Planning, Protective Services and Licensing Committee, Wednesday 19 February 2014 at 11.00am

ARGYLL COMMUNITY HOUSING ASSOCIATION: ERECTION OF 8 FLATS AND ASSOCIATED WORKS: LAND NORTH OF 34 OAKHILL, TARBERT (REF: 13/02711/PP)

Agreed Planning 2 papers

Planning, Protective Services and Licensing Committee agreed this item on Wednesday 19 February 2014. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

Decision Agreed to grant planning permission subject to the following conditions and reasons:- 1. The development shall be implemented in accordance with the details specified on the application form dated 25 th November 2013, supporting information and, the approved drawing reference numbers 1/6 – 6/6 unless the prior written approval of the planning authority is obtained for an amendment to the approved details under Section 64 of the Town and Country Planning (Scotland) Act 1997. Reason: For the purpose of clarity, to ensure that the development is implemented in accordance with the approved details. 2. The development hereby permitted shall only be implemented by a Registered Social Landlord (a body registered under part 3 chapter 1 of the Housing ( Scotland ) Act 2001, or any equivalent provision in the event of the revocation and re-enactment thereof, with or without modification) and shall not enure for the benefit of any other person, company or organisation. Reason: To ensure the provision of affordable housing to the standard required by the development plan in the absence of any other agreed means of securing such provision. 3. Notwithstanding the effect of Condition 1, no development shall commence until written details of the type and colour of materials to be used in the construction of the external wall and roof finishes have been submitted to and approved in writing by the Planning Authority. The development shall thereafter be completed using the approved materials or such alternatives as may be agreed in writing with the Planning Authority. Reason: In order to integrate the development into its surroundings. 4. The development shall be implemented in accordance with the approved Japanese Knotweed Eradication Plan/Method Statement submitted 24 January 2014 unless otherwise agreed in writing with the Planning Authority. Reason: To ensure the removal of an invasive species from the site and to control the spread of the species. 5. Notwithstanding the effect of Condition 1, no development or other site works will commence until such time as Construction Environmental Management Plan (CEMP) has been submitted to and approved in writing by the Planning Authority. The CEMP will detail the means by which the Reed bed habitat which lies within and adjoining the north and eastern edges of the application site shall be protected from the potential effects of construction activities, including physical intrusion and pollution of the water environment. Thereafter, the development hereby approved shall only commence following approval of the CEMP and shall be fully undertaken in accordance with the approved details. Reason: To ensure the protection of a Biodiversity Action Plan Habitat from the potential adverse effects of construction activities. 6. No development shall commence until a scheme of boundary treatment, surface treatment and landscaping has been submitted to and approved in writing by the Planning Authority. The scheme shall comprise a planting plan and schedule which shall include details of: i) Existing and proposed ground levels in relation to an identified fixed datum; ii) Existing landscaping features and vegetation to be retained; iii) Location design and materials of proposed walls, fences and gates; iv) Proposed soft and hard landscaping works including the location, species and size of every tree/shrub to be planted; v) A programme for the timing, method of implementation, completion and subsequent on-going maintenance. All of the hard and soft landscaping works shall be carried out in accordance with the approved scheme unless otherwise approved in writing by the Planning Authority. Any trees/shrubs which within a period of five years from the completion of the approved landscaping scheme fail to become established, die, become seriously diseased, or are removed or damaged shall be replaced in the following planting season with equivalent numbers, sizes and species as those originally required to be planted unless otherwise approved in writing by the Planning Authority. Reason: To assist with the integration of the proposal with its surroundings in the interest of amenity. 7. Notwithstanding the provisions of Condition 1, the access serving the site, including the southern turning head and adjacent footpath and link to the existing Core Path Route , shall be a Road over which the public has a right of access in terms of the Roads ( Scotland ) Act 1984 which shall be constructed in consultation with the Council’s Roads Engineers. Reason: In the interests of road safety to ensure the provision of a road commensurate to the scale of development, which provides for the development potential of the wider land holding and adjacent Housing Allocation H-AL 13/4 as defined in the Argyll and Bute Local Plan 2009, and which provides a suitable realignment of a Core Path which is affected by the development. 8. The parking and turning area shall be laid out and surfaced in accordance with the details shown on the approved plans prior to the development first being occupied and shall thereafter be maintained clear ... view the full minutes text for item 11.
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Planning, Protective Services and Licensing Committee

Argyll and Bute Council Planning and Regulatory Services

Delegated or Committee Planning Application Report and Report of handling as required by Schedule 2 of the Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2008 relative to applications for Planning Permission or Planning Permission in Principle ____________________________________________________________________________

Reference No: 13/02711/PP

Planning Hierarchy: Local Development

Applicant: Argyll Community Housing Association (ACHA)

Proposal: Erection of 8 flats and associated works

Site Address: Land North of 34 Oakhill, Tarbert ____________________________________________________________________________

DECISION ROUTE

(i) Local Government Scotland Act 1973 ____________________________________________________________________________

(A) THE APPLICATION

(i) Development Requiring Express Planning Permission

• Erection of 8 flats across 2 blocks of 4 flats (4 x 1 bed and 4 x 2 bed); • Formation of 14 parking spaces plus 1 disabled space; • Formation of new access road.

