Decision The Area Committee:- i. Noted the contents of the report. ii. Agreed that David Logan be invited to the July Business Day to clarify the situation of demolition of the old Primary School in Rothesay and the provision/installation of IT equipment in the new schools. (Reference: Report by the QIO - Special Project Officer dated 27 th June 2007 – tabled)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report updates the Committee on the arrangements surrounding the service availability of the new School Facilities being procured through the NPDO project at Rothesay and Dunoon.
Recommendation
2.1It is recommended that the Committee note the contents of this report.
3. DETAIL
Background - Rothesay
3.1Service Availability for the occupation for Rothesay Joint Campus had a date for contract completion on 22 December 2006. Due to delays by the building contractor, Barr Construction, this date was missed. The Council has incurred no costs, in relation to the Project Agreement it has with ABC School Ltd, due to the delayed transfer date.
3.2Barr have recently brought in new site management and there has been a marked improvement in the progress on the site. This progress has been monitored carefully by the eventual school operator, ABC Schools Ltd, and the Council’s Special Projects team.
Current Position
3.3Barr have informed ABC Schools, and the Council, that the school will be available on 2 July 2007. Advice received from both ABC Schools and their advisers indicates that, whilst contract completion may not be achieved on this date they are optimistic that the school will be available very shortly thereafter and certainly during the summer holiday.
3.4Taking this advice into consideration processes have been put in motion in order to ensure that all necessary arrangements are in place for pupils and staff to occupy the new school in August. Barr’s removal company, HPI, have begun packing Rothesay Academy and Rothesay Primary so that staff have the opportunity to advise on the appropriate removal of materials to the new school. No items will be moved from the existing
E:\moderngov\data\published\Intranet\C00000242\M00002855\AI00035354\RJCDGTransferJune 20070.doc 1 sites until the Council has a degree of certainty of the exact date on which the new school will be available.
3.5In order to provide as much notice to parents as possible the Head Teachers of Rothesay Academy and Rothesay Primary have issued a letter to parents which confirms the expectation that the schools will be transferring over the summer holiday. This letter advises parents to bring their children to the new Campus for the new term. It also notifies them that the Scottish Executive has agreed for the schools to remain closed for an additional four days, adjacent to the holiday period, to enable Barr and school staff to complete the decant process.
3.6The relevant bus companies have been informed of the expected move and are aware of the timetabling and route changes required as a result.
Background – Dunoon
3.7Occupation of Dunoon Grammar School was due on 25 June 2007. Due to delays by the building contractor. Mansell, this date has been missed. The Council has incurred no costs, in relation to the Project Agreement it has with ABC School Ltd, due to the delayed transfer date.
Current Position
3.8Mansell have informed ABC Schools Ltd and the Council that the school will be available on 13 July 2007. Advice received from both ABC School and their advisors indicates that whilst contract completion may not be achieved on this exact date they are optimistic that the school will be available shortly thereafter and at some point during the summer holiday.
3.9Taking this advice into consideration processes have been put in motion in order to ensure that all necessary arrangements are in place for pupils and staff to occupy the new school in August. Barr’s removal company, HPI, have begun packing Dunoon Grammar so that staff have the opportunity to advise on the appropriate removal of materials to the new school. No items will be moved from the existing sites until the Council has a degree of certainty of the exact date on which the new school will be available.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with...
Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.