PIERS AND HARBOURS MARINE ASSET MANAGEMENT PLAN - WORKS UPDATE
NotedCommittee2 papers
AI summaryArgyll and Bute Harbour Board noted progress on marine capital projects including Craignure ferry terminal, Iona breakwater, Fionnphort and Gigha upgrades, Easdale and Luing study, and a new Jura ferry, plus £377,105 in additional 2025/26 maintenance costs.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCovered Craignure, SVRP, Port Askaig, Easdale, Luing, Jura
Money£377,105 final additional maintenance 2025/26Plus multiple capital allocations across the Marine Asset Management Plan
What happens nextNot stated
Who it affectsIsland communities and CalMac ferry usersAlso fishermen, importers, exporters, wind farm and cruise firms
What was decided
The Harbour Board noted the updates on capital works being progressed within the Marine Asset Management Plan. Report 2.1
The Board received the officer response to its March 2026 motion on additional maintenance costs in 2025/26, with final outturn of £377,105. Report 3.6
Status updates were noted for Craignure (Green), Iona breakwater (Green), Fionnphort (Red), Gigha (Amber) and Easdale and Luing (Green). Report 3.4, P8, P9, P10, 3.7
Why
The Marine Asset Management Plan sets out programmed capital works to develop and upgrade marine infrastructure over five years, with many projects supporting CalMac services ahead of new vessels. Report 3.1, 3.4, 3.5
Funding mainly comes from Prudential Borrowing repaid via major port fees, with grants sought from Crown Estate Scotland and Transport Scotland; all projects go through competitive tendering. Report 3.1
The additional maintenance response was prepared to comply with a Notice of Motion approved at the Harbour Board meeting on 19 March 2026. Report 3.6
What happens next
Officers expect shortly to appoint a preferred Management and Development Consultant for Craignure to progress the Final Business Case, RIBA Stage 3 design, and licensing work. Report 3.4
Award of the Jura ferry vessel concept design contract is due shortly following tender evaluation. Report 3.8
Public engagement events are scheduled for Easdale on 29 September 2026 and Luing on 30 September 2026, with further EIA screening and consent work to follow at Fionnphort and Gigha. Report 3.7, P9, P10
The money
£2.85m Craignure Terminal 2026/27 allocation for Final Business Case and design Report 3.4
£47.9m Craignure construction project current allocation Report 3.4
£100 million Craignure long term estimate of construction costs Report 3.4
£7.8m Iona breakwater 26/27 allocation for remaining construction Report P8
£540k Fionnphort 2026/27 allocation for design and EIA works Report P9
£20m Fionnphort future provision for SVRP overnight berth and charging Report P9
£600k Gigha 2026/27 allocation for design and EIA works Report P10
£11m Gigha approximate future provision for construction Report P10
£90k Easdale and Luing Strategic Outline Case, via Crown Estate funding Report 3.7
£5.6m New Jura Ferry concept design, Transport Scotland funding 2026/27 Report 3.8
£14.m New Jura Ferry, Transport Scotland funding 2027/28 (as written) Report 3.8
£405,000 Initial February 2026 forecast of additional 2025/26 maintenance Report 3.6
£305,000 Revised March 2026 forecast of additional 2025/26 maintenance Report 3.6
£377,105 Final outturn additional maintenance expenditure 2025/26 Report 3.6
c.£88k Rothesay Harbour dive survey, January storm damage Report 3.6
c£182k Two Linkspan emergency call out repairs Report 3.6
Options considered
Chosen: Note the Marine Asset Management Plan works update. Board recommendation to note capital works progress Report 2.1
Chosen: Receive the response on 2025/26 additional maintenance. Required by Notice of Motion at 19 March 2026 Harbour Board meeting Report 3.6
Rejected: Source shore power at Craignure before 2034. Network operator advised delivery is unlikely prior to 2034 due to competing SSEN capital projects Report 3.4
Implications
Financial: Increases to fees and charges are required to ensure income is sufficient to maintain and develop marine assets.
Risk: Additional 2025/26 maintenance was largely reactive, driven by weather events, asset failures and incidents; above inflation fee rises may deter harbour users and new business. Report P12, P13, P17
Other: Fionnphort project is Red status due to potential licence issue risk; Gigha is Amber pending a more detailed cost estimate and successful Gateway Review. Report P9, P10
Other: The works are of particular importance to island communities for lifeline connectivity, access to services and economic activity; future fee and delivery decisions will need to consider affordability and impacts on residents, businesses and visitors.
Other: Children's Rights and Wellbeing: completed works will support improved accessibility and service reliability, benefiting children's access to schools and wider activities.
