Decision 1. Noted the final partner contributions that are required to support the delivery of the Mull Progressive Care Centre; and 2. Approved the final contribution of £845,844 inclusive of VAT from the Council’s Social Work Capital Programme together with £356,000 from the Strategic Housing Fund. (Reference: Report by Director of Community Services dated 8 December 2009, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The Mull and Iona Progressive Care Centre has been planned to replace the outdated Dunaros Residential Care Centre and Salen Hospital with progressive care housing and a purpose designed hospital facility.
1.2This paper outlines final recommendations relating to the Council’s financial contribution in support of the project.
Recommendation
2.1Members are asked to: (a) Note the final partner contributions that are required to support the delivery of the Mull Progressive Care Centre. (b) Approve the final contribution of £845,444 inclusive of VAT from the Council’s Social Work Capital Programme together with £356,000 from the Strategic Housing Fund.
3. DETAIL
3.1Background: The concept for the Mull and Iona Progressive Care Centre has been established as a result of partnership working between Argyll and Bute Council, NHS Highland, the Scottish Government’s Housing Investment Division, West Highland Housing Association and the Mull and Iona Progressive Care Centre Company.
3.2Ultimately, the facility will replace the outdated Dunaros Residential Care Centre and Salen Hospital. It will offer 12 individual supported tenancies and a modern hospital together with a range of other health facilities and related staff housing to ease recruitment. This compares to the 8 residential places that are currently available at Dunaros.
3.3Previous financial commitments: Members are reminded that at the meeting of 20 November 2008, the Executive agreed to approve in principle the funding contribution of £850,200 inclusive of VAT from the Council’s Social Work Capital Programme. This decision was taken on the understanding that our development partners were making appropriate funding commitments to enable the project to progress through planning and building warrant stages. This provision also allowed the project manager to conclude tender negotiations via the partnership contract with M & K MacLeod and TSL Contractors.
3.4Subsequently, on 16 April 2009, the Council agreed to provisionally allocate £356,000 from the Council’s Strategic Housing Fund in support of the housing component of the project which had an overall cost plan value of £2.837m.
3.5Project Board meeting: Following the conclusion of negotiations with the contractors, the Project Board met on 8 December 2009 to receive the formal tender evaluation report. Arising from this, all partners have agreed to move forward to seek final financial approvals to enable acceptance of the tender at the value of £8,050,340 net of VAT. Overall partner contributions arising from this are set out in the annex to this paper and in this regard, Members are asked to specifically note that the contributions expected from the Council remain at the levels previously approved in principle. In the circumstances, I recommend that the Council should now formally agree to support the project on this basis.
3.6Approval process: The Scottish Government’s Housing Investment Division has already agreed to the cost plan for the housing component thus releasing the housing association grant contribution. Colleagues in NHS Highland have also now agreed to move forward with their final approval process which should culminate with a report to their board meeting on 2 February 2010. In addition, the Mull and Iona Progressive Care Company has already agreed to their contribution and contingency arrangements have been developed should the envisaged grants for biomass, energy supply and the provision of the sprinkler system not materialise.
3.7Assuming that all necessary approvals are granted, the design and build contract will be accepted prior to the end of February 2010 with the overall project being managed by consultants engaged on behalf of the partnership via West Highland Housing Association. A site start of late March or early April 2010 should then follow with an overall contract period of 18 months anticipated.
4. CONCLUSION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.