Resolved
Decision Noted the revenue budget monitoring report as at December 2011. (Reference: Report by Head of Strategic Finance dated March 2012, submitted) #
Executive noted this item on Thursday 8 March 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision Noted the revenue budget monitoring report as at December 2011. (Reference: Report by Head of Strategic Finance dated March 2012, submitted) #
ARGYLL AND BUTE COUNCIL EXECUTIVE STRATEGIC FINANCE 8 MARCH 2012
REVENUE BUDGET MONITORING REPORT – DECEMBER 2011 CORPORATE OVERVIEW
FORECAST OUTTURN – UNDERSPEND £63,000 This Corporate Overview summarises the revenue budget position of the Council as at 31 December 2011. The overall outturn variance is forecast to be an underspend of £63k based on the December budget monitoring exercise.
1. CURRENT FINANCIAL POSITION
The overall Council financial statements are included as appendices to this report. An overall Objective Summary is included in Appendix 1 and the overall Subjective Summary for the Council is included as Appendix 2.
YEAR TO DATE POSITION
As at the end of December 2011 there is a year to date surplus of £1.609m. The main reason for this within departmental budgets is the profiling of budgets and the timing differences with payments being made.
The graph below shows the expenditure to date against the remaining budget for each Department. This is a high level summary to give an indication of the proportion of controllable budget that each Department has spent to date. The dark shade represents the actual expenditure to date as a percentage of total budget and the lighter area at the top represents the available/remaining budget.
YTD Actual vs Remaining Budget 100% 80% 60% 40% 20% 0% Chief Community Customer Development Other TOTAL Executive's Services Services and Corporate Unit Infrastructure Budgets Services
YTD Actual Remaining Budget
Page 1 of 5 FORECAST OUTTURN POSITION
The current forecast outturn position as at the end of December 2011 is a forecast underspend of £63k. Overall there is a projected underspend of £1,030k within departmental budgets, and an overspend of £967k forecast for non-departmental budgets.
The overspend of £967k outwith departmental budgets is in relation to two issues. As part of the Council’s service review programme the Council will need to provide for the cost of severance. Part of the cost has already been built into the budget but the current estimate requires an increased provision of £1,060k within 2011-12. The Council has received income in respect of the Fleming VAT claims, there has been £338k of one-off income that was not budgeted for. The Council may receive further additional income in respect of outstanding claims but at this point in time we cannot predict which claims will be successful. Of this £338k of income a total of £230k was agreed by Executive on 29 September to be used to support events and festivals and £15k was agreed on 3 November to as a one-off grant for the Waverley vessel, leaving a net position of £93k.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
REVENUE BUDGET MONITORING: DECEMBER 2011Agenda | 821 KB | DownloadRead as text |
Follow Executive at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Apr 2012 | Leader's reportDecision Noted the report. (Reference: Report by Leader of the Council dated April 2012, submitted) | Noted | Open |
| 19 Apr 2012 | EnvironmentDecision Noted the report. (Reference: Report by Spokesperson for Environment dated April 2012, submitted) | Noted | Open |
| 19 Apr 2012 | European affairsDecision Noted the report. (Reference: Report by Spokesperson for European Issues dated April 2012, submitted) | Noted | Open |
| 19 Apr 2012 | Social affairsDecision 1. Noted the report; and 2. Agreed that adoption of the Learning Disability Service Users Conference should ... | Noted | Open |
| 19 Apr 2012 | Education capital programme 2012/13 to 2014/15Decision Approved the proposed projects to invest the additional capital allocation of £2.126m in asset sustainabilit... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.