Resolved
Decision The Committee noted the progress made in delivering the Corporate Improvement Programme. (Reference: Report by Executive Director – Customer Services dated 28 May 2015)
Performance Review and Scrutiny Committee noted this item on Thursday 28 May 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Committee noted the progress made in delivering the Corporate Improvement Programme. (Reference: Report by Executive Director – Customer Services dated 28 May 2015)
1.1The purpose of this report is to advise the Performance Review and Scrutiny Committee of the progress made on the Corporate Improvement Programme. ARGYLL AND BUTE COUNCIL PERFORMANCE REVIEW AND SCRUTINY COMMITTEE
CUSTOMER SERVICES 28 May 2015
CORPORATE IMPROVEMENT PROGRAMME PROGRESS
2.1At its last meeting, the PRS Committee noted a report that provided an update on the progress of the Corporate Improvement Programme containing additional detail on the projects in the Programme. This report provides the PRS Committee with a further update on the progress of the Corporate Improvement Programme.
It is recommended that the PRS Committee:
3.1Note the progress that has been made in delivering the Corporate Improvement Programme
3.2Note that officers are carrying out work to develop an updated Corporate Improvement Programme
4.0DETAIL
4.1The current Corporate Improvement Programme has been in place for over 2 years. Progress on the projects that make up the programme had initially been reviewed regularly by the Corporate Improvement Board and the SMT. Regular updates have been presented to the PRS Committee.
4.2The Corporate Improvement Programme was developed to take account of:
• The challenging outlook for public sector finances which suggests medium to longer term reduction in funding.
• Our commitment on working together to improve the potential of our organisation including the following:
o We engage with our partners, our communities and our customers to deliver high quality, continually improving, efficient and responsive services. o Our employees have the skills and attitudes to deliver efficient and effective services. o Our customers have accurate, accessible and up-to-date information about our organisation and the services that we provide.
• Improvement opportunities identified through corporate performance reviews undertaken by Internal Audit. • Other areas for improvement opportunities identified by SMT.
4.3Corporate Improvement Programme Objectives
Taking into account these issues, the Corporate Improvement programme was designed to be a change programme to co-ordinate and challenge activity in the Council to ensure:
• We are well positioned to meet future financial challenges • We secure improvements in the management and use of corporate resources • We secure improvements in service efficiency and effectiveness • We place customer requirements at the centre of business transformation • We build on the good work from the transformation programme.
4.4The Corporate Programme initially consisted of 12 improvement projects, which are listed in Table 1.
4.5As the projects have progressed and been completed, the ongoing governance for the activities and improvements arising from the projects has agreed in order to mainstream these as ‘business as usual’ for the organisation.
4.6Corporate Improvement Programme – Next Steps
The majority of the improvement projects in the Improvement Programme have been completed and mainstreamed. The outlook for the council has changed since it was developed, with adoption of the Single Outcome Agreement and clear objectives for achieving it. The Council has agreed its approach to delivering the SOA through the Planning Our Future paper agreed by the Policy and resources Committee in December 2015. This will include the service choices process and will influence the next iteration of the Council’s approach to Corporate Improvement.
4.7The SMT will be reviewing the Corporate Improvement Programme progress and bringing forward recommendations on the future implementation of corporate improvement. This will be reported to the PRS Committee in due course. Table 1 - CORPORATE IMPROVEMENT PROGRAMME PROJECTS UPDATE
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CORPORATE IMPROVEMENT PROGRAMME PROGRESSReport | 90 KB | DownloadRead as text |
Follow Performance Review and Scrutiny Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Mar 2017 | Treasury management monitoring reportDecision The Committee noted the report. (Reference: Report by Head of Strategic Finance dated 3 March 2017, submitted) | Noted | Open |
| 3 Mar 2017 | Treasury management strategy statement and annual investment strategyDecision The Committee agreed to refer to Council; 1) the proposed Treasury Management Strategy Statement and Annual ... | Agreed | Open |
| 3 Mar 2017 | Quarterly performance reports and scorecardsDecision The Committee noted the contents of the report. (Reference: Report by Chief Executive dated 3 March 2017, su... | Noted | Open |
| 3 Mar 2017 | Maximising attendanceDecision The Committee noted; 1) the content of the report; and 2) the measures the Council has put in place to manag... | Noted | Open |
| 3 Mar 2017 | Succession planningDecision The Performance Review and Scrutiny Committee noted the presentation. (Reference: Presentation by Head of Im... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.