Resolved
Decision The application be approved subject to the conditions contained in the report by the Head of Planning Services. (Reference: Report by the Head of Planning Services dated 29 th May 2007 – submitted)
Bute and Cowal Area Committee approved this item on Wednesday 6 June 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The application be approved subject to the conditions contained in the report by the Head of Planning Services. (Reference: Report by the Head of Planning Services dated 29 th May 2007 – submitted)
DEVELOPMENT SERVICES Local Members - Councillors MacAlister, McQueen, Walsh th PLANNING APPLICATION REPORT Date of Validity - 10 April 2007 th Bute and Cowal Area Committee Date - 6 June 2007
th 29 May 2007
Reference Number: 07/00674/DET Applicant’s Name: Argyll and Bute Council, Operational Services, Roads Design, Blairvadach, Shandon, Helensburgh G84 8ND; Application Type: Detailed Application Description: Construction of flood defence works; Location: Flood Defence Works of Milton Burn from Hamilton Street to Alexandra Parade, Dunoon, Argyll
(A ) THE APPLICATION Development Requiring Express Planning Permission
• Construction of flood defence works comprising repairing and replacement training walls, overflow chamber and outfall pipe, replacing two pedestrian footbridges, earth bunds and associated engineering works.
(B ) RECOMMENDATION It is recommended that planning permission be Granted subject to the standard condition and reason and the advisory notes set out overleaf.
(C ) DETERMINING ISSUES AND MATERIAL CONSIDERATIONS
This application is for necessary flood prevention works to sections of the Milton Burn, Dunoon. The proposal has been the subject of pre-application discussions between SEPA, the Community Council representing the community affected by the scheme. The proposal comprises replacing existing walls with higher structures and replacing two existing footbridges at St. Mun’s and The Glebe. An overflow chamber with weir and new outfall pipe is proposed adjacent to the Somerfield car park. Taken separately, the majority of the works could have been considered as ‘permitted development’ but lodged as one linear scheme with overflow chamber, the proposal requires formal planning permission. Only three letters of representation have been received and of these, one is of a procedural nature, another has been addressed and another relates to works outwith the application site boundary (mater addressed and letter of objection likely to be withdrawn). Given the history of the Milton Burn and the condition of existing walls and banks, the proposed engineering works are considered necessary and acceptable in compliance with National, Structure and Local Plan policies.
Angus J Gilmour, Head of Planning Services
Case Officer: B. Close 01369-70-8604 Area Team Leader D. Eaglesham 01369-70-8608 ADVISORY NOTES TO APPLICANT RELATIVE TO APPLICATION REF. 07/00674/DET
th (i) The applicant/developer is advised of the formal response from SEPA (dated 11 May 2007) regarding technical and regulatory advice. A copy of this response is attached to the decision notice for the attention and information of the applicant/developer. th (ii) The applicant/developer is advised of the formal response from Scottish Water (dated 25 April 2007) regarding technical and regulatory advice. A copy of this response is attached to the decision notice for the attention and information of the applicant/developer. A. OTHER MATERIAL CONSIDERATIONS
(i) Site History None
(ii) Consultations th Scottish Water (response dated 25 April 2007): No objections subject to advisory notes.
Scottish Environment Protection Agency (response dated May 2007) : SEPA comment that they have been involved in the pre-application process where they have no objections to the proposal. In terms of flood risk SEPA is satisfied with the proposals but advisory comments are offered in respect of technical and regulatory advice.
Publicity and Representations th Under Section 34 Bad Neighbour Advert and Article 9 neighbour notification (expiry date 4 May 2007), a total of 3 letters of representation were received from [name removed], 2 Glebe View Cottage, George Street, Dunoon rd (letter dated 23 March 2007); Ian MacFadyen, Mariner Support Agency, PO Box 2326, Dunoon (letter dated rd 23 April 2007); and from Peter Sheppard, National Grid Property, Aviary Court, Wade Road, Basingstoke, rd Hampshire (e-mail dated 3 May 2007). The concerns raised are summarised below:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
00674 Location PlanPlan | 548 KB | Download |
PDF |
Planning Application 07/00674/DET, Argyll and Bute Council, Operational Services, Flood Defence Works of Milton Burn from Hamilton Street to Alexandra Parade, DunoonReport | 129 KB | DownloadRead as text |
Follow Bute and Cowal Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | Charts (argyll and the isles)Decision The Bute and Cowal Area Committee considered and noted the information provided in the presentation. (Refere... | Noted | Open |
| 1 Sep 2026 | Area committee quarterly performance reports fq1 2026/27Decision The Bute and Cowal Area Committee noted the performance and supporting commentary as presented. (Reference: ... | Noted | Open |
| 1 Sep 2026 | Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with... | Agreed | Open |
| 1 Sep 2026 | Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director... | Noted | Open |
| 1 Sep 2026 | Cruach mhor and clachan flats windfarm trustsDecision The Bute and Cowal Area Committee noted these updates, which are the most recent of the annual updates requi... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.