AI summaryArgyll and Bute Council noted progress on its 26-action Corporate Improvement Plan 2025 to 2028, covering transformation, performance, finance, community engagement and workforce, with most actions on track to revised targets.
Written from the decision and the officer reportPDF Pro
OutcomeNotedNo decisions taken, progress recorded only
MoneyNot stated
What happens nextContinue delivering the planActions run to March 2028 across themes
Who it affectsCouncil staff and residentsThrough service transformation and engagement
What was decided
The Council noted the progress made in delivering the Corporate Improvement Plan to date.
The Council noted the contribution the Actions make towards the delivery of Best Value.
Why
The Chief Executive's report sets out 26 Corporate Improvement Plan actions grouped under Transformation, Performance, Community, Finance, and Leadership and Workforce themes, with a status for each. Report P1, P2, P3, P8, P9, P10, P15, P18, P21
Eight actions are reported as Complete, one as Partially Complete, one as Delayed, and the rest as On Track, several to revised timescales because of pilot outcomes or further scoping work. Report P2, P3, P5, P6, P8, P9, P10, P13, P18
The report links the actions to Best Value, demonstrating contribution through areas such as data-driven decision making, financial sustainability, workforce planning and community engagement. Report P9, P14, P15, P16, P17, P18, P19, P20
What happens next
Continue delivering actions against key dates running from 2025 through to March 2028, with updates expected at future Council meetings. Report P1, P8, P15, P19, P21
Reshape action CIP04 once the National Self-Evaluation Framework pilot outcome is known. Report P3
Progress the capital programme review into 2026/27 and roll out self-improving schools groups from August 2026. Report P7, P15
Options considered
Chosen: Note the progress on the Corporate Improvement Plan and the contribution to Best Value. The Council was being asked to note progress; no alternative was tabled in the report.
Implications
Staffing: Sickness absence ranking worsened: non-teaching moved from 20 to 27 and teaching from 28 to 31 in 2024/25, against a Scotland-wide trend; a wellbeing strategy was approved in June and corporate actions are being developed. Report P18
Staffing: Agency worker spend reduced by 17.4% and temporary posts by 20% compared with 2024/25, measured against a 10% reduction and 5% reduction target respectively. Report P19
Financial: A revised approach to the capital programme was agreed in February 2026; full review work continues into 2026/27 with flexibility built into the capital funding framework. Report P15
Equalities: Engagement guidance has been updated and island-specific engagement reported to the Islands Sounding Board, with the aim of reaching a wider group of representatives including protected characteristics. Report P14
Other: Digital skills confidence rose to 24% under the AB365 programme against an 80% target, and a new digital skills action plan is to be created via the 365 Board. Report P20
Risk: The National Self-Evaluation Framework pilot will determine revised success measures and key dates for action CIP04. Report P3
Other: Microsoft Copilot is being piloted in HR&OD and direct participation in the Copilot Proof of Concept is providing feedback for wider use. Report P6
Who and where
Council staff across all services, including Head Teachers, senior leaders and HR&OD Report P6, P7, P19, P20
Residents and service users, through improved online forms, data platforms and public performance reporting Report P3, P4, P5, P10
Young people entering the Council workforce and older workers approaching retirement Report P17, P19
Community groups, consultees and protected characteristic representatives Report P14
Timeline
Jun-25: Data platform launched, first live Power BI report for Revenue and Benefits Report P2
Aug-Dec 2025: Self-improving Schools Groups pilot ran; first implementation phase from August 2026 Report P7
Feb 2026: Council agreed a change in approach to the capital programme Report P15
May/Jun 2026: Transformation and Savings Strategy reviewed by Policy and Resources and approved at Council Report P9, P21
Jun 2026: Updated wellbeing strategy approved by Council Report P18
Oct-25 to Mar-28: Key dates for individual CIP actions across the plan period Report P1, P2, P3, P5, P8, P9, P10, P11, P12, P13, P14, P15, P16, P17, P18, P19, P20, P21
Plain English for the jargon
Best Value: Statutory duty on Scottish councils to show continuous improvement in how they deliver services.
