Resolved
Decision The Committee agreed that the Section 75 obligation relative to Planning Permission 97/01526/DET be discharged. (Reference: Report by Head of Development and Economic Growth dated 28 July 2022, submitted)
Planning, Protective Services and Licensing Committee agreed this item on Wednesday 17 August 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Committee agreed that the Section 75 obligation relative to Planning Permission 97/01526/DET be discharged. (Reference: Report by Head of Development and Economic Growth dated 28 July 2022, submitted)
Argyll and Bute Council Development & Economic Growth
Delegated or Committee Planning Application Report and Report of handling as required by Schedule 2 of the Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2008 relative to applications for Planning Permission or Planning Permission in Principle ____________________________________________________________________________
Reference No: 22/00921/PP
Planning Hierarchy: Local Application
Applicant: [name removed]
Proposal: Application for Discharge of Section 75 Obligation relative to Planning Permission 97/01526/DET
Site Address: Melda House, Kilfinan, by Tighnabruaich ____________________________________________________________________________
DECISION ROUTE
Local Government Scotland Act 1973 ____________________________________________________________________________
(A) THE APPLICATION
(i) Development Requiring Express Planning Permission
Discharge of Section 75 Obligation relative to Planning Permission 97/01526/DET
(ii) Other specified operations
None ____________________________________________________________________________
(B) RECOMMENDATION:
It is recommended that the Section 75 obligation relative to Planning Permission 97/01526/DET be discharged. ____________________________________________________________________________
(C) HISTORY:
Planning Permission (ref: 01/92/0293) was granted on 11th August 1992 for the formation of a car park at the site.
Planning Permission (ref: 01-93-0363) was granted on 1st July 1993 for the formation of fishing facilities at the site for a temporary period of three years.
An application for Planning Permission (ref: 97/00968/DET) was refused on 8th September 1997 for a dwellinghouse, office and shop on the site.
Planning Permission (ref: 97/01526/DET) was granted on 7th April 1998 for the erection of a dwellinghouse, office and shop on the site. The approval was issued upon the conclusion of a Section 75 obligation tying the ownership of the dwellinghouse, office and shop to the fishing enterprise that existed at Loch Melldalloch.
Planning Permission (ref: 02/01555/DET) was granted on 10th October 2002 for amended access arrangements and the removal of Condition 2 in relation to permission 97/01526/DET.
Non Material Amendment (ref: 03/00711/NMA) was granted on 6th May 2003 for an amendment to the position of the building.
Non Material Amendment (ref: 10/00178/NMA) was granted on 4th March 2010 to incorporate an amended door design; deletion of window; and installation of two dormer windows.
Non Material Amendment (ref: 10/01012/NMA) was granted on 28th June 2010 to incorporate alterations in window sizes.
Non Material Amendment (ref: 12/02720/NMA) was granted on 18th December 2012 for the addition of two velux windows in the dining area of the building. ____________________________________________________________________________
(D) CONSULTATIONS:
Not applicable. ____________________________________________________________________________
(E) PUBLICITY:
Not applicable. ____________________________________________________________________________
(F) REPRESENTATIONS:
None. ____________________________________________________________________________
(G) SUPPORTING INFORMATION
Has the application been the subject of:
(i) Environmental Statement: No
(ii) An appropriate assessment under the Conservation (Natural Habitats) Regulations 1994: No
(iii) A design or design/access statement: No
(iv) A report on the impact of the proposed development eg. Retail impact, transport impact, noise impact, flood risk, drainage impact etc: No
(v) Supporting Statement: Yes ____________________________________________________________________________
(H) PLANNING OBLIGATIONS
(i) Is a Section 75 obligation required: No The current application seeks to discharge the existing Section 75 obligation ____________________________________________________________________________
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2200921pp plan, 08/08/2022 Pre-Agenda Briefing of the Planning, Protective Services and Licensing CommitteeAgenda | 410 KB | Download |
PDF |
MR PAUL DAVID BARKER: APPLICATION FOR DISCHARGE OF SECTION 75 OBLIGATION RELATIVE TO PLANNING PERMISSION 97/01526/DET: MELDA HOUSE, KILFINAN, BY TIGHNABRUAICH (REF: 22/00921/PP)Report | 256 KB | DownloadRead as text |
Follow Planning, Protective Services and Licensing Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.