(ii) Other specified operations

• Re-alignment of existing footpath; • Treatment of Japanese Knotweed; • Connection to public water main; • Connection to public waste water network; • Erection of fencing. ____________________________________________________________________________

(B) RECOMMENDATION:

It is recommended that permission be granted subject to the conditions and reasons listed below. ____________________________________________________________________________

(C) HISTORY:

None relevant to this application (D) CONSULTATIONS:

Area Roads Manager (Report dated 16/01/17) - No objection subject to conditions.

Scottish Water (Letter dated 04/12/13) - No objection but advised that Tarbert Water Treatment Works has limited capacity to serve new development but the Waste Water Treatment Works has capacity to service this proposal.

Public Protection Unit (Memo dated 04/12/13) - No objection.

Local Biodiversity Officer (Email dated 20/01/14) - There is no objection in principle but the method statement for the control and disposal for the Japanese Knotweed is not appropriate in this instance therefore a planning condition should be attached to allow the applicant to provide a more appropriate method.

Scottish Environment Protection Agency (Letter dated 13/12/13) - No comment.

Core Paths Officer (Letters dated 5/12/13, 15/01/14) - No objection in principle but further detail required as to the amendments to the footpath which can be dealt with by condition.

West of Scotland Archaeology Service (Letter dated 20/12/13) - No objection subject to condition.

Sustainable Travel Coordinator (Email dated 14/01/14) - No concerns but advised that some bicycle parking would be useful and that part of the existing path, outwith the site boundary, is prone to flooding. ____________________________________________________________________________

(E) PUBLICITY:

The proposal has been advertised in terms of regulation 20, closing date 03/01/14. ____________________________________________________________________________

(F) REPRESENTATIONS:

None _________________________________________________________________________

(G) SUPPORTING INFORMATION

Has the application been the subject of:

(i) Environmental Statement: No

(ii) An appropriate assessment under the Conservation No (Natural Habitats) Regulations 1994:

(iii) A design or design/access statement: No

(iv) A report on the impact of the proposed development Yes e.g. retail impact, transport impact, noise impact, flood risk, drainage impact etc: Method Statement for Treatment of Japanese Knotweed

Summary of main issues raised by each assessment/report

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
02711 location planPlan 906 KB Download
PDF
ARGYLL COMMUNITY HOUSING ASSOCIATION: ERECTION OF 8 FLATS AND ASSOCIATED WORKS: LAND NORTH OF 34 OAKHILL, TARBERT (REF: 13/02711/PP)Report 147 KB DownloadRead as text

