Performance Review and Scrutiny Committee noted this item on Thursday 29 May 2014. Below is the council's own wording, with the papers it was decided on.
Decision The Committee noted the progress of the Strategic Risk Register and agreed that the Head of Strategic Finance would issue the Strategic Risk Register to Elected Members prior to the June Council meeting to provide Elected Members with a final opportunity to provide feedback before the Council meeting in June. (Ref: Report by Head of Strategic Finance dated 19 May 2014, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Performance Review and Scrutiny Committee
Summary
1.1This report updates members on the progress in relation to progress in developing our strategic risk register.
1.2The draft register has been reviewed by both the strategic risk group and was also a discussion topic at a recent members seminar. Feedback from both reviews has been incorporated into an updated draft.
1.3The strategic risk register is updated on a live basis and will be formally reviewed twice yearly, in August (post year-end) and in February as part of budget setting process.
Recommendations
2.1Performance and Scrutiny Committee to note the progress update, consider the draft strategic risk register and feedback any further comments to the Council meeting in June.
3. DETAIL
Background
3.1The Council deferred a decision on a revised strategic risk register (SRR). The current version therefore is still in “draft” format however a number of reviews have recently taken place.
3.2The Strategic Risk Group reviewed the draft register at its 25th March meeting and a number of amendments were made which are now reflected in the updated draft.
3.3The Strategic Risk Group agreed to the inclusion of an additional risk in relation to the Built environment as detailed at 3.7.
3.4The draft SRR was a discussion topic at a members’ seminar held on the 7 April. Attendees reviewed each individual risk and considered the risk description, potential consequences, scoring and controls / mitigations in place.
3.5Feedback from the seminar was generally positive and there was a general consensus that the register captured the key risks facing the Council, however, there were a number of recurring themes arising with suggested amendments which have been considered and where appropriate adopted into the updated draft. The main themes were; • Scoring: Members agreed a number of amendments to individual risk scoring.
• Scoring: Members also raised concerns around comparative scoring and the prioritisation of individual risks which scored similar.
• Narrative: Members requested terminology be reviewed to ensure content is easily understood and where appropriate eliminates technical or in-house phraseology.
• Narrative: A number of additions and deletions to risk description, consequences and mitigations were agreed.
• Ordering: Members suggested that the register is ordered in relation of scoring of risk, e.g. Economic Development is the number one risk therefore should appear at the top of the register.
• Formatting: Members also suggested some minor formatting changes.
3.6Appendix 1 details the draft SRR. There are currently 15 strategic risks identified an increase of 1 from previous period. PRS are requested to consider the content of the draft register and feedback comment
3.7Risks Added To And Deleted From The SRR
The table below sets out any new risks that have been added to the SRR.
External built environment Risk – Our built Description – Risk environment is not relates to non council maintained to an infrastructure and adequate standard and assets. Communities does not support and public sector investment or partners fail to make the regeneration aspirations best use of our natural and built environment and it is allowed to deteriorate to levels which do not support investment or regeneration aspirations Raw 4 Raw Impact 4 Raw Score 16 Mitigations – Townscape Heritage Initiative THI – Conservation Area Regeneration Scheme. CARS – Building Standards Area Teams Residual Likelihood 3 Residual Impact 4 Residual Score 12 3.8 Subject to Council approval, the proposed process for reviewing the strategic risk register is outlined below:
• Designated risk owner to update on an ongoing basis in consultation with appropriate chief officers /service managers and spokespersons. • SMT to review progress /update report. • Strategic Risk Group review the SRR at its scheduled meetings. • Performance Review and Scrutiny Committee to consider progress/ update reports.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Performance Review and Scrutiny Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Treasury management monitoring reportDecision The Committee noted the report. (Reference: Report by Head of Strategic Finance dated 3 March 2017, submitted)
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.