Decision Members decided that the following components should be included in the Full Business Case for the first phase of the Dunoon CHORD Project. i. The re-development/refurbishment of the Queens Hall. ii. Road re-alignment. iii. Environmental improvements. iv. Harbourmaster’s building. Members decided there was insufficient evidence and justification for the following components to be included in the Full Business Case for the first phase of the Dunoon CHORD Project. i. The pier demolition and new harbour and transit marina. ii. The land reclamation with new hotel and conference. Members further agreed that given the need for effective decisions to be made about the long term future of Dunoon Pier, a strategy for the future use of the pier, including the possibility of creating 30 transit berths, must also be developed, con-currently with the Full Business Case. Councillor Marshall asked that £20,000 be given to the Dunoon & Cowal Business Association to assist them in starting their BIDS scheme, advising that point 3.5 of the report states that the CHORD project objectives are to act as an enable for private sector investment in the waterfront area and town centre. Councillors McNaughton and Simon advised that they did not have enough information to make a decision on this request, and asked for a further paper on the matter.
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Dunoon Waterfront Draft Implementation Plan March 2010
APPENDICES Appendices
Appendix 1 Implementation Plan Team Implementation Plan Brief Implementation Plan Methodology Appendix 2 Dunoon Waterfront Options – Questionnaire and Responses Marine Gateway – Questionnaire and Responses Appendix 3 Summary Reference Technical Documents and Reports Appendix 4 Stakeholder Consultees and Meetings Appendix 5 ARUP Dunoon CHORD Maritime Engineering Appraisal Client Scheme Draft 1 20 Jan 2010. Appendix 6 Arup 1st Stage Structural Survey proposal Appendix 7 Tourism Resources Consultants - Dunoon CHORD Hotel and Marina Paper February 2010 Appendix 8 Summary SWOT Tables for each Component Appendix 1
1A Implementation Plan Team 1B Implementation Plan Brief 1C Implementation Plan Methodology 1A Implementation Plan Team
Anderson Bell Christie Karen Anderson - Team Leader (Partner) Rowena Statt (Associate) Laura Coogan (Architectural/Urban Design Assistant) Mike Hyatt (Landscape Architect)
Arup Alan Richmond - Lead Engineer (Director) Gordon Barbour (Associate) Clon Ulrick - Maritime Engineering (Associate Director ) Craig Latto - Transport Planner (Associate)
Brown and Wallace John Edwards - Quantity Surveyor (Associate Partner)
Tourism Resource Consultancy David Bullough (Director)
1B Implementation Plan Brief The anticipated scope of the work required to carry out the Implementation Plan was set out in Argyll and Bute Council’s Tender for Professional Services (return date 24 September 2009). In summary specific work required was stipulated:
x Consider the project, as laid out in the approved option, and its individual components – identify relevant strategies covering the development area, complementary local projects and initiatives, planning decisions, key stakeholders, including Historic Scotland regarding the listed pier structure, landownership, funding issues, priorities and actions for partners.
x Due to the scale and longer-term nature of this project, it will be necessary to break the components of the project down into three clearly defined and deliverable phases with phase one being the focus for the Council’s initial strategic investment. This will result in the development of a clear delivery plan, including a spatial plan, relating to the physical components of the Dunoon Waterfront project each of which will stand alone in their own right.
x The first phase of development should be a solid platform on which to build the subsequent longer-term phases of the wider project and should act as a significant catalyst for the economic regeneration of Dunoon.
x Identify the interrelationships between the different components and phases of the project, the importance of these including timeframes and financial implications.
x Investigate the different options associated with each of the components and map out the implications arising from each of these options and the impact they will have on the overall project. External factors will require to be considered such as the EC investigation into the Dunoon – Gourock ferry service and the outcome of a recent Town Centre Regeneration Fund (TCRF) bid.
x Set out the processes, approaches and partnerships to deliver the project over its lifetime covering all three phases (with particular emphasis on phase one), including: potential private partners, the financial resources required both public and private and the methods for evaluating success.
x If there is strong and compelling evidence to demonstrate that aspects of the delivery of the approved option are not considered feasible due to, e.g. market conditions, technical feasibility, planning, listed building issues or funding, there will be a need to consider the project and its component parts and identify an option(s) that would be feasible and would achieve the stated CHORD objectives.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.