PIERS AND HARBOURS MARINE ASSET MANAGEMENT PLAN - WORKS UPDATE

Noted Committee 2 papers

AI summaryArgyll and Bute Harbour Board noted progress on marine capital projects including Craignure ferry terminal, Iona breakwater, Fionnphort and Gigha upgrades, Easdale and Luing study, and a new Jura ferry, plus £377,105 in additional 2025/26 maintenance costs.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCovered Craignure, SVRP, Port Askaig, Easdale, Luing, Jura
Money£377,105 final additional maintenance 2025/26Plus multiple capital allocations across the Marine Asset Management Plan
What happens nextNot stated
Who it affectsIsland communities and CalMac ferry usersAlso fishermen, importers, exporters, wind farm and cruise firms

What was decided

The Harbour Board noted the updates on capital works being progressed within the Marine Asset Management Plan. Report 2.1

The Board received the officer response to its March 2026 motion on additional maintenance costs in 2025/26, with final outturn of £377,105. Report 3.6

Status updates were noted for Craignure (Green), Iona breakwater (Green), Fionnphort (Red), Gigha (Amber) and Easdale and Luing (Green). Report 3.4, P8, P9, P10, 3.7

Why

The Marine Asset Management Plan sets out programmed capital works to develop and upgrade marine infrastructure over five years, with many projects supporting CalMac services ahead of new vessels. Report 3.1, 3.4, 3.5

Funding mainly comes from Prudential Borrowing repaid via major port fees, with grants sought from Crown Estate Scotland and Transport Scotland; all projects go through competitive tendering. Report 3.1

The additional maintenance response was prepared to comply with a Notice of Motion approved at the Harbour Board meeting on 19 March 2026. Report 3.6

What happens next

Officers expect shortly to appoint a preferred Management and Development Consultant for Craignure to progress the Final Business Case, RIBA Stage 3 design, and licensing work. Report 3.4

Award of the Jura ferry vessel concept design contract is due shortly following tender evaluation. Report 3.8

Public engagement events are scheduled for Easdale on 29 September 2026 and Luing on 30 September 2026, with further EIA screening and consent work to follow at Fionnphort and Gigha. Report 3.7, P9, P10

The money

  • £2.85m Craignure Terminal 2026/27 allocation for Final Business Case and design Report 3.4
  • £47.9m Craignure construction project current allocation Report 3.4
  • £100 million Craignure long term estimate of construction costs Report 3.4
  • £7.8m Iona breakwater 26/27 allocation for remaining construction Report P8
  • £540k Fionnphort 2026/27 allocation for design and EIA works Report P9
  • £20m Fionnphort future provision for SVRP overnight berth and charging Report P9
  • £600k Gigha 2026/27 allocation for design and EIA works Report P10
  • £11m Gigha approximate future provision for construction Report P10
  • £90k Easdale and Luing Strategic Outline Case, via Crown Estate funding Report 3.7
  • £5.6m New Jura Ferry concept design, Transport Scotland funding 2026/27 Report 3.8
  • £14.m New Jura Ferry, Transport Scotland funding 2027/28 (as written) Report 3.8
  • £405,000 Initial February 2026 forecast of additional 2025/26 maintenance Report 3.6
  • £305,000 Revised March 2026 forecast of additional 2025/26 maintenance Report 3.6
  • £377,105 Final outturn additional maintenance expenditure 2025/26 Report 3.6
  • c.£88k Rothesay Harbour dive survey, January storm damage Report 3.6
  • c£63k Craignure urgent fender repair, allision damage Report 3.6
  • c£182k Two Linkspan emergency call out repairs Report 3.6

Options considered

  • Chosen: Note the Marine Asset Management Plan works update. Board recommendation to note capital works progress Report 2.1
  • Chosen: Receive the response on 2025/26 additional maintenance. Required by Notice of Motion at 19 March 2026 Harbour Board meeting Report 3.6
  • Rejected: Source shore power at Craignure before 2034. Network operator advised delivery is unlikely prior to 2034 due to competing SSEN capital projects Report 3.4

