Resolved
Decision The Committee noted the contents of the report. (Ref: Report by Roads Performance Manager dated 20 th January 2015, submitted).
Oban Lorn & The Isles Area Committee noted this item on Wednesday 11 February 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Committee noted the contents of the report. (Ref: Report by Roads Performance Manager dated 20 th January 2015, submitted).
The main purpose of this report is to advise Members of the roads revenue budget position for the 3rd Quarter of financial year 2014/15.
The overall roads maintenance budget for the 2014/15 year (excluding winter maintenance and coastal protection) is £4,145,227. Spend at the end of the third quarter of the financial year is £3,133,803; this equates to a 76% spend, with 24% remaining for the last quarter of the financial year.
Spend to date in Oban, Lorn and the Isles is £868,792 against an overall budget for the Area of £1,150,200, i.e. 76% spend to date.
That the Committee notes this report.
1 ARGYLL AND BUTE COUNCIL Oban, Lorn and the Isles Area Committee
DEVELOPMENT AND INFRASTRUCTURE SERVICES 11 FEBRUARY 2015
ROADS REVENUE BUDGET 2014 TO 2015 – 3rd QUARTER UPDATE
2.1This report is the second of four reports which will provide Members with information on road maintenance revenue activities being delivered in 2014/15.
3.1That the Committee notes this report.
4.0DETAILS
4.1Members were presented with four reports for each quarter of the 2013 to 2014 financial year which provided information on the roads maintenance revenue budget. This third, of four reports in the series, provides financial information on roads maintenance spend for the third quarter of the 2014 to 2015 financial year.
4.2The table at Appendix 1a) provides details of spend in the area of Oban, Lorn and the Isles. Actual costs to date are provided, along with spend for the 2nd and 3rd quarters, to allow comparisons to be made between the two periods. This table indicates that, for an overall budget for the Area of £1,150,200, spend to date is £868,792 i.e. 76% spend to date. Appendix 1b), indicates the overall roads revenue maintenance budget for each area; the total roads maintenance budget for the 2014/15 year (excluding winter maintenance and coastal protection) is £4,145,227 as indicated in the table.
4.3Appendix 1c) provides information on percentage spend for all areas. The spend for Lorn is currently at 69% whist the Mull spend is 89%. Overall, the spend sits comfortably at 76%. Clearly, funding will require to be transferred from the Lorn budget to the Mull budget – the figure for transfer is £45,000 to ensure that revenue maintenance commitments on the island can be met. The spend on patching, jet-patching and potholing on Mull this year was higher than anticipated, however, this additional spend has made a notable difference to the islands roads and addressed many safety-related issues. There was also a higher than anticipated spend on emergency works due to the autumnal storms on Mull.
4.4In Appendix 1d) the budget spent for each activity has been divided by the estimated unit rate for that activity to give the amount of work that would be expected to have been achieved within that budget spend. In future, actual quantities of works carried out in each area will be correlated with costs to provide average unit rates for each area.
4.5Appendix 1e) shows graphically how some of the main work activities have progressed in the first quarter of the year in financial terms. Budget profiles are set for each budget line and are used to manage actual expenditure against available budget. Graphs show ‘target’
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
ROADS REVENUE BUDGET 2014 TO 2015: 3RD QUARTER UPDATEReport | 361 KB | DownloadRead as text |
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | Public question time part 1It was agreed therefore that the responses would not be read out but included in the minute and also emailed to the A... | Agreed | Open |
| 9 Sep 2026 | CHARTS (Argyll and Isles)Decision The Oban, Lorn and the Isles Area Committee considered and noted the information provided in the presentatio... | Noted | Open |
| 9 Sep 2026 | Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv... | Noted | Open |
| 9 Sep 2026 | Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co... | Noted | Open |
| 9 Sep 2026 | Argyll Square Project: Consolidated Financial Report and Delivery UpdateDecision The motion was carried by 4 votes to 2 and the Committee resolved accordingly. (Reference: A report by Secti... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.