Decision The Council noted the actions being taken to progress improvements to the capital planning process and that on conclusion of this exercise, a detailed report recommending revisions to the capital planning and prioritisation process will come before the Council in the Autumn for approval. (Ref: Report by the Executive Director of Customer Services dated 15 June 2018, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
At the Council Meeting in February 2018 the Council approved the Capital Plan until financial year 2019/20 on the basis that as financial settlements will continue to tighten and the allocation of capital resources will come under increased scrutiny the shortened timeframe for the plan would give the Council an opportunity to review the existing approach to Capital Planning and Investment and if appropriate introduce a new process for future years. The Council endorsed the proposed improvements to the Capital Planning process which would enable emerging requirements and risks across the Council’s services to be identified and prioritised and instructed officers to bring a report to Council by June 2018 providing an update on these changes.
Recommendations The Council is invited to note the actions being taken to progress improvements to the capital planning process and that on conclusion of this exercise a detailed report recommending revisions to the capital planning and prioritisation process will come before the Council in the Autumn for approval. ARGYLL AND BUTE COUNCIL COUNCIL
CUSTOMER SERVICES 28 JUNE 2018
Capital Planning Update
2.0INTRODUCTION At the Council Meeting in February 2018 the Council approved the Capital Plan until financial year 2019/20 on the basis that as financial settlements will continue to tighten and the allocation of capital resources will come under increased scrutiny the shortened timeframe for the plan would give the Council an opportunity to review the existing approach to Capital Planning and Investment and if appropriate introduce a new process for future years. The Council endorsed the proposed improvements to the Capital Planning process which would enable emerging requirements and risks across the Council’s services to be identified and prioritised and instructed officers to bring a report to Council by June 2018 providing an update on these changes.
This report provides a brief overview of the actions being taken to support the programme of review to enable recommendations on a revised capital planning and prioritisation process to come to a future meeting of the Council for approval.
3.0RECOMMENDATIONS 3.1 The Council is invited to note the actions being taken to progress improvements to the capital planning process and that on conclusion of this exercise a detailed report recommending revisions to the capital planning and prioritisation process will come before the Council in the Autumn for approval.
4.0DETAIL 4.1 The Council’s current approach to capital investment is contained in the Capital Programme Planning and Management Guide which is periodically updated to reflect best practice, with the overall process being overseen from an operational perspective by the Strategic Asset Management Board (SAMB). The Guide:- Sets out the Capital Programme planning and management arrangements; Clarifies their links with existing Council processes; Defines roles and responsibilities for governance, management and implementation; and Provides detail on processes and procedures to be followed in making the arrangements a success.
Currently, Members role in this process is limited to setting the Capital Plan on an annual basis and, thereafter, reviewing progress towards delivery of projects through scrutiny via the capital monitoring procedures.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.