Implications

  • Financial: Increases to fees and charges are required to ensure income is sufficient to maintain and develop marine assets.
  • Risk: Additional 2025/26 maintenance was largely reactive, driven by weather events, asset failures and incidents; above inflation fee rises may deter harbour users and new business. Report P12, P13, P17
  • Other: Fionnphort project is Red status due to potential licence issue risk; Gigha is Amber pending a more detailed cost estimate and successful Gateway Review. Report P9, P10
  • Other: The works are of particular importance to island communities for lifeline connectivity, access to services and economic activity; future fee and delivery decisions will need to consider affordability and impacts on residents, businesses and visitors.
  • Other: Children's Rights and Wellbeing: completed works will support improved accessibility and service reliability, benefiting children's access to schools and wider activities.
  • Climate: No direct climate change impacts from this report; due regard will be given to climate change considerations as projects progress. Report 5.7

Who and where

  • Island communities served by Mull, Iona, Fionnphort, Gigha, Easdale, Luing and Jura ferry routes Report 3.4, 3.5, 3.7, 3.8
  • CalMac Ferry Limited services and CMAL vessel replacement programme Report 3.1, 3.5
  • Fishermen, bulk importers, timber exporters, wind farm developers and cruise companies using harbour facilities
  • Bidders and suppliers participating in competitive tenders for marine capital works Report 3.4, 3.8

Timeline

  • January 2026: Storm damage at Rothesay Harbour led to dive survey costs of c.£88k Report 3.6
  • 19 February 2026: Policy and Resources Committee considered Financial Monitoring Overview with £405,000 forecast additional maintenance Report 3.6
  • 19 March 2026: Harbour Board approved Notice of Motion requiring report on 2025/26 additional maintenance Report 3.6
  • 21 to 22 May 2026: Fionnphort Pre-Application Consultation events attended by over 60 people Report P9
  • June and July 2026: Resident surveys for Easdale and Luing study: 95 responses from Luing and 18 from Easdale Report 3.7
  • 29 September 2026: Public engagement event scheduled for Easdale Report 3.7
  • 30 September 2026: Public engagement event scheduled for Luing Report 3.7
  • 2026/27: Capital allocations drawn down: £2.85m Craignure, £7.8m Iona, £540k Fionnphort, £600k Gigha, £90k Easdale and Luing, £5.6m Jura Report 3.4, P8, P9, P10, 3.7, 3.8
  • 2027/28: Further £14.m Transport Scotland funding allocated to Jura ferry project Report 3.8
  • From 2028 onwards: First phase Small Vessel Replacement Programme vessels expected to be introduced on Iona, Fionnphort, Gigha and Tayinloan routes Report 3.5
  • Prior to 2034: SSEN shore power delivery at Craignure unlikely to be achievable due to competing capital projects Report 3.4

Plain English for the jargon

  • MAMP: Marine Asset Management Plan, the council's five year programme of capital works for marine infrastructure
  • SVRP: Small Vessel Replacement Programme run by Transport Scotland and CMAL to replace ageing ferries with new, initially all electric vessels
  • CFL: CalMac Ferry Limited, the ferry operator
  • CMAL: Caledonian Maritime Assets Limited, owner of ferries and port infrastructure
  • MDC: Management and Development Consultant being procured for Craignure Terminal
  • FBC: Final Business Case, the stage the MDC will progress the Craignure project to
  • RIBA Stage 3: Royal Institute of British Architects design stage 3, the level of design the Craignure MDC will advance to
  • PAC: Pre-Application Consultation held at Fionnphort on 21 to 22 May 2026
  • EIA: Environmental Impact Assessment screening work underway at Fionnphort and Gigha
  • RET: Road Equivalent Tariff, the ferry fares policy that may be reviewed
  • SSEN: Scottish and Southern Electricity Networks, the electricity network operator for Craignure shore power
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

Decision The Argyll and Bute Harbour Board noted the updates on capital works currently being progressed within the Marine Asset Management Plan. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services dated August 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Argyll and Bute Harbour Board, 8 pages

Recommendations

2.1Members are asked to consider and note the updates on capital works currently being progressed within the Marine Asset Management Plan.

