Decision 1. The Council agreed:- (a) The proposed changes to the Argyll and Bute Local Plan Wind Farm Policy Map and to the Renewable Energy Policies as detailed in Appendix A of the submitted report. (b) That the changes as detailed in Appendix A be issued as Modifications 4 and that they be advertised, and a six week period allowed for representations to be made. (c) To delegate to the Head of Planning powers to respond to any representations made during the six week publicity and representation period on the proposed representations, and to deal appropriately with them at the reconvened Public Inquiry session. (d) That the Public Local Inquiry session on the Renewable Energy section of the Plan be re-scheduled to allow representations on Modifications 4 to be considered at the Inquiry. (Ref: Report by Head of Planning dated 26 September 2007, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report proposes that changes be made to the renewable energy policies and to the wind farm proposals map of the Modified Finalised Draft Local Plan. These Modifications being proposed in order to reflect the new SPP 6 on Renewable Energy which Scottish Ministers issued in March of this year. In proposing these changes, the representations received to the Modified and Finalised Draft Local Plan have also been taken into account. In particular, policy LP REN 2 has been amended to refer to all wind farm developments below 20 mega watts, and adopting a strictly criteria based approach rather than map based, and a new policy LP REN 3 inserted to refer to smaller scale wind turbines which are intended to serve on site domestic or commercial / industrial requirements.
Recommendations
2.1That Members agree to:
The proposed changes to the Argyll and Bute Local Plan Wind Farm Policy Map and to the Renewable Energy policies as detailed in Appendix A of this report. That the changes as detailed in Appendix 1 be issued as Modifications 4, and that they be advertised, and a six week period allowed for representations to be made. Delegate to the Head of Planning powers to respond to any representations made during the 6 week publicity and representation period on the proposed representations, and to deal appropriately with them at the reconvened public inquiry session. Members will of course have final say on the policy to be formally adopted after consideration of the Reporters views on the Public Local Inquiry That the Public Local Inquiry session on the Renewable Energy section of the Plan be re-scheduled to allow the representations on Modifications 4 to be considered at the Inquiry.
Background
3.1Members will recall that the Renewable Energy policies of the Local Plan attracted a considerable number of representations. In total 136 representations were received with specific reference to the Local Plan policies on renewable energy and/or the wind farm policy map. The objections range from the renewable energy industry and members of the public who are concerned that the renewable energy policies are too restrictive, and members of the public, community councils and interest groups who think that the policies and wind farm maps are too permissive
3.2In view of the wide range of representations which were received on the Finalised Draft Local Plan, Planning Services had recommended that no change be made to the policies or the maps at the Modified Draft stage of the Plan. The main reason for this being that because of the range of representations, it would be difficult to have made changes which would not have resulted in counter representations.
3.3Members may recall that the Bute and Cowal Area Committee recommended that an alteration to the wind farm policy maps be made, to remove the preferred areas of search for wind farms from Bute and Cowal. This was accepted by the Council and consequently the Modified Finalised Draft was issued for public consultation, with the wind farm policy map showing Bute and Cowal as a constrained area. In response to these changes representations have been received from both the renewable energy industry and interest groups.
3.4At around about the same time that the Council was consulting on the proposed modifications to the Finalised Draft Local Plan, the Scottish Executive was consulting on a review of NPPG 6 Renewable Energy Developments. A &RQVXOWDWLRQ 'UDIW RI WKH ([HFXWLYH¶V SURSRVHG 633 (Renewable Energy) was therefore issued for consultation last summer. Following this consultation period Scottish Ministers have considered the responses to the consultation exercise and published the SPP6 (Renewable Energy) in April 2007.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary