DEVELOPMENT MANAGEMENT PERFORMANCE UPDATE - FQ4 2025/26

Agreed Planning 2 papers

AI summaryArgyll and Bute's planning committee has reviewed a development management performance update for FQ4 2025/26, noting further delays in determining applications and a small rise in legacy cases from 93 to 95.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedReport on FQ4 2025/26 performance
MoneyNot stated
What happens nextCut legacy backlogAim to reduce legacy cases towards single figures
Who it affectsPlanning applicants and DM serviceAcross the Argyll and Bute council area

What was decided

The committee reviewed and agreed the development management performance update for the fourth quarter of 2025/26, covering demand, output, backlog handling and average determination times. Report P4, 1.1, 1.2

Why

Performance has been hit by the legacy of the Covid pandemic, a previously downsized service, long-term staff vacancies and the arrival of National Planning Framework 4 with limited transition arrangements. Report 3.1

Output in the quarter has kept pace with new applications, but legacy cases continue to distort average determination times, and IT disruption in the previous quarter has had a knock-on effect. Report 3.5, 3.12

A planning team leader post in the MAKI area remains vacant, with cover on an acting-up basis and agency staff providing additional capacity. Report 3.4, 3.6

What happens next

Continue working to reduce the 95 legacy cases towards single figures. Report 3.13

Recruit a permanent team leader for the MAKI team and fill remaining vacancies. Report 3.4, 3.6

Introduce an interim admin process for pre-application enquiries in FQ1 2026/27 and develop a new pre-application service. Report 3.8

Implications

  • Other: The implications section flags a customer service duty to manage applicant expectations on planning decision times. Report 4.0
  • Risk: Risk is identified: inefficient determinations could affect the local economy, housing delivery and individual wellbeing. Report 4.0

Who and where

  • Planning applicants across Argyll and Bute Report 3.3, 3.10, 3.11
  • Development Management Service staff in the MAKI and BCHL teams Report 3.4
  • The local economy and housing delivery Report 3.13

Timeline

  • FQ4 2025/26: Reporting period for the performance update Report 1.1
  • Early 2023: Improvement Action Plan prepared in response to falling performance
  • 18th September 2024: Development Management Service Plan and Charter approved by PPSL
  • January 2026: Vacant planning and enforcement officer posts filled in MAKI and BCHL teams Report 3.4
  • FQ1 2026/27: Interim admin process to be introduced for pre-application enquiries Report 3.8

Plain English for the jargon

  • DM: Development Management, the council service that determines planning applications
  • IAP: Improvement Action Plan, drawn up in 2023 to lift planning performance
  • MAKI: Mid Argyll, Kintyre and the Islands planning team area
  • BCHL: Bute and Cowal, Helensburgh and Lomond planning team area
  • NPF4: National Planning Framework 4, the Scottish Government's national planning policy adopted in February 2023
  • Legacy case: A planning application that has been live for more than one year from validation
  • Householder application: A planning application for works to a single home, such as extensions or alterations
  • PPSL: Planning, Protective Services and Licensing Committee of the council
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

Decision The Committee reviewed and agreed the content of the report. (Reference: Report by Executive Director with responsibility for Development and Economic Growth dated 28 April 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Planning, Protective Services and Licensing Committee

Executive summary

1.1This report provides an update on the performance of the Development Management Service for the reporting period FQ4 2025/26.

1.2The attached document Appendix 1 provides an overview of the current demands upon the Development Management Service, its output during this period, the handling of the current backlog of casework, and the average time taken to determine planning applications.

Recommendations

2.1It is recommended that PPSL:

(a) Review and agree the content of the report.