3.0DETAIL

3.1The Marine Asset Management Plan (MAMP) outlines the Council’s programmed capital works to develop and upgrade marine infrastructure across Argyll and Bute. The plan provides cost estimates for the next five years while remaining flexible to respond to changing priorities, design developments, construction methods, and market conditions. A significant number of projects focus on renewing or adapting infrastructure to support CalMac Ferry Limited (CFL) services ahead of the arrival of new vessels. 3.2 Funding is primarily sourced through Prudential Borrowing, repaid via fees from major ports, with additional grants actively pursued from organisations such as Crown Estate Scotland and Transport Scotland. All projects undergo competitive tendering to secure value for money and high quality delivery. They are regularly monitored and re-forecast to manage risk, maintain progress, and ensure budgets are adjusted appropriately. 3.3 Alongside our maintenance, servicing and conservancy works, Marine Operations are presently engaged in several long, and shorter-term projects across Argyll & Bute which include:

• Craignure – New Ferry Terminal; • SVRP Projects which include Iona/Fionnphort and Gigha/Tayinloan • Port Askaig – Enabling works for new CalMac vessel; • Easdale and Luing Strategic Outline Case • New Jura Ferry Funding

3.4Craignure Terminal Project Overview The Craignure Ferry Terminal project will replace ageing infrastructure and provide a future-proofed terminal capable of accommodating new and existing ferry vessels serving Mull. The project aims to improve service resilience, reduce weather-related disruption, increase marshalling capacity and support long-term island connectivity Latest Update The procurement process for the Management and Development Consultant (MDC) has progressed, with tenders currently under clarification with bidders. Officers are working through these queries, and appointment of a preferred supplier is anticipated shortly. While this stage is taking slightly longer than initially expected, this reflects the need to fully explore and respond to clarifications across a number of competitive bids, ensuring the Council secures the most economically advantageous tender for the full scope of works. Once appointed, the MDC will be responsible for progressing the project to Final Business Case (FBC), advancing the design to RIBA Stage 3, and initiating the licenses, consents and permissions required to support the construction phase. In parallel, initial discussions have commenced with the electricity network operator regarding the provision of shore power infrastructure to support the New Mull Vessels. Initial quotations have been received; however, we have been advised that, due to competing SSEN capital projects, delivery is unlikely to be achievable prior to 2034. Officers will continue to explore options in collaboration with Transport Scotland and CMAL. Marine Asset Management Plan Reference: 2026/27: £2.85m allocated for Final Business Case and design development, informing the estimated future construction programme. In total £47.9m is currently allocated to the construction project with the long term estimate of Construction Costs to be £100 million. MAMP status: Green

Further Information Craignure Ferry Terminal Project | Argyll and Bute Council

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Simplified MAMP September 26Appendix 1 2 pages Download
PDF
PIERS AND HARBOURS MARINE ASSET MANAGEMENT PLAN: WORKS UPDATEReport 8 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 11 attended
JP
Julieann PenmanSecretary, expected
KM
Katie McKenzieSecretary, expected
JA
Councillor John ArmourVice-Chair, expected
GB
Councillor Gordon BlairMember, expected
MC
Councillor Maurice CorryMember, expected
AK
Councillor Andrew KainMember, expected
LM
Councillor Liz McCabeMember, expected
DM
Councillor Dougie McFadzeanMember, expected
RM
Councillor Ross MorelandChair, expected
AV
Councillor Andrew VennardMember, expected
HM
Hazel MacInnesSecretary, expected

On this subject at Argyll and Bute

Search all
  1. PIERS AND HARBOURS MARINE ASSET MANAGEMENT PLAN - WORKS UPDATEThis decision
  2. Piers and Harbours - Marine Works UpdateNoted
  3. Piers and harbours - performance reportingAgreed
  4. Piers and harbours marine asset management plan fees and charges 2027 / 2028Noted
  5. Piers and Harbours - Marine Works UpdateAgreed
  6. Piers and harbours marine asset management plan - works updateNoted

More from Argyll and Bute Argyll and Bute Harbour Board

All decisions
MeetingDecisionOutcome
9 Oct 2026 Piers and harbours - performance reportingDecision The Argyll and Bute Harbour Board – 1. agreed the proposed approach and structure to annual performance repo... Agreed Open
9 Oct 2026 Carradale harbourDecision The Argyll and Bute Harbour Board noted the content of the report. (Reference: Report by Executive Director ... Noted Open
9 Oct 2026 Piers and harbours marine asset management plan fees and charges 2027 / 2028Decision The Argyll and Bute Harbour Board – 1. noted that officers were of the view that a review is required to con... Noted Open
9 Oct 2026 Argyll and bute harbour board workplanDecision The Argyll and Bute Harbour Board noted the content of the workplan. (Reference: Argyll and Bute Harbour Boa... Noted Open
19 Mar 2026 Piers and harbours marine asset management plan - works updateDecision The Argyll and Bute Harbour Board noted the updates on capital works currently being progressed within the M... Noted Open