Decision Noted the savings recognised by the Council from procurement over previous years and the significant potential for procurement activity to have a positive effect on delivery of Council services from reducing budgets. (Reference: Report by Exchequer Services Manager dated 17 February 2010, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1There has been an awareness across the Council of the potential to achieve significant savings through Procurement since the Council joined the eProcurement Scotland programme in early 2004 and began to seriously engage with the public sector procurement agenda.
1.2Until 2009 however and the implementation of the Process for Change programme there has been limited investment in purchasing capability by the Council and this has restricted the ability to deliver savings from Council contracts. Up until now savings have been delivered almost exclusively from collaborative contracts let by other organisations on the Council’s behalf
Recommendations
2.1That the Committee note the savings recognised by the Council from procurement over previous years and the significant potential for procurement activity to have a positive effect on the delivery of Council services from reducing budgets.
3. SAVINGS METHODOLOGY
3.1The savings methodology applied to date has been calculated on a relatively simple basis. Price savings have only been applied where a clear baseline could be established from a previous price, either contracted or commonly purchased. The previous arrangement is the baseline and the savings are calculated for the length of the new contract, which becomes the new baseline on expiry.
3.2Savings generated through Process for Change will be reflected directly in Council budgets and therefore a more rigorous methodology has been developed based on the benefits realisation methodology used for projects
3.3Although cost reduction will continue to be a major objective when new contracts are being let, the new sourcing strategies will use a balanced
Page 1 of 3 scorecard approach to objectives, including Enhanced Service Delivery, Internal Process Improvements and Sustainability with Cost.
4. HISTORICAL SAVINGS FIGURES
4.1The Council has recorded cashable savings from procurement for a number of years, as follows;
CONTRACT SAVINGS SAVINGS SAVINGS 2007/08 2008/09 2009/10 Stationery and Office Supplies 60,000 60,000 0 Light Vehicle Contract 37,500 50,000 62,500 Heavy Vehicle Contract 35,000 35,000 35,000 Microsoft Enterprise Licences 24,000 24,000 24,000 PCs and Laptops 71,000 120,000 0 Protective Clothing 50,000 Advertising 25,000 TOTAL 227,500 289,000 196,500
While almost all of the above contracts have been let by organisations on the Council’s behalf, the Council have been instrumental in bringing many of the contracts to fruition. The light vehicle contract for example, is now used across Scotland but the concept was developed from an initial collaboration between Argyll and Bute, Renfrewshire and North Lanarkshire Councils.
The Council has also recorded non – cashable or time releasing savings from the use of the Pecos e-procurement system for purchase to pay. The savings are calculated on a transaction basis, obtained from time studies on a range of paper and e-transactions carried out by the Scottish Procurement Directorate across Argyll and Bute. The calculated saving per transaction is £3.40. The savings, over the same years are as follows;
2009/2010 £107,525 (estimated to end of March) 2008/2009 £107,341 2007/2008 £56,814
5. PRESENT AND FUTURE SAVINGS
5.1The Council now has a sufficient complement of purchasing officers in place who, while still relatively inexperienced, will be able to deliver significant cost savings through better procurement practice and increasing the overall level of expenditure that is carried out under formal contract.
Page 2 of 3 5.2 During 2010/11 it is expected that savings will be generated from a range of contracts covering but not restricted to postal services, car leasing, temporary and agency staff contracts, property maintenance and
Alan Brough Exchequer Services Manager 17th February 2010.
Page 3 of 3
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Internal audit summary of activitiesDecision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March ...
Internal audit annual plan 2017 - 2018Decision The Committee agreed and approved the Internal Audit Annual Plan 2017/18 (Reference: Report by Chief Interna...
External audit plan 2017 - 2018Decision The Committee noted the contents of the report. (Reference: Report by Audit Scotland dated March 2017, submi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.