Resolved
Decision Noted the results of the public consultation process and agreed on site 2A as the site for the proposed new Oban High School. (Ref: Report by Executive Director of Community Services dated 9 January 2014, submitted)
Argyll and Bute Council noted this item on Thursday 23 January 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision Noted the results of the public consultation process and agreed on site 2A as the site for the proposed new Oban High School. (Ref: Report by Executive Director of Community Services dated 9 January 2014, submitted)
1.1This report updates the Council on the outcome of the agreed public consultation for a preferred site for the proposed new Oban High School.
2.1It is recommended that the Council:
2.1.1 Note the results of the public consultation process; and
2.1.2 Agree on site 2A as the site for the proposed new Oban High School.
3.1At its meeting on 27 June 2013 the Council agreed that the methodology for detailed appraisal of sites for delivering a new Oban High School and delegated the detailed arrangements for the public consultation to the Executive Director of Community Services, in consultation with the Lead Councillor for Education and Lifelong Learning ( now termed Policy Lead).
3.2As agreed by the Council, the sites that were subject to the detailed appraisal were:
Site
1. Glen Shellach – Land adjacent to Argyll College opposite the hospital 2. Existing school and land behind Tweed Mill
3. Dalintart and Glencruitten
4. Land adjacent to Park Primary and Pennyfuir Cemetery
Through the appraisal process a fifth option was identified. This variant on sites 2 and 3, Option 2A, was reported to local members at the Oban Lorn and the Isles business day on 10 September 2013. 2A Amalgamate options 2 and 3 - Existing school and land behind Tweed Mill and Dalintart and Glencruitten
3.3The appraisal process of the five sites was conducted in a workshop scenario by officers from different parts of the Council representing, amongst others, Education, Facility Services, Planning, Economic Development, Roads and Legal Services. The officers assessed each option against the pre-agreed criteria and assigned a ‘score’ in relation to impact, affordability, deliverability and risk.
The sites ranked in the following order:
Rank Site Option 1 2A - Amalgamate options 2 and 3 - Existing school and land behind Tweed Mill and Dalintart and Glencruitten. 2 1 - Glen Shellach – Land adjacent to Argyll College opposite the hospital 3 2 - Existing school and land behind Tweed Mill 4 3 - Dalintart and Glencruitten 5 4 - Land adjacent to Park Primary and Pennyfuir Cemetery
3.4At its meeting on 31 October 2013, the Council considered a report that detailed the results of the appraisal process on the feasibility of the agreed shortlist of five sites for the new Oban High School. The Council agreed that Site 2A should be taken to public consultation as the preferred site, as it was deemed to be the most feasible and deliverable option.
The consultation exercise took place between 18 November and 8 December 2013 and included the following activities:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
OBAN HIGH SCHOOL SITE: CONSULTATIONReport | 78 KB | DownloadRead as text |
Follow Argyll and Bute Council at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Sep 2026 | Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro... | Decided | Open |
| 23 Sep 2026 | Nhs highland director of public health annual report 2025Decision The Council – 1. noted the Director of Public Health Annual Report 2025; and 2. supported the recommendation... | Noted | Open |
| 23 Sep 2026 | Leader's reportDecision The Council – 1. noted the contents of the submitted report; and 2. noted that any reports, briefings or cop... | Noted | Open |
| 23 Sep 2026 | Policy leads reportDecision The Council noted the content of the submitted report. (Reference: Report by Policy Lead Councillors dated 1... | Noted | Open |
| 23 Sep 2026 | Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.