Decision To approve the new schemes identified in paragraphs 4.2 – 4.6 of the report in line with the general phasing shown in Appendix A and the initial business cases attached to the report. (Reference: Joint Report by Director of Development Services and Director of Operational Services dated 15 April 2009, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Capital Project Name – Campbeltown Infrastructure Improvements 1. Strategic fit: the strategic case: 1.1 Identify and explain business need
The project will centre on the expansion of the marine facilities at Campbeltown New Quay and associated road improvements. It will allow the exported amount of locally generated goods to be significantly increased.
1.2Demonstrate how the project support the corporate plan and other resource strategies
Completion of the project will aid a growing sustainable economy.
1.3State expected benefits
Larger ships will be able to use the harbour and freight movements to the pier will be made easier by the provision of a stronger structure. This will permit business expansion in the South Kintyre area.
1.4Outline the key risks to achieving these benefits
Acquisition of land, planning objections, ground conditions, funding, market conditions at the time of tender, market forces, existing users of the pier facilities.
1.5Identify main stakeholders and their commitment
Harbour and road users Council - Project Manager, harbour authority, designer, funder, project sponsor; Consultants – Design of the harbour works; Contractors – Construction of the harbour works; Crown Estates Land owners
2 Options appraisal: the economic case :
2.1Outline options considered
Definitions: S-type vessel – The preferred ship at 168m length and 8m draught F-type vessel – Ship meeting minimum requirements at 138m length and 6.8m draught The existing quay means Campbeltown New Quay.
The costs shown include roadworks between the factory and the quay.
Modification of the existing New Quay. Option 1A £15m Extend existing quay for S-type vessels. Option 1B £10.9m Extend existing quay for F-type vessels. Option 1C £12.7m Part extend existing quay. Length to accommodate F-type vessels but depth to accommodate S-type vessels, to allow for future development. 1 of 4 Option 1D Not costed. Ruled out (refer to Section 2.2) Option 1E Not costed. Ruled out (refer to Section 2.2)
Construction of another quay. Option 2A £21m New jetty to South of existing quay for S-Type vessels Option 2B £17.5m New jetty to South of existing quay for F-Type vessels Option 3 Not costed. Ruled out (refer to Section 2.2)
Option 1C is the preferred option.
2.2Summarise the costs and benefits and advantages and disadvantages of the options
The costs are listed in Section 2.1
Advantages Disadvantages Extend New Quay Good site information Difficulty of maintaining operations during (Options 1A, 1B, 1C) available. construction. Low risk of objections More difficult for PS Waverley to use old quay. Extend New Quay by Less costly No increase in working, laydown, or storage provision of berthing areas. dolphins (Option 1D) Cranes may only be able to reach one end of vessel. Extend New Quay by Minimise quay extension Scottish Water tunnel and close proximity to reconfiguring slipway buildings and ferry terminal likely to pose (Option 1E) unsurmountable difficulties. New Build Jetty No interference with port High ground risk due to lack of site (Options 2A, 2B) operations. investigation data. Avoids restrictions Possible locations have more difficult road associated with existing access. quay. Likely to attract planning objections. Longer timescale due to need for more extensive site investigation and planning. Develop NATO Jetty Available water depth. Highly unlikely that jetty can take loadings. (Option 3) Industrial operations Jetty too narrow for cranes and vehicles. more remote from town. Higher risk due to lack of site investigation data. Long and expensive road access is required.
3 Commercial aspects: the financial case : 3.1 Outline of the proposed procurement and approach and the rationale for that approach
Design will be done by a combination of in-house and external consultants. This will allow our local engineering knowledge to be supported by the resources and expertise of appropriate consultants and will facilitate greater flexibility.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.