Resolved
Decision The Committee noted the progress to improve sections of the network. (Reference: Report by the Roads Performance Manager dated 1 st June 2012 – tabled)
Bute and Cowal Area Committee noted this item on Wednesday 6 June 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Committee noted the progress to improve sections of the network. (Reference: Report by the Roads Performance Manager dated 1 st June 2012 – tabled)
CAPITAL RECONSTRUCTION PROGRAMME 2012-13 COWAL APRIL MAY JUNE JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER JANUARY FEBRUARY
WO number Ward Road Location AREA COST Extent Material 2.4.12 9.4.12 16.4.12 23.4.12 30.4.12 7.5.12 14.5.12 21.5.12 28.5.12 4.6.12 11.6.12 18.6.12 25.6.12 2.7.12 9.7.12 16.7.12 23.7.12 30.7.12 6.8.12 13.8.12 20.8.12 27.8.12 3.9.12 10.9.12 17.9.12 24.9.12 1.10.12 8.10.12 15.10.12 22.10.12 29.10.12 5.11.12 12.11.12 19.11.12 26.11.12 3.12.12 10.12.12 17.12.12 24.12.12 31.12.12 7.1.13 14.1.13 21.1.13 28.1.13 4.2.13 11.2.13 18.2.13 25.2.13 35300 +(35K F'way, c'way additional - surfacing 3211033 7 A885 Argyll st (2011-12 Cap) 1,385 extended Dunoon Stadium to MacArthur St 10mm SMA works) 100% complete
scrub cut, drainage, psdp Keilly Bro
3211038 6 A886 Dunnans 54,000 £183,000.00 Dunans to Leanach SD PSDP, scrub & ditching Complete
scrub cut, drainage, psdp Keilly Bro
3211038 6 A886 Newton 27,000 £92,000.00 Leanach to Mid Letter SD PSDP, scrub & ditching Complete scrub cut, drainage, Keilly Bro psdp 3211039 6 A815 Ardkinglas 28,800 £98,000.00 Ardno to A83(T) SD PSDP, scrub & ditching Complete
Plane out and overlay Full length including Southern 3211040 7 UC74 William St 2,730 £65,000.00 leg of Edward St 14mm EDBM 100% complete
14mm SMA Drainage only Hunters Quay holiday village to 3211041 6 A815 Hafton 5,000 £94,500.00 Lazaretto Ferry Road Drainage works only
Cut joints and overlay 3211042 6 C9 Gairletter 700 £120,000.00 Blairmore to Ardentinny 14mm EDBM 100% complete, awaiting lining
Edge, ditching, scrub Overlay Invernoaden to Beinn Laggan 3211043 6 A815 Glenbranter 7,192 £218,000.00 Forest Access 14mm SMA
Plane out, ditch and Strachur Fire Station to UC12 overlay 3211044 6 A815 Strachur 4,000 £110,000.00 Succoth Road Junction 14mm SMA
Road widen and overlay
3211045 6 A8003 Ormidale 1,800 £120,000.00 Ormidale Road heading North 14mm EDBM
Plane out, ironwork, regulate and overlay
3211046 7 A815 Bullwood Road 15,540 £320,000.00 Kilbride road to Cedar Lodge 14mm SMA 2% complete
Rest and Be thankful. 3211047 6 B828 Contribution to diversion 2,620 £100,000.00 A83(T) to forest access. 14mm SMA route
BUTE APRIL MAY JUNE JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER JANUARY FEBRUARY
WO number Ward Road Location AREA COST Extent Material 2.4.12 9.4.12 16.4.12 23.4.12 30.4.12 7.5.12 14.5.12 21.5.12 28.5.12 4.6.12 11.6.12 18.6.12 25.6.12 2.7.12 9.7.12 16.7.12 23.7.12 30.7.12 6.8.12 13.8.12 20.8.12 27.8.12 3.9.12 10.9.12 17.9.12 24.9.12 1.10.12 8.10.12 15.10.12 22.10.12 29.10.12 5.11.12 12.11.12 19.11.12 26.11.12 3.12.12 10.12.12 17.12.12 24.12.12 31.12.12 7.1.13 14.1.13 21.1.13 28.1.13 4.2.13 11.2.13 18.2.13 25.2.13
Overlay
3111008 8 A886 Shalunt 6,160 £114,000.00 11-12 site heading south 14mm SMA
Hillhouse/ ABC? Acholter farm to Cranslogvourity 3111009 8 A844 Cranslaglogan 4,610 £95,000.00 farm 14mm SMA 5% complete Hillhouse/ ABC? 3111010 8 B875 St Colmac Cemetery 1,806 £28,500.00 Cnoc-an-Raer to A844 14mm SMA 5% complete
Hillhouse/ ABC?
3111011 8 A844 Kilmory Circle 4,610 £95,000.00 Various - Ettrick Bay to B881 14mm SMA 5% complete
Structural patching
3111012 8 UC51 Montegue Street 1,500 £30,000.00 High St to Gallowgate 14mm SMA
Planned works 168,068 £1,883,000
Full week worked
Partial week worked
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
BC Cap resurf 2012-13 PROGRESS JUNEReport | 18 KB | DownloadRead as text |
PDF |
CAP EST v Priced BoQs 280512Report | 103 KB | Download |
PDF |
Carriageway Reconstruction Works 2012-13Report | 70 KB | Download |
Follow Bute and Cowal Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | Charts (argyll and the isles)Decision The Bute and Cowal Area Committee considered and noted the information provided in the presentation. (Refere... | Noted | Open |
| 1 Sep 2026 | Area committee quarterly performance reports fq1 2026/27Decision The Bute and Cowal Area Committee noted the performance and supporting commentary as presented. (Reference: ... | Noted | Open |
| 1 Sep 2026 | Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with... | Agreed | Open |
| 1 Sep 2026 | Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director... | Noted | Open |
| 1 Sep 2026 | Cruach mhor and clachan flats windfarm trustsDecision The Bute and Cowal Area Committee noted these updates, which are the most recent of the annual updates requi... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.