3.0DETAIL & BACKGROUND

3.1The performance of the Council’s Development Management Service has been significantly impacted by the legacy effect of the Covid Pandemic upon interruption to workflow and a subsequent increase in demand for regulatory activity relating to new development. This situation has been exacerbated by the Service having previously been down-sized in response to the longer-term wider financial pressures facing the Council combined with a number of long-term vacancies that proved extremely difficult to fill as a result of a national shortage of planning professionals. The determination of planning applications has also been impacted by the uncertainty created by a changing planning policy backdrop with the Scottish Government’s adoption of National Planning Framework 4 (NPF4) in February 2023 with minimal transition arrangements having had a noticeable adverse impact on FQ4 2022/23 output as a result of a significant volume of casework requiring to be reassessed prior to its determination. The cumulative effect of these extraordinary pressures has given rise to a significant backlog of planning casework that continues to impact upon the ability of the Council to deliver the Development Management Service in an efficient and effective manner at this time, and impacts upon customer service. At FQ4 2022/23 the backlog of applications amounted to approximately 375 formal applications and 175 pre-application enquiries. 3.2 An Improvement Action Plan (IAP) was prepared in early 2023 in response to the significant decrease in performance and wider issues impacting upon the resourcing of the service and its interactions with customers. The implementation of the IAP has ensured the delivery of additional capacity within the Development Management Service and along with this improvement initially in terms of output and more latterly improving trends are also now able to be identified in relation to the making of timely determinations. Building upon the foundation of the IAP, the Development Management Service Plan and Development Management Charter approved by PPSL on 18th September 2024 set out updated performance targets for the Service. These include a wider range of measures that seek to demonstrate the delivery of individual elements of the IAP and in addition to timeliness include measures which can be utilised to measure customer satisfaction, and staff welfare.

3.3DEMAND: The Development Management Service receive approximately 2000 planning and related application case work items on an annual basis. The Development Management Service is resourced with the expectation that demand will be relatively constant and steady throughout the year. Whilst the volume of new submissions decreased by approximately 10% during 2020/21 they had returned to and exceeded pre-pandemic levels during 2021/22. Submission rates have subsequently been maintained at a high level and during 2022/23 were 5% up on pre-pandemic levels. Appendix 1, Sheet 1 shows that whilst submission rates continued to show an increase in demand during FQ4 2025/26 this has increased slightly from the previous reporting period.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
DM Performance FQ4 2526Appendix 1 633 KB Download
PDF
DEVELOPMENT MANAGEMENT PERFORMANCE UPDATE: FQ4 2025/26Report 168 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 16 attended
KM
Katie McKenzieSecretary, expected
JA
Councillor John ArmourMember, present
GB
Councillor Gordon BlairChair, apologies
JB
Councillor Jan BrownMember, present
AF
Councillor Audrey ForrestMember, apologies
KG
Councillor Kieron GreenChair, present
AH
Councillor Amanda HampseyMember, present
DH
Councillor Daniel HampseyMember, present
GH
Councillor Graham HardieMember, present
FH
Councillor Fiona HowardMember, present
AK
Councillor Andrew KainMember, present
PD
Councillor Paul Donald KennedyMember, present

All 16 on the meeting page

On this subject at Argyll and Bute

Search all
  1. DEVELOPMENT MANAGEMENT PERFORMANCE UPDATE - FQ4 2025/26This decision
  2. Development management performance update - fq1 2026/27Agreed
  3. Helensburgh golf club, cala management ltd & dunbrittton housing: proposal of application notice for residential development (including affordable housing housing association);Noted
  4. Development management performance update - fq3 2025/26Agreed
  5. Development management performance update - fq4 2024/2025Decided
  6. Development management performance update - fq3 2024/25Noted

More from Argyll and Bute Planning, Protective Services and Licensing Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Beaufort wind limited: erection of 7 turbines (up to 149.9m to tip) and ancillary development and decommissioning of existing beinn ghlas wind farm: existing beinn ghlas wind farm, taynuilt (ref: 25/01240/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: 1. PP - A... Agreed Open
15 Sep 2026 Mr tony coogan: alterations to guesthouse to facilitate lawful use of existing roof space as ancillary guest house owner's accommodation: greencourt, benvoullin road, oban (26/00434/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Mrs faulkes: proposed alterations and erection of extension: 30 the green, craobh haven (ref: 26/01009/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Scottish power renewables/machair wind limited: scottish government's marine directorate section 36 consultation on proposed machair offshore wind farm: site 15 km north west of isle of islay and 12.4 km west of isle of colonsay (ref: 26/01100/s36)Decision The Committee agreed that the Scottish Government’s Marine Directorate should be notified that Argyll and Bu... Agreed Open
15 Sep 2026 Development management performance update - fq1 2026/27Decision The Committee reviewed and agreed the content of the report. (Reference: Report by Executive Director with r... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies