Decision The Area Committee agreed: i. The Area Roads & Amenity Services Manager will investigate the possibility of installing a security camera and provision of a staff presence at the facility. ii. That this matter be referred to the Council Executive to identify potential budget slippage within the existing Operational Services capital budget or from the Council’s capital budget to enable the upgrade of the to proceed without further delay. (Reference: Report by the Project Manager dated 2 nd July 2007 – tabled)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report updates members on the proposals to upgrade the Riverside public toilets and in particular asks members to consider how best to address the gap between available budget and anticipated upgrade costs.
Recommendations
2.1Members are asked to refer this shortfall to the Council Executive to identify potential budget sources from within the existing Operational Services or other Council Capital slippage.
Background
3.1Members were presented with upgrade options for the Riverside public toilets during February and June this year.
3.2Three options were discussed each with different standards of finish and with different associated costs.
3.3A middle ground option was selected by members as the most appropriate way forward. This allows for a “pay to enter” facility which would see the toilets undergoing a medium standard of internal upgrade and redecoration along with addressing the gathering of youngsters. The entry fee for use of the facility is proposed at 20p which is in line with similar facilities elsewhere in Argyll & Bute.
3.4Anticipated cost of this upgrade is £127,000 against an available budget (from previously unallocated Bute & Cowal infrastructure improvements) of £54,000. Thus a shortfall of £73,000 currently exists.
3.5There are no easily identifiable sources with which to address this shortfall. With few exceptions, projects already proposed for capital budget spend are expected to exhaust available funding.
3.6Given the above and in the absence of alternative and quickly identifiable monies, It is suggested that Members refer this matter to the Council Executive for consideration. 4. CONCLUSION
4.1Argyll & Bute relies heavily on tourism and although there is no statutory requirement to provide public toilets, members should be aware of the impact of poor PC provision on visitors’ perceptions of an area.
5. IMPLICATIONS Policy: None Financial: None - within appropriate financial capital allocation Personnel: None Equal Opportunity: None
For further information contact: Iain Welsh, Project Manager, Roads & Amenity Services
Telephone 01631 562125
Date 2ND July 2007
LIST OF BACKGROUND PAPERS: 1. RIVERSIDE POOL TOILETS – PROPOSED UPGRADE (B&C Business Day - 18th June 2007)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with...
Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.