Decision 1. To note the report. 2. That the CHORD Programme Manager would forward the details of the snagging list to local Members. (Reference: Report by Executive Director – Development and Infrastructure Services, dated 16 March 2015, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
This report outlines progress to date in the delivery of the Helensburgh CHORD town centre Public Realm Improvement works.
There are essentially four main phases to the works:
Phase 1 A and B West Clyde St/Colquhoun St South and West Bay Esplanade Phase 2 Colquhoun Square, Sinclair Street Car Park and West Princes St Phase 3 A and B Colquhoun St North and East Princes St Phase 4 A and B Sinclair St Phases 1 to 3 and 4A are complete and phase 4B is substantially complete. Public Conveniences and Sinclair St car park re-opened. Contractor currently addressing snagging matters and tidying up the site compound ready for handover to Council at the end of March/early April 2015. . RECOMMENDATIONS
That the Area Committee notes the progress report.
That the Area Committee instruct the Helensburgh CHORD Project Manager to bring a final progress report to the Helensburgh and Lomond June Area Committee. ARGYLL AND BUTE COUNCIL Helensburgh & Lomond Area Committee
DEVELOPMENT AND INFRASTRUCTURE 14 April 2015
HELENSBURGH CHORD PUBLIC REALM IMPROVEMENTS – PROGRESS UPDATE
2.0INTRODUCTION The purpose of this report is to update Members on progress to date in the delivery of the Helensburgh CHORD town centre Public Realm Improvement works. 3.0 RECOMMENDATIONS
3.1That the Area Committee notes the progress report.
3.2That the Area Committee instruct the Helensburgh CHORD Project Manager to bring a final progress report to the Helensburgh and Lomond June Area Committee.
4.0DETAIL
4.1Background The Helensburgh Town Centre Public Realm Improvement works include road narrowing and widening of adjoining pavements in natural materials; resurfacing of the carriageway; installation of new street furniture; soft landscape works; enhanced lighting; creation of a gathering/event space in Colquhoun Square; upgrading the West Bay Esplanade; introducing public art to reflect the heritage and culture of the town; refurbishing the Public Conveniences on the esplanade and upgrading Sinclair St car park. The aim is to enhance both the local and wider communities’ perceptions of the town as a good place to live, work and play and to raise Helensburgh’s reputation as an attractive day visitor destination.
4.2Works to Phases 1 to 3 and 4A. Phase 1 A and B West Clyde St/Colquhoun St South and West Bay Esplanade; Phase 2 - Colquhoun Square, Sinclair Street Car Park and West Princes St; Phase 3 A and B Colquhoun St North and East Princes St and Phase 4 A Sinclair St, works in these areas are complete and the majority of the snagging issues have been addressed. 4.3 Phase 4B Sinclair Street South – works are substantially complete, white lining due to be completed by the 20th March.
4.4The cost for delivering the Helensburgh CHORD Public Realm is anticipated to come in under budget. Once the Final Account has been agreed, likely to be in June 2015, a final cost report will be brought to the Area Committee.
4.5Given the project is more or less complete, the only remaining risks are the satisfactory completion of the snagging items including returning the area of the site compound to the Council in a satisfactory condition and addressing any defects highlighted by the Council during the defects liability period (March 2015 – March 2016). The risks are low to medium. To mitigate against the contractor not satisfactorily addressing these risks an element of funds are being retained by the Council along with the retention budget which is 2.5 % of the contract value paid out at the end of the defects liability period, i.e. March 2016 – see attached Appendix.
4.6To mark the completion of the project it is intended that a launch will take place in Colquhoun Square in early summer, details will be announced shortly. 5.0 CONCLUSION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Helensburgh & Lomond Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref...
Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.