Helensburgh & Lomond Area Committee agreed this item on Tuesday 10 February 2015. Below is the council's own wording, with the papers it was decided on.
Decision Members agreed: 1. To note the report, and 2. That the Roads Performance Manager would provide an update report to the Business Day and Area Committee meetings which would outline information on the concerns raised. (Reference: Report by Executive Director - Development and Infrastructure dated 14 January 2015, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
The main purpose of this report is to advise Members of the roads revenue budget position for the 3rd Quarter of financial year 2014/15.
The overall roads maintenance budget for the 2014/15 year (excluding winter maintenance and coastal protection) is £4,145,227. Spend at the end of the third quarter of the financial year is £3,133,803; this equates to a 76% spend, with 24% remaining for the last quarter of the financial year.
Spend to date In Helensburgh and Lomond is £425,622 against an overall budget for the Area of £679,075, i.e. 63% spend to date. Plans are already in place to ensure that the remaining 37% of the Helensburgh and Lomond revenue budget is spent over the remaining last quarter of the year.
Recommendation
That the Committee notes this report.
1 ARGYLL AND BUTE COUNCIL Helensburgh and Lomond Area Committee
DEVELOPMENT AND INFRASTRUCTURE SERVICES 10 FEBRUARY 2015
ROADS REVENUE BUDGET 2014 TO 2015 – 3rd QUARTER UPDATE
Summary
2.1This report is the second of four reports which will provide Members with information on road maintenance revenue activities being delivered in 2014/15.
Recommendations
3.1That the Committee notes this report.
4.0DETAILS
4.1Members were presented with four reports for each quarter of the 2013 to 2014 financial year which provided information on the roads maintenance revenue budget. This third, of four reports in the series, provides financial information on roads maintenance spend for the third quarter of the 2014 to 2015 financial year.
4.2The table at Appendix 1a) provides details of spend in the Helensburgh and Lomond Area. Actual costs to date are provided, along with spend for the 2nd and 3rd quarters, to allow comparisons to be made between the two periods. This table indicates that, for an overall budget for the Area of £679,075, spend to date is £425,622 i.e. 63% spend to date. Appendix 1b), indicates the overall roads revenue maintenance budget for each area; the total roads maintenance budget for the 2014/15 year (excluding winter maintenance and coastal protection) is £4,145,227 as indicated in the table.
4.3Appendix 1c) provides information on percentage spend for all areas. As mentioned above, the spend for Helensburgh and Lomond is currently at 63%, which is slightly low for this time of year; this is mainly due to concentrating the majority of resources on delivery of the roads reconstruction programme which is now virtually complete. Revenue maintenance works planned for the remainder of the year in the Lomond Area include white lining and studding, patching, gully-emptying and general drainage works.
4.4In Appendix 1d) the budget spent for each activity has been divided by the estimated unit rate for that activity to give the amount of work that would be expected to have been achieved within that budget spend. In future, actual quantities of works carried out in each area will be correlated with costs to provide average unit rates for each area.
4.5Appendix 1e) shows graphically how some of the main work activities have progressed in the first quarter of the year in financial terms. Budget profiles are set for each budget line and are used to manage actual expenditure against available budget. Graphs show ‘target’ spend versus ‘actual and re-profiled’ spend. The last two graphs indicate the overall position.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Helensburgh & Lomond Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref...
Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.