Short Life Working Group - Argyll Islands Task Force noted this item on Monday 23 March 2015. Below is the council's own wording, with the papers it was decided on.
Decision The Task Force noted the content of the report and noted that since the report had been originally written; Argyll and Bute had been awarded £1.8M towards Fuel Poverty on Mull. (Reference: Report by Executive Director – Customer Services dated 6 February 2015, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Short Life Working Group - Argyll Islands Task Force
Executive summary
1.1Applications for Phase 2 of the Local Energy Challenge Fund have now been submitted which take forward the following successful Phase 1 applications
Machrihanish Renewables Supply Micro Grid Project lead: Community Energy Scotland Award amount: £12,838 Area: Argyll and Bute (Machrihanish)
ACCESS - Assisting Communities to Connect to Electric Sustainable Sources Project lead: Community Energy Scotland Award amount: £29,999 Area: Argyll and Bute (Isle of Mull)
Community Micro Acceleration Project Project lead: Dalavich Improvement Group Award amount: £29,501 Area: Highlands and Islands (Dalavich within Argyll)
1.2Following discussions between the projects the Machrihanish and Community Micro Acceleration Projects have combined. Phase 2 applications have been submitted.
1.3The ACCESS project focused on the Island of Mull but the learning resulting from the work being carried out could be applied to a number of our island communities where grid constraints are an issue.
1.4It is recommended that the Taskforce notes the content of this report. ARGYLL AND BUTE COUNCIL Argyll Islands Taskforce
Development and Infrastructure Services 23 March 2015
Local Energy Challenge Fund
2.0INTRODUCTION
2.1The Local Energy Challenge Fund has been created to demonstrate the value and benefit of local low carbon energy economies. The new fund coincided with the launch of the Community Energy Policy Statement which sets out the Scottish Government’s record of support for community energy and new ambition for holistic local energy solutions.
2.2The focus of the fund is to secure the delivery of large-scale local low carbon demonstrator projects which show a local energy economy approach linking local energy generation to local energy use. This could include projects looking to develop innovative distribution and storage solutions, and with an overall aim to create more local value and benefit. There is a fantastic £20 million available in the Local Energy Challenge Fund, and this will support cutting edge projects which will lead the way in transforming how Scotland’s communities interact with their energy supply and demand.
2.3There were a total of 114 bids submitted to the Local Energy Challenge Fund (£20 million pot) and only 17 were successful in securing a first phase pass. Phase 2 applications have now also been prepared and submitted.
Recommendations
3.1That the Taskforce notes the content of this report.
4.0DETAIL
4.1Applications for Phase 2 of the Local Energy Challenge Fund were submitted at the beginning of February. Two of the successful Argyll based Phase 1 applications have now combined – the Machrihanish Renewables Supply Micro Grid and the Community Micro Acceleration Project (details of each project can be found at Appendix 1). The ACCESS project on Mull has stayed as a separate project.
4.2In relation to the ACCESS project Community Energy Scotland (CES) have been working closely with the Mull and Iona Community Trust to identify households who may be interested in having the new equipment installed should the Phase 2 application be successful. CES have also been in discussions with Housing Services staff in relation to the works undertaken through the Home Energy Efficiency Programmes Scotland Area Based Scheme (HEEPS ABS) to see whether the two projects could align as together they could have a significant impact on fuel poverty for the households involved.
4.3The timescale for the Phase 2 application process is as follows: 6th Feb Submission of final bid 9-13th Feb Pre-assessment of bids 16th Feb Local Energy Scotland collate assessments 24th/25th Feb Panel meeting 26th Feb Requests for additional supporting information from panel 9th March Local Energy Scotland inform applicants of the outcomes
5.0CONCLUSION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Short Life Working Group - Argyll Islands Task Force at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.