Decision To approve continuing development of the Council depot project at Luss Road , Helensburgh in line with the detail at paragraph 4.3 of the report. (Reference: Report by Director of Operational Services dated 7 August 2007, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
This report advises the Executive Committee on the anticipated shortfall in capital funding currently preventing full implementation of proposals for the new Operational Services depot at Luss Road, Helensburgh.
Recommendations
2.1The Executive approved continuing development of the Council Depot project at Luss Road, Helensburgh in line with paragraph 4.3 of this report.
Background
3.1The Operational Services workforce for Helensburgh & Lomond works from several locations, including one at Millburn, Renton on lease from West Dunbartonshire Council (WDC).
3.2There has been a long standing desire to operate from one consolidated base within the Helensburgh & Lomond area for reasons of operational efficiency. Additionally there is a requirement to vacate the Renton site as WDC intend to terminate the lease and actively market the site in the reasonably short term. We currently have an occupancy agreement through to the end of March 2008.
3.3During the last 10 years or so a variety of sites in Helensburgh & Lomond were assessed for suitability and the Luss Road ground was selected and purchased in 2003. Prior to that, in 2002, £1,221,000 was approved for allocation to the site in the capital programme. Following access road construction and design fees there is currently £874,000 remaining.
3.4Subsequent to this purchase various depot designs have been proposed, all of which so far have greatly exceeded the available budget. Officers in Operational Services along with consultant engineers and architects have proposed cost saving designs and different layouts in an effort to bring the development in line with current budget but this process has not closed the gap, largely due to expenditure required to deal with existing ground conditions.
3.5Expenditure for drainage in particular is far in excess of that predicted - and the anticipated sum for remaining construction is likely to be at least £1,840,000 –an anticipated shortfall of £966,000.
1 3.6 The works do not appear eligible for external funding, including European sources, so the shortfall requires to be addressed by Argyll & Bute Council, if it is to proceed in the proposed form.
3.7It is not possible to continue with using the Millburn Depot in Renton as West Dunbartonshire Council have indicated that they intend developing this site. It should be recognised that this matter has been ongoing since 1995, although in the first few years of Local Government re-organisation there was no great desire to complete the re-location of staff. As mentioned previously around 2002 there was a capital allocation made to construct a new depot on the current proposed site. In the following five years there has been no allowance made for inflation. The significant increase in the building industry which has resulted in tender prices way in excess of anticipated prices, the requirements of SEPA from a drainage requirement and a salt dome provision and perhaps most importantly the estimate was based on a lack of knowledge in the geotechnical condition. Subsequent investigations have shown the need to undertake ground stabilisation work and also substantial additional drainage work.
It is not possible to “do nothing” as there will be no depot from which road services can be delivered. There are clear operational benefits to locate the depot in Helensburgh & Lomond, and possible temporary use of West Dunbartonshire depots in Clydebank or Dumbarton should be discounted on economic and operational grounds.
There are no other sites available in the Helensburgh & Lomond area. Indeed in 2003 the Luss Road was purchased after and exercise was undertaken.
When the Depot has been completed this will provide an appropriate operational base for roads and waste collections and in the fullness of time ground maintenance.
4. OPTIONS TO BRIDGE FUNDING GAP
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.