Organisational Development Policy and Performance Group noted this item on Wednesday 12 March 2008. Below is the council's own wording, with the papers it was decided on.
Decision 1. To note the contents of the submitted report. 2. That the Group be given the opportunity to have an input to the priorities and that a report on this be brought to the next meeting of the PPG scheduled for 11 June 2008. (Ref: Report by Head of ICT and Financial Services dated 3 March 2008, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Organisational Development Policy and Performance Group
Summary
1.1The Shared Services diagnostics (Simplify, Standardise, Share) commenced in February 2008, a little later than originally planned but this project is still on schedule to be largely completed by end of June 2008, with reports to be finalised by end of August. This report gives an update on progress to date and key milestones.
Recommendations
2.1The update is noted.
3 DETAIL
Project resourcing 3.1 The project team structure has been put in place as follows:
Project Sponsor: James McLellan, Chief Executive
Shared Services and Procurement Board: Chair: Nigel Stewart
Senior Responsible Officer: Judy Orr
Project Manager: Tom Millar
Project Team: Lisa Bridgewater, Gordon Munro, Ian Nisbet, Rikki Young Administrator: Esther Anderson
3.2The Project Manager and the project team appointments have been made on the basis of secondments with the cost of the secondments being met by the project.
3.3In addition, a number of people across the organisation have been identified as cross cutting subject matter experts and they will act as a lead for workshops on these key themes.
Page 1 of 4 External consultancy 3.4 Following a tender using the OGC catalyst framework agreement “Multi- disciplinary Consultancy” Code RM353, PriceWaterhouseCoopers (PwC) were selected to provide external consultancy for this project. PwC were the consultants to the Glasgow pathfinder and bring the learning from that assignment and from a number of other similar projects they have carried out for other local authorities. PwC were appointed collaboratively by ourselves along with Highland, Moray and Dumfries and Galloway Councils.
3.5The PwC tender offers us 95 days consultancy. The consultancy days are allocated to the project stages as follows:
Total Days Getting started 6 Gathering Information 12 Identify Opportunities 50 Moving Forward 27 Total 95
Progress 3.6 The formal project launch was held on 25 February and this completed the “Getting started” stage. The launch was attended by 82 councillors, directors, heads of service, union representatives and third/fourth tier managers. It communicated the aims and objectives of the project, the project structure, project plan and key milestones, described the Improvement Service toolkit and PwC methodology, and how staff would be involved through interviews and workshops. Launch packs have been issued to all those who did not manage to attend.
3.7The Shared Services and Procurement Board reviewed the Project Initiation Document and project plan at its meeting on 18 February and agreed this subject to a number of amendments.
3.8The Gathering Information stage of the project has commenced with 12 interviews completed (7 signed off) as of 29 February, and a further 38 interviews organised out of an estimated total required of 91. This is on track for the next milestone of completing 80% of interviews by 28 March. Interviews with directors, heads of service and third tier managers are initially being carried out in teams of two for the first two weeks, and then as expertise grows, interviews will be carried out on a one to one basis except where significant complexity is anticipated.
Key milestones 3.9 The key milestones laid down by the Improvement Service for this national project are as follows:
• Data Gathering commenced 15 Feb • 80% meetings completed by 28 March • As Is baseline submitted by 4 April
Page 2 of 4 • Gap analysis commenced by 30 April • Report on Gap analysis by 30 May • Commence prioritisation by 6 June • Complete prioritisation report by 30 June • 2 page business cases by 4 July • Agreed by SMT by 15 August • Deliverables all submitted by 29 August
3.10The Improvement Service carried out an assessment of the Council’s progress on 25 February and assessed us as being on track on all aspects. The next assessment of progress is due on 19 March.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Organisational Development Policy and Performance Group at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Asset management progress reportDecision The PPG noted:- 1. the progress that has been achieved over the past year; 2. the key elements of the forwar...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.