Decision 1. To note the contents of the report about progress achieved in implementing the action plans arising from the SWIA Inspection and the Scrutiny Review of Social Work; and 2. To note that the progress made in both of these Plans can be monitored on the Pyramid Performance Management System. (Reference: Report by Director of Community Services dated 17 March 2008)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report provides a six month update on progress made in the implementation of the Social Work Review and Social Work Inspection Agency (SWIA) Improvement Plan (appendix 1). Using the traffic light system to chart progress, the Action Plan highlights:
SWIA
• Green 23 recommendations in the SWIA Improvement Plan are on target. • Amber 1 • Red 0
Scrutiny Review
11 actions have been incorporated into the SWIA Improvement Plan.
• Green 11 (9 actions completed, 2 on target) • Amber 0 • Red 0
Recommendations
2.1Members are asked to note the content of this report about progress achieved in implementing the action plans arising from the SWIA Inspection and the Scrutiny Review of Social Work.
2.2Members should be aware that the progress made in both of these plans can be monitored on the Pyramid Performance Management System.
3. DETAIL
3.1At a meeting of the Strategic Policy Committee (SPC) held on 14 December 2006, a report from the Director of Community Services, summarising the key findings and recommendations of the Social Work Scrutiny Review which was carried out over an eight month period, was considered. 3.2 The SPC agreed to recommend that the Council accept the findings of the report and to approve the implementation plan set out.
3.3The Council discussed the Social Work Scrutiny Review paper referred by the SPC at a meeting held on 17 January 2007, where it was agreed to endorse the recommendations made.
3.4At a meeting of the Council in January 2008, the Improvement Plan to meet the Social Work Inspection Agency’s requirements was presented and approved.
3.5Progress made on this will be monitored by SWIA quarterly and by a six month return visit which will take place between 18 – 20 June 2008.
3.6A copy of the latest action plan is attached for information and is monitored fortnightly at the Departmental Management Team.
3.7The final action point of the plan recommended that a six monthly update be made available for Elected Members.
3.8A seminar for Members will be held in April/May on the work done in relation to the future of older peoples services which forms a significant part of the action plan for Social Work.
4. CONCLUSION
4.1This report and its appendix provide Members with detailed progress made in implementing the Social Work Scrutiny Review/Social Work Inspection Agency (SWIA) Improvement Plan.
5. IMPLICATIONS
Policy: None.
Financial: The action plan aims to implement a robust and transparent financial regime for the managing of Social Work Services.
Legal: None.
Personnel: None.
Equal Opportunities: Actions are in line with Council’s Equal Opportunities Policy.
Director of Community Services 17 March 2008
For further information contact: Sandra Greer, Head of Service, Kilmory, Lochgilphead Tel: 01546 604391
Swreviewswiaupdateapril20080.Doc 2 10/04/08
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.