Resolved
Decision The Committee noted the content of the report. (Reference: Report by Chief Internal Auditor dated 13 March 2015, submitted)
Audit Committee noted this item on Friday 13 March 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Committee noted the content of the report. (Reference: Report by Chief Internal Auditor dated 13 March 2015, submitted)
1.1The objective of the report is to provide a summary of Internal Audit activity and progress during Quarter 4.
1.2Core activities together with a progress update statement are shown below.
• 14/15 Audit Plan progress: Audit plan is currently on track. It is anticipated that all planned 14/15 Audits will be completed by 31 March.
• Individual Audits undertaken: Eight individual audits have been completed during the period. Of these 8 audits, 6 are rated substantial and 2 are rated limited.
• Continuous Monitoring Programme Testing: A number of auditable units are subject to continuous testing. Reporting is by exception. Management have responded to previous quarter notifications and there are no outstanding issues. A number of school fund checks were carried out during the quarter
• National Fraud Initiative: New matches have been released. Review work has commenced and findings will be reported to September 2015 Audit Committee.
• Development Plan: Progress continues to be made against revised development plan action points. All items are currently on track.
• Performance indicators: Revised indicators are in place and current status is on track / green. ARGYLL AND BUTE COUNCIL AUDIT COMMITTEE
STRATEGIC FINANCE 13 MARCH 2015
INTERNAL AUDIT SUMMARY OF ACTIVITIES
2. INTRODUCTION
2.1The objective of the report is to provide an update on Internal Audit activity during Quarter 4 against a number of areas;
• 14/15 Audit Plan progress • Individual Audits undertaken • Continuous Monitoring Programme Testing • National Fraud Initiative • Development Plan • Performance indicators
3.1The Audit Committee is asked to note the content of the report.
4. DETAIL
4.1The Audit Plan is currently on track and anticipated to be fully completed by 31 March 2014. Eight Audits have been completed as detailed at 4.2. The remaining 3 audits are in progress and are at various stages of completion. These are Business Continuity, Employment and Training and Adult Learning Policy. These will be completed during Quarter 4 and will be submitted to the June committee meeting. One audit, Health and Social Care Integration Governance arrangements, is being carried forward to 15/16 audit plan as it is deemed more appropriate to undertake a review once arrangements are finalised.
4.2Audits completed to March are detailed in Table 1.
Table 1: Summary of Audits performed in Quarter 3, 2014/15:
Audit Name Level of No. of High Assurance recommendations/ Recommendations observations Winter Maintenance Limited 10 3 Flood Risk Management Substantial 0 0 Fostering and Adoption Substantial 6 0 CHORD Limited 8 2 Revenue & Benefits Substantial 0 0 Communications Substantial 4 0 Information Security Substantial 0 0 4.3 Audits planned for the Quarter 1 15/16 are shown in the table below.
Quarter 1 Residential Placements Roads Maintenance HR Training Education – SQA Health & Safety Health and Social Care Integration Catering
4.4A number of areas which were previously subject to individual audits now form part of our continuous monitoring programme. These areas are tested on a regular basis and detailed reporting will be by exception to Audit Committee. Standard audit tests are applied relevant to each auditable unit. Clients are notified by memo of any concerns and a follow up process is in place to ensure active management /rectification of issues raised. Table 2 below summarises activity to date outlining issues arising and provides a level of assurance.
Table 2: Continuous monitoring programme results:
Audit Unit Areas Tested Issues Arising Assurance Follow up Level Payroll and • Excessive & • Street Lighting Substantial Policy Overtime Regular and Janitorial Review and Overtime additional over Resource time regularly request. occurring
Debtors • Supporting • Segregation of Substantial No action Documentation duties required • Charging Schedules
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
INTERNAL AUDIT SUMMARY OF ACTIVITIESReport | 125 KB | DownloadRead as text |
Follow Audit Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Mar 2017 | Internal audit summary of activitiesDecision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March ... | Noted | Open |
| 24 Mar 2017 | Internal audit reportsDecision The Committee noted the contents of the summary report and the detail within each individual report. (Refere... | Noted | Open |
| 24 Mar 2017 | External & internal audit report follow-up 2016 - 2017Decision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March ... | Noted | Open |
| 24 Mar 2017 | Internal audit annual plan 2017 - 2018Decision The Committee agreed and approved the Internal Audit Annual Plan 2017/18 (Reference: Report by Chief Interna... | Agreed | Open |
| 24 Mar 2017 | External audit plan 2017 - 2018Decision The Committee noted the contents of the report. (Reference: Report by Audit Scotland dated March 2017, submi... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.