Resolved
Decision The Committee noted the contents of the report. (Ref: Report by Area Commander, Scottish Fire and Rescue dated 29 May 2014, submitted)
Performance Review and Scrutiny Committee noted this item on Thursday 29 May 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Committee noted the contents of the report. (Ref: Report by Area Commander, Scottish Fire and Rescue dated 29 May 2014, submitted)
SCOTTISH FIRE & RESCUE SERVICE
Performance Report
Fiscal year 2013 -2014 Annual Report
The following pages represent the performance of the Scottish Fire & Rescue Service using the priorities and objectives as laid out in the Local Fire Plan for Argyll & Bute 2013 - 2014 Priority 1 - Reduction of Accidental Dwelling Fires
3 year Reduction Actual this Performance Annual target average target year indicator
88 10% 79 78 green
This target is the main focus of all Community Safety activities through our Text Home Fire Safety Visit initiatives and education programmes.
Over recent years this figure has improved to its now all time low figure although there is no room for complacency.
From statistical annalysis we have found that cooking remains the most common cause of these types of fires and therefore will continue to be the focus for safety information and advice.
Priority 2 - Reduction of Fire Casualties & Fatalities
3 year Reduction Actual this Performance Annual target average target year indicator
17 6% 16 12 green
Casualty figures are better than target and again provides an indicator that Text our preventative approach is working within our communities.
Caution must be exercised with this Performance Indicator (PI) as a single incident with multiple casualties can cause this target to be missed, every effort will be maintained to continue to improve this PI
Priority 3 - Reduction of Deliberate Fire Setting
3 year Reduction Actual this Performance Annual target average target year indicator
Primary 32 4% 31 17 green Secondary 105 10% 95 55 green Primary Fires are designated as fires that involve property, Secondary Fires are Text designated as fires involving refuse, grass and heathland etc.
We have worked with Police Scotland over recent years in order to improve detection rates in deliberate fire raising however, despite these reductions, the number of incidences of Fire Related Anti Social Behaviour continues to require this multi-agency focus.
This summer was warm and dry and therefore the Service as a whole experienced a considerable rise in grass fires during this period, however safety campaigns conducted prior to the annual bonfire night did see a general reduction in overall calls being attended to by the Service.
Priority 4 - Reduction of Fires in Other Buildings
3 year Reduction Actual this Performance Annual target average target year indicator
Accidental 47 10% 42 41 green Deliberate 7 10% 6 4 green
Fire can have a devastating effect on business therefore the Service will Text continue to work with the business sector in order to ensure that there is compliance with Fire Safety Legislation.
This target will be monitored throughout the year
Priority 5 - Reduction of Road Traffic Collisions
3 year Reduction Actual this Performance Annual target average target year indicator
79 5% 75 79 amber
We Texthave continued to provide safety information through our drive safe programmes and young drivers initiatives and worked alongside our Community Safety Partnership colleagues to tackle this priority. This continues to be a challenging PI in the Argyll & Bute area and remains on average due to a particularly low figure (62) in the previous year. More intense focus, in association with our Partners, will be undertaken for the future term of our Local Fire Plan. Priority 6 - Reduction of Unwanted Fire Alarm Signals
3 year Reduction Actual this Performance Annual target average target year indicator
Automatic 742 10% 668 825 red Malicious 22 9% 20 8 green
The reduction of Automatic Fire Alarms (AFA) continues to challenge the Text service as a whole. More AFAs are being installed in premises as part of fire safety requirements, this ultimately means there are more alarms in the community available to raise the alarm to a potential fire, which is obviously a positive step. However the need to tackle repeat offenders who have a malfunctioning or improperly working alarm system remains a priority for the service.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
SCRUTINY OF SCOTTISH FIRE AND RESCUEReport | 264 KB | DownloadRead as text |
Follow Performance Review and Scrutiny Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Mar 2017 | Treasury management monitoring reportDecision The Committee noted the report. (Reference: Report by Head of Strategic Finance dated 3 March 2017, submitted) | Noted | Open |
| 3 Mar 2017 | Treasury management strategy statement and annual investment strategyDecision The Committee agreed to refer to Council; 1) the proposed Treasury Management Strategy Statement and Annual ... | Agreed | Open |
| 3 Mar 2017 | Quarterly performance reports and scorecardsDecision The Committee noted the contents of the report. (Reference: Report by Chief Executive dated 3 March 2017, su... | Noted | Open |
| 3 Mar 2017 | Maximising attendanceDecision The Committee noted; 1) the content of the report; and 2) the measures the Council has put in place to manag... | Noted | Open |
| 3 Mar 2017 | Succession planningDecision The Performance Review and Scrutiny Committee noted the presentation. (Reference: Presentation by Head of Im... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.