Resolved
Decision Members agreed to not the contents of the report. (Reference: Report by Executive Director – Development and Infrastructure Services, dated 16 March 2015, submitted).
Helensburgh & Lomond Area Committee agreed this item on Tuesday 14 April 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision Members agreed to not the contents of the report. (Reference: Report by Executive Director – Development and Infrastructure Services, dated 16 March 2015, submitted).
The Roads Reconstruction Programme has been structured in accordance with the Roads Asset Management and Maintenance Strategy. The focus has been to recover the network through a delivery of a mix of carriageway resurfacing, patching/surface dressing and in-situ road surface recycling; designed to seal the road to stop the ingress of water, improve ride quality and reduce the amount of reactive repairs.
Over the last 4 years approximately 20% of the Council road network in the Helensburgh and Lomond Area has been treated which will make a significant and positive impact upon the local economy, connectivity and the quality of life in our community.
That the Area Committee notes the successful completion of the 3 year Roads Reconstruction Programme for 2012-2015 and notes the proposed programme and budget for 2015/16.
1 ARGYLL AND BUTE COUNCIL Helensburgh & Lomond Area Committee
DEVELOPMENT AND INFRASTRUCTURE SERVICES 14 April 2015
ROADS CAPITAL RECONSTRUCTION PROGRAMME 2015/16
2.1This report provides Members with details of the proposed roads reconstruction programme for 2015/16.
3.1That the Committee notes the successful completion of the 3 year Roads Reconstruction Programme for 2012-2015 and notes the proposed programme and previously agreed budget for 2015/16.
4.0DETAILS
4.1The focus of the roads reconstruction programme has been to recover the network through the delivery of a mix of carriageway resurfacing schemes, patching/surface dressing and insitu road surface recycling, which follow the principles set out within the Roads Asset Management and Maintenance Plan.
4.2The schemes have been selected using the Councils Roads Asset database WDM-PMS and using the information collected from the full SCANNER Survey carried out in summer 2014. In-line with recommendations within the Annual Status and Options Report, the programme is not necessarily concentrated on the red roads but instead has been realigned to focus on the amber roads to arrest deterioration and prevent these becoming red.
4.3Members’ attention is drawn to the fact that schemes are not necessarily directed at what could be considered as ‘roads in a poor condition’. Surface dressing schemes are selected on the basis that, either the skid resistance of the road surface is poor, or the road surface requires sealing before it fails. As Members are aware, schemes are also weighted on the basis of the strategic level of importance the route.
4.4The summary table below highlights the positive and visible impact of the works undertaken to date. Since 2011 the Council has upgraded almost 40% of its A Class roads in the Helensburgh and Lomond Area and approximately 47km length of roads in the Area, which makes a significant and positive impact upon the local economy, connectivity and the quality of life in our community.
2 4.5 Table – Treatment 2012/13 to 2015/16 in the Helensburgh and Lomond Area
4.6As in previous years, the roads reconstruction programme will be delivered by a mixed economy model with the Councils in-house team delivering carriageway reconstruction and patching works. The surface dressing element of the programme will be delivered by an external contractor; yet to be identified, however, the tendering process is currently underway.
5.0CONCLUSION
This report provides details of the roads reconstruction programme for 2015-16.
6.0IMPLICATIONS
6.1Policy Works assessed and carried out under the current Roads Asset Management and Maintenance Plan.
6.2Financial Programme based on capital allocation for years 2012 – 2016.
6.3Legal None
6.4HR Reconstruction works delivered by a combination of in- house Roads Operations team and sub-contractors.
6.5Equalities None
6.6Risk Completed works will reduce requirement to repair and maintain existing carriageway deterioration.
6.7Customer Services Overall improvement in travel time and quality of driven and walking journeys.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Roads Reconstruction Programme: 2015/2016Report | 127 KB | DownloadRead as text |
PDF |
Helensburgh Lomond Location Plans ALLPlan | 2 MB | Download |
Follow Helensburgh & Lomond Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Police scotland updateDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Report by Police Scotl... | Noted | Open |
| 8 Sep 2026 | Clyde transformation programme & clyde land acquisition overviewDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Verbal update from Cly... | Noted | Open |
| 8 Sep 2026 | Charts (argyll and the isles)Decision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Presentation by Chair,... | Noted | Open |
| 8 Sep 2026 | Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref... | Noted | Open |
| 8 Sep 2026 | Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.