Resolved
Decision Noted the contents of the Highlight Report and agreed to continue to support this project. (Reference: Report by Head of Planning and Regulatory Services and Highlight Report – June 2012 to December 2014, submitted)
Planning, Protective Services and Licensing Committee noted this item on Wednesday 21 January 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision Noted the contents of the Highlight Report and agreed to continue to support this project. (Reference: Report by Head of Planning and Regulatory Services and Highlight Report – June 2012 to December 2014, submitted)
Argyll and Bute Council Development and Infrastructure Services
PLANNING, PROTECTIVE SERVICES AND LICENSING COMMITTEE - 21st January 2015 ____________________________________________________________________________
Waitrose Planning Contribution – Project Highlight Report and Update ____________________________________________________________________________
A) INTRODUCTION
This report provides an update on the progress and delivery of projects associated with Planning Consent 11/01422/PP which approved a foodstore and petrol filling station at Cardross Road, Colgrain, Helensburgh – now built and operated by Waitrose.
Planning consent was issued for the foodstore in June 2012 and Waitrose began trading in October 2013. As part of the planning consent a legally binding s75 agreement was drawn up between the Council and Developer which secured financial contributions to deliver projects to the value of £880,000. The money and projects were to offset perceived negative impacts that the foodstore would have on existing town centre shops, business and industry land and open space / trees.
There have been project specific updates to the Helensburgh and Lomond Business Day (shop front enhancement scheme, gateway feature, town centre public art and tree planting) over the past 2 years however it has been identified in a recent internal audit that a regular 6 monthly update should be provided to the determining committee (PPSL) given the financial scale and strategic nature of the fund. Other major and complex s75 agreements shall also be reported this way in the future.
B) RECOMMENDATION
Members are asked to note the content of this Highlight Report and asked to continue to support this project.
C) IMPLICATIONS
Policy: Continued support of projects essential to comply with provisions of the s75 and planning consent.
Financial: £418,000 worth of projects have either been commenced or delivered. £470,000 worth of projects still need to be delivered and funds utilised before 2023 (at earliest) – otherwise the developer is entitled to a reimbursement of unspent capital
Personnel: Resource to deliver projects.
Equal Opportunities: None
Author and Contact Officer: Ross McLaughlin, Development Manager
Angus J Gilmour Head of Planning & Regulatory Services Waitrose Planning Contribution
Highlight Report
Highlight Report - Overall Project Status Name of Document: Waitrose Planning Contribution
Author: Ross McLaughlin
Summary of progress from June 2012 to Description of Content: December 2014 Green Planning, Protective Services and Licencing Distribution: Committee
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
WAITROSE PLANNING CONTRIBUTION: PROJECT HIGHLIGHT REPORT AND UPDATEAgenda | 173 KB | DownloadRead as text |
Follow Planning, Protective Services and Licensing Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.