Helensburgh & Lomond Area Committee agreed this item on Tuesday 10 February 2015. Below is the council's own wording, with the papers it was decided on.
Decision Members agreed : 1. To note the report; 2. That the Roads Performance Manager would provide an updated report for the March Business Day and the April Area Committee providing the detail of next year’s Capital Works programme, and 3. That the Roads Performance Manager would review the issues highlighted by Members and provide an update. (Reference: Report by Executive Director - Development and Infrastructure dated 28 January 2015, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
The main purpose of this report is to provide Members with an update on works carried out to date on this year’s capital roads reconstruction programme.
The overall Council roads capital reconstruction budget for year 2014 to 2015 is £6,822,000; the Helensburgh and Lomond Area has been allocated £955,000 (or 14% of the overall budget).
Spend to date is £867,000, which equates to 91% of the Helensburgh and Lomond capital budget. All works will be complete by the end of this financial year.
Recommendation
That the Committee notes this report.
1 ARGYLL AND BUTE COUNCIL Helensburgh and Lomond Area Committee
DEVELOPMENT AND INFRASTRUCTURE SERVICES 10 FEBRUARY 2015
ROADS CAPITAL RECONSTRUCTION PROGRAMME - UPDATE
Summary
2.1This report provides an update on works carried out on the capital roads reconstruction programme in the Helensburgh and Lomond Area this financial year.
Recommendations
3.1That the Committee notes this report.
4.0DETAILS
4.1Members were presented with the proposed capital roads reconstruction programme in March 2014 for the, at the time, forthcoming 2014 to 2015 financial year.
4.2The table attached in the appendix to this report provides an update on works carried out to date in the Helensburgh and Lomond Area. Two schemes, at Old Luss Road and South King Street in Helensburgh, have both been delayed due to forthcoming excavation works programmed by Scottish Gas Networks (SGN); it is proposed to include these two schemes in next year’s Helensburgh and Lomond capital programme. The B833 scheme at Cove will be delivered under the auspices of the roads revenue budget.
4.3In general, where scheme costs have increased significantly beyond budget limits, this reflects additional surfacing and edge strengthening work which has been carried out utilising available funding from the deferred schemes. In particular, on the B833 Barreman scheme, works were extended to address extensive carriageway edge deterioration on an adjacent section of the site.
4.4The Helensburgh and Lomond Area capital roads reconstruction budget is £955,000; spend to date is £867,000 (i.e. programme currently 91% complete). With the exception of those schemes mentioned above, most schemes are now complete.
4.5Capital footway works are progressing well with completion programmed for the end of February; a sub-contractor is providing additional assistance to ensure that the programmed completion date will be met. Locations are as follows:- Sinclair Street, Helensburgh – West side from West Montrose Street to West Dunhill Drive, East side from Victoria Road to Sinclair Drive, Colquhoun Street – East side from West King Street to West Argyll Street and Feorlin Way, Garelochhead – East side above roundabout.
2 5.0 CONCLUSION
This report provides Members with a financial update on the roads capital reconstruction budget for the financial year 2014 to 2015. It indicates a spend to date of 91% for the Helensburgh and Lomond Area at the end of the third quarter.
6.0IMPLICATIONS
6.1Policy Works assessed and carried out under the current Roads Asset Management and Maintenance Plan.
6.2Financial Programme based on capital allocation for years 2012 – 2015.
6.3Legal None
6.4HR Reconstruction works delivered by a combination of in- house Roads Operations team and sub-contractors.
6.5Equalities None
6.6Risk Completed works will reduce requirement to repair and maintain existing carriageway deterioration.
6.7Customer Services Overall improvement in travel time and quality of driven and walking journeys.
Executive Director of Development and Infrastructure: Pippa Milne Head of Roads & Amenity Services: Jim Smith 28 January 2015
For further information contact: Stewart Clark, Roads Performance Manager, Tel: 01546 604893
Appendices
Appendix – List of capital schemes and costs to date.
Follow Helensburgh & Lomond Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref...
Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.