Mid Argyll, Kintyre & the Islands Area Committee agreed this item on Wednesday 6 February 2013. Below is the council's own wording, with the papers it was decided on.
Decision Members agreed:- 1. That the Chair and Councillor Semple would liaise with the Central Governance Manager to establish if a Short Life Working Group could be convened to support further discussion and evaluation of the Ferries Plan. 2. That Marine Operations Manager would provide an update on Tayinloan Pier to the March Business Day. (Reference: Report by Executive Director – Development and Infrastructure Service, dated 18 January, 2013, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Mid Argyll, Kintyre & the Islands Area Committee
Summary
1.1This report provides a review of the recently published Ferries Plan and how it impinges on the Mid Argyll Kintyre and Islay area. There are proposals to introduce a pilot service to the Ayrshire coast via Arran and to modify the service provision to Islay and Jura. The commitment is apparent that the Government will engage with the Council in respect of the transfer of responsibilities for ferry services and details of how Road Equivalent Tariff will be implemented.
Recommendations
2.1That Members note the contents of this report and that; 2.2 A further report will be presented to the Council in March which will set out the Council’s proposed position with regard to the Ferries Plan and associated actions.
3.0DETAIL
3.1Ferries plan
The plan for the period 2013 – 2022 was published by Transport Scotland prior to Christmas 2012. The purpose of the document is to provide communities with a clear view of the intended way forward. The Review has enabled the Scottish Government to develop a shared vision for lifeline ferry services in the context of the National Transport Strategy and inform their long term plan.
3.2Proposals affecting Mid Argyll Kintyre and Islay
In the short term the Government proposes to implement a new two year summer only (May to September) pilot ferry service between Campbeltown and Ayrshire via Arran 3 days per week.. As a temporary step they will introduce a summer months service on a Saturday from Colonsay, via Islay to Kennacraig. In addition, subject to the transfer of responsibility to the Scottish Government, the proposal is to offer zero fares between Jura and Islay when that journey is part of an onward journey to the mainland. What should be noted is that all of the proposals are subject to future Spending Review commitments.
3.3Tarbert - Portavadie
The plan confirms that as a result of the consultation this route provides a vital link for the local community and will be retained.
3.4Claonaig- Lochranza
The Government have questioned the validity of the provision of this service given that it is a second route to Arran. However, it does fulfil a strategic role in providing support to local tourism and carries dangerous goods which cannot be carried on the principal route. On this basis the route will be retained.
3.5Campbeltown – Ardrossan via Arran
The Government has committed to provide a pilot summer service operating from Campbeltown to Ardrossan via Arran running three times per week. The vessel will be the Isle of Arran and is designed to offer a reasonable day trip, an overnight and weekend stays on the west coast. Subject to an evaluation of the pilot the Government could link the new service to the longer term proposals for Arran leading to the possibility of a winter service between Campbeltown and Ardrossan. The implications for the port of Campbeltown are that, dependent upon the timetable, it may impact on the ability to provide the same level of service for the export of timber. The ferry berth would need to be safe for passengers to ensure that there was no risk to them from other operations. Preliminary discussions with staff from Calmac Ferry Ltd confirm that they are willing to modify their initial timetable proposals to mitigate the impact it may have on the port. In respect of the tower shipments, these are intended to utilise the inner berth and provided satisfactory levels of pedestrian and vehicular segregation can be achieved in compliance with our obligations under Port security, this element of our business should not be affected.
3.6Jura
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mid Argyll, Kintyre & the Islands Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an...
Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.