Decision To request that further information be brought forward to the meeting scheduled for 10 December 2008 relating to:- (a) Paragraph 6.4 of the submitted report. What does this mean and what options were being looked at for contract forms? (b) On the basis that a lot of Local Authorities were using NEC, had this Authority looked into this and how would it all fit in with Scotland Excel? (Ref: Joint Report by Strategic Finance, Operational Services and Corporate Services dated 5 March 2008, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Organisational Development Policy and Performance Group
ARGYLL AND BUTE COUNCIL ORGANISATIONAL DEVELOPMENT PPG 12 MARCH 2008
BASELINE PAPER ON LARGE SCALE CAPITAL PROCUREMENT
1 INTRODUCTION
1.1The PPG at its meeting on 23 January 2008 requested a baseline paper on procurement of large scale capital projects be prepared. The PPG instructed Stewart Turner, Sandy Mactaggart, Donnie Kelly and Bruce West to prepare the baseline paper.
1.2This baseline report is set out as follows: • Pre procurement/capital planning – Bruce West • Roads & Amenity Sevices o Tendering and letting of contracts – Stewart Turner o Tendering evaluation and assessment process – Stewart Turner o Monitoring and management of contracts - Stewart Turner • Facility Services o Tendering and letting of contracts –Sandy Mactaggart o Tendering evaluation and assessment process – Sandy Mactaggart o Monitoring and management of contracts - Sandy Mactaggart • Post completion reviews – Bruce West • Contract Standing Orders and key legal issues – Donnie Kelly • Scotland Excel Procurement Issues – Alan Brough
2 PRE PROCUREMENT AND CAPITAL PLANNING
2.1A key issue in the management of large scale capital procurement is ensuring that the project is properly planned and scoped with appropriate analysis of options, risks and financial consequences prior to the commencement of the procurement process. This is about being clear what it is we want to buy and understanding why it is we want to buy it. A robust process surrounding the development and assessment of capital projects before they move to the procurement phase is essential.
2.2Historically approval to proceed with projects has been based around the inclusion of a project in the capital plan with reporting of tenders to the Council for approval where required in terms of contract standing orders. Projects were traditionally considered for inclusion in the capital plan each year when the capital plan was updated as part of the budget process. This often meant projects were approved for inclusion in the capital plan on the basis of only a preliminary assessment and with estimates of cost made early in the development of a project. For the last few years only block allocations have been made in the capital plan and this was to enable the consideration of future projects to be based on a business case approach. 2.3 The capital planning guidance that is in the process of being finalised is based around the concept of a gateway approach and preparation of business cases. This guidance sets down 3 categories of capital project – asset sustainability, service development and strategic change. It is envisaged that large scale capital procurements would fall into the category of strategic change. Strategic change projects would require to submit 3 levels of business case before they received final approval to commit/commence works/accept tenders.
2.4An initial business case (IBC) would be prepared at the very early stages of a project to identify the projects that are worthy of further investment by development of an outline business case (OBC) and those which could be rejected at an early stage. Approval of the IBC would represent permission to develop and OBC. An IBC should be no more than 2-4 sides of A4 and should cover the following:
• A paragraph describing the specific project being proposed.
• Paragraphs indicating the explicit contributions the proposal will make to the Council’s plans and strategies and will ensure compliance with external requirements. This will include an indication of how it is anticipated the project will contribute to the corporate plan themes, corporate resource strategies, area priorities, service plans and legal and national requirements.
• An indication of the range of capital costs, revenue costs and external funding including comment on the basis of these estimates.
• An outline of how the project would be delivered, the timescales for delivery and any knock on residual consequences.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Organisational Development Policy and Performance Group at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Asset management progress reportDecision The PPG noted:- 1. the progress that has been achieved over the past year; 2. the key elements of the forwar...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.