Climate: No direct climate change impacts from this report; due regard will be given to climate change considerations as projects progress. Report 5.7
Who and where
Island communities served by Mull, Iona, Fionnphort, Gigha, Easdale, Luing and Jura ferry routes Report 3.4, 3.5, 3.7, 3.8
2027/28: Further £14.m Transport Scotland funding allocated to Jura ferry project Report 3.8
From 2028 onwards: First phase Small Vessel Replacement Programme vessels expected to be introduced on Iona, Fionnphort, Gigha and Tayinloan routes Report 3.5
Prior to 2034: SSEN shore power delivery at Craignure unlikely to be achievable due to competing capital projects Report 3.4
Plain English for the jargon
MAMP: Marine Asset Management Plan, the council's five year programme of capital works for marine infrastructure
SVRP: Small Vessel Replacement Programme run by Transport Scotland and CMAL to replace ageing ferries with new, initially all electric vessels
CFL: CalMac Ferry Limited, the ferry operator
CMAL: Caledonian Maritime Assets Limited, owner of ferries and port infrastructure
MDC: Management and Development Consultant being procured for Craignure Terminal
FBC: Final Business Case, the stage the MDC will progress the Craignure project to
RIBA Stage 3: Royal Institute of British Architects design stage 3, the level of design the Craignure MDC will advance to
PAC: Pre-Application Consultation held at Fionnphort on 21 to 22 May 2026
EIA: Environmental Impact Assessment screening work underway at Fionnphort and Gigha
RET: Road Equivalent Tariff, the ferry fares policy that may be reviewed
SSEN: Scottish and Southern Electricity Networks, the electricity network operator for Craignure shore power
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4
Resolved
Decision The Argyll and Bute Harbour Board noted the updates on capital works currently being progressed within the Marine Asset Management Plan. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services dated August 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
2.1Members are asked to consider and note the updates on capital works currently being progressed within the Marine Asset Management Plan.
3.0DETAIL
3.1The Marine Asset Management Plan (MAMP) outlines the Council’s programmed capital works to develop and upgrade marine infrastructure across Argyll and Bute. The plan provides cost estimates for the next five years while remaining flexible to respond to changing priorities, design developments, construction methods, and market conditions. A significant number of projects focus on renewing or adapting infrastructure to support CalMac Ferry Limited (CFL) services ahead of the arrival of new vessels. 3.2 Funding is primarily sourced through Prudential Borrowing, repaid via fees from major ports, with additional grants actively pursued from organisations such as Crown Estate Scotland and Transport Scotland. All projects undergo competitive tendering to secure value for money and high quality delivery. They are regularly monitored and re-forecast to manage risk, maintain progress, and ensure budgets are adjusted appropriately. 3.3 Alongside our maintenance, servicing and conservancy works, Marine Operations are presently engaged in several long, and shorter-term projects across Argyll & Bute which include:
• Craignure – New Ferry Terminal; • SVRP Projects which include Iona/Fionnphort and Gigha/Tayinloan • Port Askaig – Enabling works for new CalMac vessel; • Easdale and Luing Strategic Outline Case • New Jura Ferry Funding
3.4Craignure Terminal Project Overview The Craignure Ferry Terminal project will replace ageing infrastructure and provide a future-proofed terminal capable of accommodating new and existing ferry vessels serving Mull. The project aims to improve service resilience, reduce weather-related disruption, increase marshalling capacity and support long-term island connectivity Latest Update The procurement process for the Management and Development Consultant (MDC) has progressed, with tenders currently under clarification with bidders. Officers are working through these queries, and appointment of a preferred supplier is anticipated shortly. While this stage is taking slightly longer than initially expected, this reflects the need to fully explore and respond to clarifications across a number of competitive bids, ensuring the Council secures the most economically advantageous tender for the full scope of works. Once appointed, the MDC will be responsible for progressing the project to Final Business Case (FBC), advancing the design to RIBA Stage 3, and initiating the licenses, consents and permissions required to support the construction phase. In parallel, initial discussions have commenced with the electricity network operator regarding the provision of shore power infrastructure to support the New Mull Vessels. Initial quotations have been received; however, we have been advised that, due to competing SSEN capital projects, delivery is unlikely to be achievable prior to 2034. Officers will continue to explore options in collaboration with Transport Scotland and CMAL. Marine Asset Management Plan Reference: 2026/27: £2.85m allocated for Final Business Case and design development, informing the estimated future construction programme. In total £47.9m is currently allocated to the construction project with the long term estimate of Construction Costs to be £100 million. MAMP status: Green
Further Information Craignure Ferry Terminal Project | Argyll and Bute Council
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Argyll and bute harbour board workplanDecision The Argyll and Bute Harbour Board noted the content of the workplan. (Reference: Argyll and Bute Harbour Boa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.