‘as-built’ layouts within the current proposal.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
00373_SR1 Cowal Leisure regularisation of layouts Hunter's Quay Holiday VillageReport | 326 KB | DownloadRead as text |
PDF |
Planning Application 07/00373/DET, Cowal Leisure Ltd, Hunter's Quay, Holiday Village, Hunter's Quay, DunoonReport | 210 KB | Download |
Follow Bute and Cowal Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | Charts (argyll and the isles)Decision The Bute and Cowal Area Committee considered and noted the information provided in the presentation. (Refere... | Noted | Open |
| 1 Sep 2026 | Area committee quarterly performance reports fq1 2026/27Decision The Bute and Cowal Area Committee noted the performance and supporting commentary as presented. (Reference: ... | Noted | Open |
| 1 Sep 2026 | Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with... | Agreed | Open |
| 1 Sep 2026 | Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director... | Noted | Open |
| 1 Sep 2026 | Cruach mhor and clachan flats windfarm trustsDecision The Bute and Cowal Area Committee noted these updates, which are the most recent of the annual updates requi... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.