Decision The Committee:- (i) Noted the contents of the report (ii) Agreed a Council wide target of 69% for processing all applications for the period 2007/08. (iii) Agreed to adopt the Scottish Executive target of processing 90% of householder applications within two months. (iv) Agreed the target of processing non-householders applications of 60% within two months. (v) Agreed the decentralised targets specified. (vi) Endorsed the principal of the proposed change in the “Blue Report” consultation process. (vii) Noted the potential savings in terms of finance regarding the use of Post Offices. (viii) Congratulated the Development Control staff on their performance. (Reference: Report by the Head of Planning Services – submitted) Councillor Marshall joined the meeting at this stage and took over the Chair.
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This paper outlines my Services Development Management performance with respect to planning applications, reports progress on key Service Plan targets and provides the results on the exit questionnaires.
1.2As with the previous few years, the Service has struggled to reach the target of processing 69% of planning applications within two months. For the fourth year in a row performance has hovered around the 64% mark, with last years performance being 63%; 6% below the agreed target.
1.3What is of significant concern to the Department is a further drop in the processing of householder applications from last years 89% to 83%. In previous years the Service has been able to maintain a performance of around the Scottish Executive target of 90%.
1.4Notwithstanding the current drop in performance, which has been essentially the result of a significantly lower level of performance in the Bute and Cowal Area Office than expected, and to a lesser extent in Helensburgh and Lomond, it is recommended that the targets stay the same as last year.
1.5As indicated in last July’s report, I am now in a position to advise on the number of major applications processed by each area together with including an analysis on the “application type” received by Area Office. Unfortunately, it has not yet been possible to set up a preliminary enquiry register, although this does remain a priority.
Recommendation
2.1It is recommended that Members:
a) Note the contents of the report. b) Agree a Council wide target of 69% for processing all applications within two months for the period 2007/8. c) Continue to adopt the Scottish Executive target of processing 90% of householder applications within two months. d) By agreeing an overall target of 69% with 90% of householder applications being dealt within two months this would require around 60% of non-householder applications to be dealt with, within a two month period. e) Agree the decentralised targets specified below:
• Bute and Cowal 65% No change; but would require a 19% improvement in performance. • Helensburgh 80% No change; but would require a 10% improvement in and Lomond performance.
• Oban, Lorn and 66% No change; but would require the maintenance of current the Isles levels of performance.
• Mid Argyll, 66% No change; but would require a 1% improvement in Kintyre and the performance. Islands f) Endorsing the principal of the proposed change in the “Blue Report” consultation process detailed in paragraph 3.10 (subject to the final detail being agreed in consultation with the Council Leader, Development Services Spokesman and Area Chairmen. g) Particularly note the potential savings in terms of finance, paper and staff resources if the use of “Post Offices” is stopped with regard to depositing plans (subject to the production of a detailed review of the cost and savings for Members consideration).
3.0COUNCIL WIDE DEVELOPMENT MANAGEMENT PERFORMANCE APRIL 2005 – MARCH 2006
3.1Table 1, which sets out the Development Management targets and achievements since 1996, is contained in Appendix 1 (Tables) to the rear of the report.
3.2As can be seen from Table 1, Development Management performance has remained consistent at around 64% for the last four years, with the Service struggling to improve overall service delivery. It should however be noted that performance fluctuates between area offices, with some areas improving performance whilst other areas continue to decline.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with...
Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.