Decision The Committee:- i. Noted the contents of the report by the Principal Engineer. ii. Agreed to invite the appropriate person from Morrison Supermarket to the February Business Day to discuss issues relating to the Flood Prevention Scheme. (Reference: Report by the Principal Engineer dated 15 th January 2010 – submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
The purpose of this report is to advise the Members of the status of the project.
Recommendations
That Members note the report.
3. DETAILS
Following on from the December 2009 Area Committee meeting, local members and officers met to discuss the project. The outcome of that meeting was to re- programme the scheme, assuming that access to the necessary ground will be achieved by voluntary agreement rather than through the powers obtained by the lengthy process contained in the Flood Prevention Act.
Accordingly a site investigation tender has been issued to obtain information on the ground below John Street. This is expected to be on site in February.
The tenders for the main works (retaining walls and bunds upstream of and at the supermarket, the draw-off chamber/weir at the carpark and the completion of the flood relief pipe in John Street) are now programmed for issue in spring with expected start on site in the summer. Works are likely to take a year and when completed, will deal with the majority of the flows in the burn up to the 1 in 100 year plus climate change flood event. Consideration can then be given as to whether any works would be required in future, downstream of the supermarket.
Estates colleagues have been in contact with the supermarket to set up a meeting to discuss compensation for the loss of car parking spaces during the works. The supermarket’s approach to this is absolutely vital to progress with the scheme for the programme above.
The project will be taken through the Outline Business Case procedure.
4. IMPLICATIONS
4.1Policy None
4.2Financial All construction costs have a financial risk 1 4.3 Personnel Significant officer time is required to develop the project
4.4Equalities Impact Not required Assessment
4.5Legal The current programme assumes that access to the ground to undertake the project will secured by voluntary means. If this is not successful, the scheme will need to be advertised through the Flood Prevention Act.
For further information, please contact
Name Arthur McCulloch Job Title Principal Engineer Date 15 January 2010
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with...
Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.