LGBF: Local Government Benchmarking Framework, used to compare council performance.
NSEF: National Self-Evaluation Framework, the basis for the council's self-assessment pilot.
Power BI: Microsoft data reporting tool used to publish dashboards and performance information.
SISG: Self-improving Schools Groups, a pilot for school leadership through professional collaboration.
PDA: Professional Development Award, here at SCQF Level 8 in Project Management.
AB365: The council's digital skills programme, aiming to raise employee confidence in digital tools.
Health of the Organisation: Internal reporting dashboard used to track workforce indicators such as absence and young people employed.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10c
Resolved
Decision The Council – 1. noted the progress made in delivering the Corporate Improvement Plan to date; and 2. noted the progress made and the contribution that the Actions make towards the delivery of Best Value. (Reference: Report by Chief Executive dated 26 August 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Corporate Improvement Plan Action Plan 2025-28 ID Theme Outcome Success Measure Key Date 2025/26 Progress Status CIP01 Transformation Scottish Approach to Service Design is Report on utilisation of framework in at Mar-27 Transformation strategy approved and approach to transformation and Project On track to embedded into our transformation least 3 services' change processes. Management Office underway. Approach to transformation projects still being revised programme. put in place. timescale
CIP02 Transformation We identify opportunities to resolve Increase in Power BI reports available by Mar-26 2025/26 FQ1 - 4 Complete data challenges through production of 6 per quarter. 2025/26 FQ2 - 9 Power BI reports to support our Connect 2025/26 FQ3 - 13 for Success principle - Data and evidence- 2025/26 FQ4 - 16 driven. CIP03 Transformation Data deployment and accessibility is Data platform launched and available. Jun-25 The Data platform was launched and used for the first live Power BI report for Complete improved by the development of the Revenue and Benefits Team in June 2025. It has since been used and is now interfaces. available to support the creation of other reports.
CIP04 Transformation Self-assessment feeds into improvement Number of improvement plans at each Mar-26 The Council has been selected as a pilot in the national self-evaluation Delayed and plans at team, service and corporate level that have self-assessment as the framework (NSEF) and this will shape our approach to self-evaluation. Success rescheduled levels using appropriate LGBF indicators. source of improvement identified. measure and key date to be revised depending on outcome of pilot. to align with NSEF. CIP05 Transformation We improve accessibility, capture and Increase in online forms, that are Jul-26 The Web Team carried out a full review of all forms as part of Budget Complete use of data through increased use of compatible with data analysis and Transformation activities and a priority list of eform additions and improvements online forms. automation processes. has been added to the Customer Engagement Team, Team Plan for 2026/27.
Property Services have developed and implemented a MS Forms Client Service Request form replacing the original A5 process representing a key step in improving accessibility and the capture of consistent data. The form will ultimately integrate with Concerto to enhance reporting, analysis and to reduce errors/improve consistency by ensuring data is extracted from a single point of origin. Property Services are also keen to investigate automation of the Helpdesk function similar to the HR bot.
Estates and Property Development are working with Community Development to develop an online form for asset transfer - expressions of interest.
Phase one of the HR&OD Digital Project saw the launch of an AI chat bot and implementation of service desk ticketing functionality as well as an exploration for replacement for the absence telephone line. Phase two will further this work with ongoing exploration of absence line functionality and an optional appraisal for all forms with appropriate automation identified. Corporate Improvement Plan Action Plan 2025-28 ID Theme Outcome Success Measure Key Date 2025/26 Progress Status CIP06 Transformation Our learning council principle is 2 pilot approaches complete and Oct-26 Direct participation in the Microsoft Copilot Proof of Concept pilot, testing its use Complete embedded through increased use of evaluated. in day to day work and providing feedback on effectiveness and wider pilots and reflective evaluation. application. Use of Copilot across HR&OD to support meeting notes, actions and documentation, alongside sharing learning with colleagues. Ongoing engagement with services to promote use of Copilot, with a focus on building capability for workforce planning, improving insight and reducing administrative effort.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.