Decision 1. To note that the provision of 29 flats for shared equity will still address the Local Housing Strategy priorities in the area; 2. To agree the provisional allocation of £400,000 from the Strategic Housing Fund to help secure the revised funding package of £5.4m, subject to Fyne Homes obtaining all statutory permissions and complying with the conditions for draw down; 3. To instruct the Director of Community Services to prepare a report for an early meeting of the Executive regarding the housing situation in Argyll and Bute and the policy issues in place; and 4. To request that the Director of Community Services and Spokesperson for Housing Issues arrange to meet with appropriate Government Ministers/Officials to discuss the concerns raised by Members in respect of the housing situation in Argyll and Bute. Councillor Robb, having moved an amendment which failed to find a seconder required his dissent from the foregoing decision to be recorded. (Reference: Report by Director of Community Services dated 25 April 2008, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1Members may recall that at the Executive meeting of 20 September 2007, agreement was reached to provisionally allocate £400,000 from the Strategic Housing Fund in support of the above project. This was to help secure an overall funding package of £4.4m.
1.2Fyne Homes have now advised that following their tendering exercise, the global development costs for the project have risen to £5.4m. In an effort to address the increased costs, Communities Scotland (now merged with the Scottish Government) have indicated that they will only be able to sign off the project if the tenure of the flats is changed from social renting to LIFT/Shared Equity.
Recommendation
2.1Members are asked to:
(a) Note that the provision of 29 flats for shared equity will still address Local Housing Strategy priorities for the area (b) Confirm the provisional allocation of £400,000 from the Strategic Housing Fund to help secure the revised funding package of £5.4m, subject to Fyne Homes obtaining all statutory permissions and complying with the conditions for draw down.
3. DETAIL
3.1Within my report to the Executive of 20 September 2007, I outlined Fyne Homes’ proposals for the conversion of the former Council Chambers and Sheriff Court building, together with the neighbouring property at 3 King Street, in the centre of Rothesay. Their proposals were for the provision of the following units of accommodation:
• King Street – 4 x 1 bedroomed 2 person flats • Council Building & Sheriff Court - 19 x 1 bedroomed 2 person flats - 6 x 2 bedroomed 4 person flats • Total – 29 flats
3.2At that point in time, the overall project costs were projected to be around £4.4m and Members agreed to allocate £400,000 from the Council’s Strategic Housing Fund in support of the project. This was with a view to assisting the association to secure the overall funding package which would be made up of Housing Association Grant from Communities Scotland, together with the necessary private finance.
3.3Regrettably, however, after undertaking a tendering exercise which complies with all European competition requirements, Fyne Homes have reported that the development costs associated with the project have now risen to £5.4m. These revised costings were subjected to appraisal on a value for money basis by Communities Scotland prior to their merger with the Scottish Government. Arising from this, they have confirmed that the project could still be considered to represent value for money but only if the tenure of the flats was changed from the originally planned social renting to shared equity or LIFT. This change is necessary in order to increase private sector leverage into the scheme. Having carried out this re-assessment, both the Scottish Government and Fyne Homes have requested the Council to confirm the previously agreed allocation of £400,000 from the Strategic Housing Fund on the basis of the change in tenure.
3.4Members are asked to note that Fyne Homes’ revised proposals still serve to address Local Housing Strategy priorities for the area. In the circumstances, it is recommended that the £400,000 grant previously offered should now be confirmed on the basis of the altered provision.
4. CONCLUSION
4.1Fyne Homes have developed proposals for the conversion and upgrading of the former Council Chamber together with the neighbouring property at 3 King Street in Rothesay. Their project proposals fit within the context of the Local Housing Strategy and will secure the delivery of 29 much needed flats for shared equity. Communities Scotland/Scottish Government have confirmed their support for the project and have committed funding within their investment programme in each of the next 3 years.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.