Decision The Dunoon CHORD Project Board agreed:- i. To recommend that the CHORD Programme Management Board agree to the request from the Dunoon & Cowal Business Association for £20k to be released from CHORD Revenue funds, to be used for the development costs of the Association in proceeding to create a Business Improvement District in Scotland (BIDS) in Dunoon Town Centre, or if agreed in a wider area around town; that such approval, if given, be conditional on the Association successfully attracting match funding for the process from Scottish Government, LEADER and Highland and Islands Enterprise, and that such approval only be given once a fully costed business case for the process is submitted by Dunoon & Cowal Business Association and agreed by the CHORD Programme Management Board. ii. To request that the Council consider on a corporate basis the strategic direction and consideration of Business Improvement Districts in Scotland or similar schemes in order to ensure a consistent risk based approach to supporting such schemes as they are developed across Argyll & Bute. On being put to the vote Sandy MacTaggart abstained from voting on point i of the recommendation.
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report is to advise Members on the request from the Dunoon & Cowal Business Association in assisting them in starting their BIDS scheme.
Recommendations
2.1That the Dunoon CHORD Project Board agree to the request from Dunoon & Cowal Business Association for the sum of £20k from the Dunoon CHORD Project funds to be used for the development cost by the Association of the process to create a Business Improvement District in Scotland (BIDs) in Dunoon town centre or if agreed in a wider area around the town.
Background
3.1Dunoon & Cowal Business Association (D&CBA) wish to create a BID in the Dunoon area. In order to determine the desire for a BIDs in the area the A&CBA require in Phase 1 • Initial discussions with Businesses • Initial discussion with Local Authority • Initial discussion with Police and other organisations • Determine BID project • Determine BID area • Agreement from 5% of BID area businesses to proceed • Application for one off funding of up to £20k from Scot. Govt. and others to develop Phase 2
In Phase 2 D&CBA require to • Develop projects & create business case • Provision of above to BID area business • Consult with BID area business • Ballot BID area business • If the required percentage of businesses agree the BID would then proceed to Phase 3 In Phase 3 a BID Ltd Company would be formed and D&CBA would proceed with projects. Projects must be completed within five years when businesses would again be balloted to determine their desire for a further BID
The estimated cost to reach Phase 3 is £55,500 which would be funded by • Scot Govt. £20k • A&BC CHORD money £20k • Leader Fund £10k • HIE £5.5k
Outlined in appendix 1 below are examples of how BIDs can create employment and strengthen the economic viability of an area and allow business communities to have a strong say in how there own and public monies are spent.
5. IMPLICATIONS
Policy:
Financial: CHORD Budget
Personnel: N/A
Equal Opportunity: N/A
For further information contact: Councillor Marshall Appendix 1
Business Improvement Districts Scotland • A Business led initiative • Businesses working together to provide beneficial improvements • Businesses determining improvement Projects • Businesses controlling expenditures • All businesses contribute and all gain benefit ----------------- A BID is not a substitute for central or local government services, but is a way additional funding can be raised which businesses then decide how to use to strengthen the local business economy.
Benefits a BID can provide
• Increased footfall and consumer spend, as a direct result of an improved trading environment
• Sustained investment over a 5 year period
• Improved leisure facilities, for locals and tourists,
• Increased desire to trade locally due to improved perception of area.
• A strong voice on issues that matter to businesses
• Knowledge that their money is being spent on projects they want Below lets one see how the money would be collected over a five year period and an example of how it might be spent
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.