Resolved
Decision Agreed to grant planning permission subject to the following conditions and reasons: 1. No development shall commence or is hereby authorised until the proposed access has been upgraded in accordance with the Council’s Roads Standard Detail Drawing SD08/004a with visibility splays of 53.0 metres to point X by 2.4 metres to point Y from the centre line of the proposed access. The access shall be surfaced with a bound material in accordance with the stated Standard Detail Drawing. Prior to work starting on site the access hereby approved shall be formed to at least base course standard and the visibility splays shall be cleared of all obstructions such that nothing shall disrupt visibility from a point 1.05 metres above the access at point X to a point 0.6 metres above the public road carriageway at point Y. The final wearing surface on the access shall be completed prior to the development first being brought into use and the visibility splays shall be maintained clear of all obstructions thereafter in perpetuity. Reason: In the interests of road safety. 2. N o development shall commence or is hereby authorised until samples of materials and colour finishes for external materials to be used in the construction of the restaurant have been submitted to and approved in writing by the Planning Authority. The development shall be completed and maintained thereafter using the approved materials and colour finishes, or such alternatives as may be agreed in writing with the Planning Authority. Reason: In order to integrate the development into its surroundings. 3. The first floor office and flat shall only be occupied for residential purposes by a person mainly employed in the running and day to day operation of the restaurant hereby approved at the site, along with his or her partner and immediate family as may be necessary, unless otherwise agreed in advance in writing by the Planning Authority,. Reason: In accordance with the use applied for and because separate residential usage may raise conflicts between residential amenity and the ability to operate the commercial use unencumbered, which have not been evaluated in the determination of this application. 4. No development or demolition work shall be carried out on the site until a pre-commencement survey for the presence of nesting birds has been carried out by an appropriately qualified person and has been submitted for the written approval of the Planning Authority. In circumstances where species of conservation interest are identified as being present, or at risk from construction works, the survey shall further provide suggested avoidance and or mitigation measures, including timing constraints, to address such presence or risk. The development shall only be implemented in accordance with the measures and timescales identified in the duly approved scheme. No development or demolition may occur between end of February and late August to avoid adverse impacts on the bird nesting season. Reason: In the interest of nature conservation. 5. N o development shall commence or is hereby authorised until details of all proposed external lighting, and methods by which it is intended to prevent light spillage from the site, have been submitted to and approved in writing by the Planning Authority. The development shall be completed in strict accordance with such details as are approved, and no additional lighting may be installed unless otherwise first agreed in writing by the Planning Authority. Reason: In order to prevent light pollution that may otherwise occur. 6. The development shall be implemented in accordance with the details specified on the application form dated 05/07/13 and the approved amended drawing reference numbers: Plan 1 of 15 Plan 2 of 15 Plan 3 of 15 Plan 4 of 15 Plan 5 of 15 Plan 6 of 15 Plan 7 of 15 Plan 8 of 15 Plan 9 of 15 Plan 10 of 15 Plan 11 of 15 Plan 12 of 15 Plan 13 of 15 Plan 14 of 15 Plan 15 of 15 unless the prior written approval of the planning authority is obtained for other materials/finishes/for an amendment to the approved details under Section 64 of the Town and Country Planning (Scotland) Act 1997 (as amended). Reason: For the purpose of clarity, to ensure that the development is implemented in accordance with the approved details. (Reference: Report by Head of Planning and Regulatory Services dated 24 December 2013 and supplementary ... view the full minutes text for item 6.