Decision Approved the proposed projects to invest the additional capital allocation of £2.126m in asset sustainability and service development as detailed in Appendix 2 to the report by the Executive Director. (Reference: Report by Executive Director – Community Services dated 19 March 2012, submitted) #
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1At its budget setting meeting on 16th February 2012, the Council approved the capital budget for the period 2012/13 to 2014/15. The approved budget included an additional allocation of £2.126m to be invested in the education estate to improve the sustainability of the assets and to support service development projects. In total this allocation increased the Council’s investment in the education estate over the 3 year period to £17m.
1.2This reports provides proposals for the investment of the additional capital allocation for consideration by the Executive.
Recommendations
2.1The Executive is asked to approve the proposed projects detailed in appendix 2 to this report to invest of the additional capital allocation of £2.126m in asset sustainability and service development.
3. DETAIL
3.1Background.
At its budget setting meeting on 16th February 2012, the Council approved the capital budget for the period 2012/13 to 2014/15. The approved budget included an additional allocation of £2.126m to be invested in the education estate to improve the sustainability of the assets and to support service development projects. In total this allocation increased the Council’s investment in the education estate over the 3 year period to £17m.
3.2The increased investment in the education capital plan over the 3years to £17m will support the corporate outcome of our young people having the skills, attitudes and achievements to succeed throughout their lives by improving the quality of the school estate and raising the condition of school buildings.
3.3As detailed in the Corporate Asset Management Plan approved by Council in February, the main focus of the Education capital programme is to ensure that buildings are safe and wind and water tight, with particular emphasis being given to upgrading life expired electrical, alarm systems and heating installations. Expenditure has been prioritised on properties based on the risk profile associated with property attributes. Improvements to school buildings are targeted at properties in the poorest condition, and building elements which are currently rated as Bad or Poor. For schools where the significant building fabric issues have now been addressed, consideration is now being given to works to improve suitability. The asset sustainability activity is supplemented with investment on service development projects such as the new Campbeltown Grammar School and the Shared Primary and Pre 5 Campus in the Dunoon area.
3.4The Community Services Asset Management Plan links directly to the Council's 2011-2012 Corporate Plan, and in particular the Corporate Objectives of;
(2) Working together to improve the potential of our Communities, and (3) Working together to improve the potential of our area.
In addition the key themes of the Councils Improvement Plan Risk Management and Asset Management are addressed. The Community Services Departmental Service Plan requires the delivery of improvements to the Department's building assets, and the delivery of safe, efficient, fit for purpose public buildings which enhance service.
The requirements of the Council’s Corporate Asset Management Strategy are also adhered to with many of the Asset Sustainability projects which are being put forward under the 2012-13 and 2013-14 capital plan supporting the Council’s Carbon Management Plan, through the upgrading of insulation as part of re roofing contracts, replacing single glazed windows with double glazed units, and through the specification of low energy light fittings as part of rewiring contracts.
The new proposals set out within this paper are fully consistent with the Education Service Plan, the overall education capital programme and its contribution to and alignment with the above strategic planning documents.
3.5Phasing of the Additional Allocation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.