Dunoon CHORD Project Board, Thursday 29 April 2010 at 2.00pm

Proposed BIDS Scheme for Dunoon Town Centre

Agreed Committee 1 paper

Dunoon CHORD Project Board agreed this item on Thursday 29 April 2010. Below is the council's own wording, with the papers it was decided on.

Item3

Resolved

Decision The Dunoon CHORD Project Board agreed:- i. To recommend that the CHORD Programme Management Board agree to the request from the Dunoon & Cowal Business Association for £20k to be released from CHORD Revenue funds, to be used for the development costs of the Association in proceeding to create a Business Improvement District in Scotland (BIDS) in Dunoon Town Centre, or if agreed in a wider area around town; that such approval, if given, be conditional on the Association successfully attracting match funding for the process from Scottish Government, LEADER and Highland and Islands Enterprise, and that such approval only be given once a fully costed business case for the process is submitted by Dunoon & Cowal Business Association and agreed by the CHORD Programme Management Board. ii. To request that the Council consider on a corporate basis the strategic direction and consideration of Business Improvement Districts in Scotland or similar schemes in order to ensure a consistent risk based approach to supporting such schemes as they are developed across Argyll & Bute. On being put to the vote Sandy MacTaggart abstained from voting on point i of the recommendation.
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Dunoon CHORD Project Board

Summary

1.1This report is to advise Members on the request from the Dunoon & Cowal Business Association in assisting them in starting their BIDS scheme.

Recommendations

2.1That the Dunoon CHORD Project Board agree to the request from Dunoon & Cowal Business Association for the sum of £20k from the Dunoon CHORD Project funds to be used for the development cost by the Association of the process to create a Business Improvement District in Scotland (BIDs) in Dunoon town centre or if agreed in a wider area around the town.

Background

3.1Dunoon & Cowal Business Association (D&CBA) wish to create a BID in the Dunoon area. In order to determine the desire for a BIDs in the area the A&CBA require in Phase 1 • Initial discussions with Businesses • Initial discussion with Local Authority • Initial discussion with Police and other organisations • Determine BID project • Determine BID area • Agreement from 5% of BID area businesses to proceed • Application for one off funding of up to £20k from Scot. Govt. and others to develop Phase 2

In Phase 2 D&CBA require to • Develop projects & create business case • Provision of above to BID area business • Consult with BID area business • Ballot BID area business • If the required percentage of businesses agree the BID would then proceed to Phase 3 In Phase 3 a BID Ltd Company would be formed and D&CBA would proceed with projects. Projects must be completed within five years when businesses would again be balloted to determine their desire for a further BID

The estimated cost to reach Phase 3 is £55,500 which would be funded by • Scot Govt. £20k • A&BC CHORD money £20k • Leader Fund £10k • HIE £5.5k

Outlined in appendix 1 below are examples of how BIDs can create employment and strengthen the economic viability of an area and allow business communities to have a strong say in how there own and public monies are spent.

5. IMPLICATIONS

Policy:

Financial: CHORD Budget

Personnel: N/A

Equal Opportunity: N/A

For further information contact: Councillor Marshall Appendix 1

Business Improvement Districts Scotland • A Business led initiative • Businesses working together to provide beneficial improvements • Businesses determining improvement Projects • Businesses controlling expenditures • All businesses contribute and all gain benefit ----------------- A BID is not a substitute for central or local government services, but is a way additional funding can be raised which businesses then decide how to use to strengthen the local business economy.

Benefits a BID can provide

• Increased footfall and consumer spend, as a direct result of an improved trading environment

• Sustained investment over a 5 year period

• Improved leisure facilities, for locals and tourists,

• Increased desire to trade locally due to improved perception of area.

• A strong voice on issues that matter to businesses

• Knowledge that their money is being spent on projects they want Below lets one see how the money would be collected over a five year period and an example of how it might be spent

Example BID Project 1/ Improved Appearance 2/ Safety & security 3/ Focal Awareness 4/ Facility Projects Year 1 Year 2 Year 3 Year 4 Year 5 Total Street Wardens 6,000 6,000 6,600 6,600 7,000 32,200 Shop Frontage Improvement Grants 10,000 10,000 10,000 10,000 10,000 50,000 Additional signage 2,000 2,000 4,000 Leisure facility 50,000 25,000 2,500 2,500 2,500 82,500 Event 5,000 5,000 5,000 5,000 5,000 25,000 1. Brand & Merchandise 5,000 5,000 5,000 5,000 5,000 25,000 Marketing of Businesses 5,000 5,000 5,000 5,000 5,000 25,000 Area 2 projects 23,000 10,000 10,000 10,000 10,000 63,000 Management 18,000 18,000 18,000 18,000 18,000 90,000 Administration 3,000 3,000 3,000 3,000 3,000 15,000 Accountant & Legal fees 5,000 5,000 5,000 5,000 5,000 25,000 Preparation for next BID 10,000 10,000 Contingencies 5% 6,450 4,700 3,600 3,600 3,600 21,950 TOTAL 138,450 98,700 73,700 73,700 84,100 468,650

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Proposed BIDS Scheme for Dunoon Town CentreReport 73 KB DownloadRead as text

At this meeting

Whole meeting
2Minutes of Meeting of 15th April 2010On the agenda
3Proposed BIDS Scheme for Dunoon Town CentreThis decision

Who was there

9 of 10 attended
ND
Nicola DebnamOfficer, present
SM
Shirley MacLeodSecretary, present
SM
Sandy MactaggartOfficer, present
BM
Councillor Bruce MarshallMember, present
AM
Audrey MartinOfficer, apologies
AM
Councillor Alister McAlisterMember, present
SM
Sandra McLindonPublic, present
AM
Councillor Alex McNaughtonMember, present
JM
Councillor James McQueenMember, present
RS
Councillor Ron SimonMember, present

More from Argyll and Bute Dunoon CHORD Project Board

All decisions
MeetingDecisionOutcome
3 Feb 2012 Dunoon Waterfront Highlight / Progress ReportDecision The Board noted the information provided. (Reference: Report by the CHORD Project Manager – submitted) Noted Open
15 Apr 2010 Implementation PlanDecision Members decided that the following components should be included in the Full Business Case for the first pha... Agreed Open
16 Apr 2009 Potential Architectural CompetitionIt was agreed that the Board would not pursue the architectural competition at this stage. Agreed Open
16 Apr 2009 Scottish government town center regeneration fundIt was agreed that Kevin would monitor this funding. Agreed Open
17 Mar 2009 Any Other BusinessDecision The Board agreed:- i. Sandy MacTaggart would liaise with Douglas Hendry to get Turner and Townsend to help p... Agreed Open