At this meeting

Whole meeting
3MINUTESOn the agenda 4CIVIC GOVERNMENT (SCOTLAND) ACT 1982: LICENSING OF TAXIS - DETERMINATION OF DEMANDNoted 5CIVIC GOVERNMENT (SCOTLAND) ACT 1982: TAXI FARE SCALE REVIEWAgreed 6MR STEPHEN SLOSS: SITE FOR THE ERECTION OF DWELLINGHOUSE: LAND SOUTH WEST OF CRERAN COTTAGE, BENDERLOCH (REF: 13/00903/PPP)Agreed 7AWESIDE DEVELOPMENTS LTD: RELOCATION OF EXISTING PLOTS 22 AND 24 TO NEW PLOTS 4A AND 8, ADDITIONAL NEW PLOTS 5A, 18A AND 37 AND REPOSITIONING OF CHALETS ON PLOTS 17 AND 18 AND ASSOCIATED MASTERPLAN FOR PDA 5/115: DALAVICH CHALET PARK, DALAVICH (REF: 13/01501/PP)Agreed 8H THORNTON: ERECTION OF BOATHOUSE: LAND SOUTH WEST OF TIGH MOR NA-H-AIRD, BALLIEMOR, CASTLETON, LOCHGILPHEAD (REF: 13/02528/PP)Agreed 9MR AND MRS N J CRAWFORD: DEMOLITION OF GARAGE, ERECTION OF DWELLINGHOUSE AND FORMATION OF VEHICULAR ACCESS: GARDEN GROUND OF 45 MOUNTSTUART ROAD, ROTHESAY (REF: 13/02662/PP)Agreed 10BARRY ADAMSON: NON MATERIAL AMENDMENT TO PLANNING PERMISSION 12/02792/PP (ERECTION OF A BUILDING TO BE USED IN PART AS DOMESTIC DOUBLE GARAGE/WORKSHOP AND IN PART AS A COOKERY SCHOOL INCLUDING FACILITATING WORKS AND INSTALLATION OF 2,000 LIAgreed
11ARGYLL COMMUNITY HOUSING ASSOCIATION: ERECTION OF 8 FLATS AND ASSOCIATED WORKS: LAND NORTH OF 34 OAKHILL, TARBERT (REF: 13/02711/PP)This decision
12PORT ELLEN PLAYING FIELDS ASSOCIATION: ALTERATIONS AND ERECTION OF EXTENSION TO EXISTING PAVILION: RECREATION GROUND, PORT ELLEN, ISLE OF ISLAY (REF: 13/02751/PP)Agreed 13COLIN LINDSAY MACDOUGALL: LUNGA ESTATE MASTERPLAN RE. PDA 12/76 - ARGYLL AND BUTE LOCAL PLAN 2009 (REF: 13/02859/MPLAN)Agreed 14TIGH GRIAN LIMITED: ERECTION OF 18 AFFORDABLE DWELLINGS (4 - 1 BED UNITS, 10 - 2 BED UNITS AND 4 - 3 BED UNITS), FORMATION OF NEW VEHICULAR ACCESS AND ASSOCIATED MASTERPLAN FOR PDA 10/15: LAND SOUTH EAST OF IMERIVALE COTTAGE, PORT ELLEN, ISLE OF ISLAY (REF: 13/02862/PP)Agreed 15MR DONALD MACLAUCHLAN: FORMATION OF PATHWAY: LAND SOUTH OF KILMORIE CHAPEL BURIAL GROUND, STRATHLACHLAN (REF: 14/00024/PP)Agreed 16APPEALS UPDATE - BUTE HOUSE HOTEL, ROTHESAYNoted 24TheOn the agenda 17ENFORCEMENT REPORT - 12/00176/ENAMENPrivate

Who was there

12 of 15 attended
DK
Councillor David KinniburghChair, present
GB
Councillor Gordon BlairMember, absent
MB
Councillor Michael BreslinMember, absent
RC
Councillor Rory ColvilleMember, present
RC
Councillor Robin CurrieMember, present
MD
Councillor Mary-Jean DevonMember, present
GF
Councillor George FreemanMember, present
AM
Councillor Alistair MacDougallMember, present
RG
Councillor Robert Graham MacIntyreMember, present
DM
Councillor Donald MacMillanMember, present
RM
Councillor Roderick McCuishMember, present
AM
Councillor Alex McNaughtonMember, present

All 15 on the meeting page

On this subject at Argyll and Bute

Search all
  1. ARGYLL COMMUNITY HOUSING ASSOCIATION: ERECTION OF 8 FLATS AND ASSOCIATED WORKS: LAND NORTH OF 34 OAKHILL, TARBERT (REF: 13/02711/PP)This decision
  2. Live Argyll Community Learning Services UpdateNoted
  3. Liveargyll - community learning and development report 2025-26Decided
  4. Argyll and Bute Climate Action: Community Planning Partnership Climate Change Strategy and developing a Climate Ready Region for Argyll and ButeNoted
  5. Argyll Community Housing Association (ACHA)Noted
  6. Live Argyll Community Learning Services - Kintyre Youth WorkNoted

More from Argyll and Bute Planning, Protective Services and Licensing Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Beaufort wind limited: erection of 7 turbines (up to 149.9m to tip) and ancillary development and decommissioning of existing beinn ghlas wind farm: existing beinn ghlas wind farm, taynuilt (ref: 25/01240/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: 1. PP - A... Agreed Open
15 Sep 2026 Mr tony coogan: alterations to guesthouse to facilitate lawful use of existing roof space as ancillary guest house owner's accommodation: greencourt, benvoullin road, oban (26/00434/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Mrs faulkes: proposed alterations and erection of extension: 30 the green, craobh haven (ref: 26/01009/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Scottish power renewables/machair wind limited: scottish government's marine directorate section 36 consultation on proposed machair offshore wind farm: site 15 km north west of isle of islay and 12.4 km west of isle of colonsay (ref: 26/01100/s36)Decision The Committee agreed that the Scottish Government’s Marine Directorate should be notified that Argyll and Bu... Agreed Open
15 Sep 2026 Development management performance update - fq1 2026/27Decision The Committee reviewed and agreed the content of the report. (Reference: Report by Executive Director with r... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies