Decision The Council – 1. Approved the recommendations contained within the Capital Plan Summary Report. 2. Approved the Corporate Asset Management Strategy. 3. Approved the Corporate Asset Management Plan. 4. Approved the Service Asset Management Plans. (Reference: Capital Planning Pack 2015/16 to 2019/20, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report introduces the full package of papers included in the budget pack in relation to capital and asset management planning: Capital Plan Summary Report Corporate Asset Management Strategy Corporate Asset Management Plan Service Asset Management Plans
1.2The schools projects in relation to the replacement of Campbeltown Grammar School, Oban High School and Kirn Primary School and the refurbishment of Dunoon Primary School are at present not fully funded within the capital plan the gap after using additional revenue funding is £18.061m.
1.3The proposed capital projects are being brought forward to address the red risks identified within the service asset management plans and the ICT group asset management plan. Where the indicative funding is insufficient to deal with all the red risks this is highlighted within the Corporate Asset Management Plan. ARGYLL AND BUTE COUNCIL COUNCIL
STRATEGIC ASSET MANAGEMENT 23 APRIL 2015 BOARD
INTRODUCTORY REPORT AND RECOMMENDATIONS FOR BUDGET PAPERS ON CAPITAL PLANNING AND ASSET MANAGEMENT PLANNING
2. INTRODUCTION
2.1This report introduces the full package of papers included in the budget pack in relation to capital and asset management planning.
2.2Capital Plan Summary – This report summarises the base capital budget previously approved, profiling and phasing changes, cost increases, overall capital commitment and capital funding to bring out the net level of capital funding available. Separate Appendices set out proposed additions to the capital plan, the phasing and cost changes and the resulting proposed capital plan.
2.3Corporate Asset Management Strategy – Outlines the overall approach to managing the asset base of the Council.
2.4Corporate Asset Management Plan – Identifies key issues for this planning cycle in managing the asset base, the proposed actions and any red risk assets not addressed through the proposed Capital Plan.
2.5Service Asset Management Plans –Summarises the asset base, arrangements for managing assets and key issues for individual departments.
Recommendations
3.1To approve the recommendations in the Capital Plan Summary Report.
3.2To approve the Corporate Asset Management Strategy.
3.3To approve the Corporate Asset Management Plan.
3.4To approve the Service Asset Management Plans.
4. DETAIL
4.1The asset management papers have been prepared by the Strategic Asset Management Board in accordance with policies agreed by Council.
4.2The Corporate Asset Management Strategy outlines the overall approach to managing the asset base of the Council. 4.3 The Corporate Asset Management Plan identifies key issues for this planning cycle in managing the asset base, the proposed actions and any red risk assets not addressed through the proposed Capital Plan.
4.4The Service Asset Management Plans summarises the asset base, arrangements for managing assets and key issues for individual departments.
4.5The Proposed Capital Projects for the period 2015- 20 have been prepared to on the basis of an indicative allocation to address the red risk assets identified by services when preparing their service asset management plans.
5. CONCLUSION
5.1The capital papers have been prepared by the Strategic Asset Management Board in accordance with current approved policies to identify the risks to the Council’s asset base which require to be addressed by capital investment.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.