Decision 1. To note the contents of the report; and 2. To agree to invite the Performance Manager to the next meeting of the Audit Committee to give a progress report on the implementation of Pyramid. (Reference: Report by Chief Executive’s Unit, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
ARGYLL AND BUTE COUNCIL AUDIT COMMITTEE CHIEF EXECUTIVE’S UNIT 27 JUNE 2008
SUMMARY OF QUARTERLY PERFORMANCE REPORTS
1 SUMMARY This paper provides a summary of the Service quarterly reports for the period January to March 2008, consisting of the exceptional performance sections only.
2 RECOMMENDATIONS It is recommended that the Audit Committee • notes the Service performance in the report and • considers the style and content of the report and makes suggestions about improvements to this report to assist the Audit Committee in considering performance matters.
3 DETAIL Service Plans include a level of detail for each Priority, essentially the third tier management level across the Council. Where a Priority is reported as performing above or below the planned level, this performance may be evaluated as exceptional.
The selection of performance included as exceptional relies on the report provided by Services. It is this exceptional performance that is included here. Where explanations for exceptional performance have been provided by Services they are repeated here.
The full quarterly reports are available from the Performance Manager in the Policy and Strategy Team.
For further information contact:
David Clements, Performance Manager, Policy and Strategy. Telephone 01546 604205 Email: [email protected]
1 Argyll and Bute Council Extracts from Quarterly Performance Reports Jan – Mar 2008 This paper draws together the exception reports from the quarterly Service performance reports for the fourth quarter 2007/08. Exception reports are those areas of service delivery that the Head of Service considers ahead (ü) or behind (û) the planned level of service. Where no exceptional performance has been reported, the level of service is generally as planned.
Chief Executive’s Unit Communications – no exception reports
Personnel Services – no exception reports • The detailed sickness absence figures have been entered into Pyramid, the Council’s performance management system, providing a simple method to analyse the large volume of data provided.
Policy and Strategy Proactive work is still suffering due to pressures on the small team; this period effort has been directed to the Single Outcome Agreement.
Strategic Finance ü Both loan fund and long term borrowing rates show favourable trends
Community Services Adult Social Work • The number of people with no allocated caseworker is reported at 246 (against 321 planned this quarter) • The number of people with no allocated caseworker awaiting Occupational Therapy Services is reported at 445 (against 513 planned this quarter) • The number of people awaiting funding for a care package is not reported (previous reports showed Nov 07 = 51; Dec 07 = 27) ü The number of people waiting for assessment and for a service following assessment is reported to be reducing
Community Regeneration - no exception reports
Planning and Performance - no exception reports
Children and Families ü The number of children in the child protection system with no allocated worker has reduced to around 4%
Education ST Mun’s Primary school received an exceptionally good HMIE report
Corporate Services ICT and Financial Services û 12 month delay to e-Planning system due to national programme delays. (same comment as previous report) û Care First financial modules implementation delayed by 9 months and NHS declining to use Care First in integrated teams
2 Over 95% of Council Tax has been collected (provisional figure) Over 97% of non-domestic rates has been collected (provisional figure) û The number of new Benefit claims outstanding longer than 50 days stands at over 25% against a target of 9%. û Benefit claims have generally been slower than planned Annual cashable savings of £386,500 reported from Exchequer Services.
Legal and Protective Services – no report received
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Internal audit summary of activitiesDecision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March ...
Internal audit annual plan 2017 - 2018Decision The Committee agreed and approved the Internal Audit Annual Plan 2017/18 (Reference: Report by Chief Interna...
External audit plan 2017 - 2018Decision The Committee noted the contents of the report. (Reference: Report by Audit Scotland dated March 2017, submi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.