MULL OF KINTYRE TIDAL GENERATION PROJECT - CONSULTATION FROM MARINE SCOTLAND (REF: 14/00527/S36)
AgreedPlanning2 papers
Planning, Protective Services and Licensing Committee agreed this item on Wednesday 19 March 2014. Below is the council's own wording, with the papers it was decided on.
Decision The Committee agreed that:- 1. No objection be raised to the principle of the project as a whole or the details of the marine component of the scheme; 2. Objection be raised to the issuing of a Marine Licence until such time as an appropriate solution for the terrestrial works has been identified and any necessary consents have been obtained from Council as Planning Authority and the Scottish Government’s Energy Consents Unit; and 3. Marine Scotland is notified accordingly. (Reference: Report by Head of Planning and Regulatory Services dated 5 March 2014, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Planning, Protective Services and Licensing Committee
Argyll and Bute Council Planning Protective Services & Licensing Committee Development & Infrastructure Services 19th March 2014 _________________________________________________________________________
Reference No: 14/00527/S36
Proposal: Proposed Tidal Generator – Consultation under the Marine (Scotland) Act 2010
Site Address: Argyll Tidal Demonstrator Project North Channel, west of the Mull of Kintyre _________________________________________________________________________
A. SUMMARY
This is a consultation from Marine Scotland in respect of an application for a Marine Licence under Part 4 of the Marine (Scotland) Act 2010 to deploy and operate a tidal energy generator with the installation of an export cable. The report recommends views to be conveyed to Marine Scotland on behalf of the Council as Planning Authority.
B. DETAILS OF THE PROPOSAL
This project relates to an Agreement for Lease concluded by a prospective developer with the Crown Estate in respect of a proposed tidal energy site approximately 800m off the west coast of the Mull of Kintyre. The extent of the development site relates back to the ‘area of search’ approach to the leasing process, whereas the proposed infrastructure will only occupy a small fraction of this area. The development was originally conceived as a 3MW scheme which would have entailed the installation of 6 No. 500kw tidal generators. That original proposal was screened by the Scottish Government who determined that an Environmental Impact Assessment would be required to accompany an application for consent under Section 36 of the Electricity Act 1989 along with an accompanying Marine Licence application.
In the event, the prospective developers have scaled back the project to a single demonstration device and the Scottish Government has confirmed that as a consequence in the reduction in scale of the project to less than 1MW, a Section 36 application and environmental assessment will not be required. The marine elements of the project will therefore now require to be consented by means of a Marine Licence under Part 4 of the Marine (Scotland) Act 2010. Such an application has been submitted to Marine Scotland who have consulted the Council, along with other consultees, as part of their consideration of the proposal.
The project consists of the proposed installation of one 0.5MW Tidal Energy Generator including an export cable to a landfall on the Mull of Kintyre. The location has been selected for its tidal resource, its lack of environmental designations, and proximity to a suitable cable landing point and areas of electricity demand. The intention is to secure the demonstrator generator by means of a three pin moored foundation rather than a fixed foundation, as water depth and resource levels off Kintyre lend themselves to this means of deployment. The generator comprises a device with contra-rotating blades, based on a scaled-down prototype previously deployed in the Sound of Islay and elsewhere outwith Argyll. The horizontal axis to the nacelle would be positioned around 23m below the surface and the closest part of the equipment to the surface (a stabilising hydrofoil) would be at about 10 metres depth.
The mooring equipment and generator will be deployed from Campbeltown harbour and it is anticipated that this will also be the maintenance point. The Crown Estate lease would be for a 7 year period but the device has a 20 year design life, so there is both possibility of this being extended and the device being replaced in the longer- term.
C. POLICY CONTEXT
Consultation on the draft of Scotland’s first ‘National Marine Plan’ has closed and it is expected to be adopted later this year. This seeks to support the sustainable development of wind, wave and tidal renewable energy, to facilitate joined-up marine planning and licencing processes, to contribute to national renewable energy targets, and to facilitate the development of offshore demonstration facilities.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning, Protective Services and Licensing Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.