Decision The Committee noted the recommendations at 3.1 of the report. (Ref: Report by Oban Lorn Arc Regeneration Programme Manager dated 16 th February 2016, submitted). The Council resolved in terms of Section 50(A)(4) of the Local Government (Scotland) Act 1973 to exclude the press and public for the following item of business on the grounds that it was likely to involve the disclosure of exempt information as defined in Paragraphs 8&9 respectively of Part 1 of Schedule 7A to the Local Government (Scotland) Act 1973. The Committee considered the appendices to the Report referred to above. Decision The Committee noted the information provided.
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The purpose of this report is to update the Policy & Resources Committee on progress in delivering the Lorn Arc Tax Incremental Financing Programme and its nine capital infrastructure investment projects led by Development and Infrastructure Services. The attached Highlight Report (Appendix A) outlines the current position of the three most immediate projects as at the 16th February 2016.
1.2This paper also reiterates the need for the Lorn Arc and reports on key issues that will impact on the successful delivery of the projects from design development stage through to procurement and implementation.
1.3This report sets out the envisaged timelines for the nine projects within the Lorn Arc programme and provides a brief synopsis of the current position relating to each of these projects.
1.4Of particular note, is that the Phase 1 works at the new business park at Oban Airport (Project 9) has been completed.
1.5Budget: Detailed below is the current budget position for both the revenue and capital approved budget allocations.
REVENUE £000s Total approved funds 1,607 Total project spend to date Jan 2016 71 Balance 1,536 CAPITAL £000s Total approved funds 1,388 Total project spend to date Jan 2016 483 Balance 905
1.6It is recommended that the Policy & Resources Committee:
Note the current progress with the Lorn Arc Programme; Note that recruitment is underway for 1 full time Lorn Arc Programme Manager, 1 full time Lorn Arc Project Manager and a Secondment opportunity for a Lorn Arc Project Manager; Approve Officers formally requesting from the Lorn Arc TIF Executive the removal of the two Barcaldine projects from the Lorn Arc Business Case but retaining the option to borrow up to £18.9m across the remaining projects or bringing forward additional projects in due course subject to approval and affordability. Approve revising the reporting Tolerance levels in line with the levels set for the Council’s monthly Capital Financial Reporting i.e. Project Plan +/- 2 months on agreed completion and Project Budget +/- 5% of agreed budget subject to a minimum of £50,000. ARGYLL AND BUTE COUNCIL POLICY & RESOURCES COMMITTEE
DEVELOPMENT & INFRASTRUCTURE SERVICES 17th March 2016
LORN ARC – UPDATE REPORT AS AT 16th FEBRUARY 2016
2. INTRODUCTION
2.1This report reiterates the need for the Lorn Arc and provides an update to the Policy & Resources Committee on progress in delivering the Lorn Arc Tax Incremental Financing Programme led by Development and Infrastructure Services. The attached Highlight Report (Appendix A) outlines the current position of the three most immediate projects as at the 16th February 2016.
2.2The paper also reports on key issues that will impact on the successful delivery of the projects from development stage through to procurement and implementation.
Recommendation
3.1It is recommended that the Policy and Resources Committee:-
Note the current progress with the Lorn Arc Programme
Note that recruitment is underway for 1 full time Lorn Arc Programme Manager, 1 full time Lorn Arc Project Manager and a Secondment opportunity for a Lorn Arc Project Manager;
Approve Officers formally requesting from the Lorn Arc TIF Executive the removal of the two Barcaldine projects from the Lorn Arc Business Case but retaining the option to borrow up to £18.9m across the remaining projects or bringing forward additional projects in due course subject to approval and affordability
Approve revising the reporting Tolerance levels in line with the levels set for the Council’s monthly Capital Financial Reporting i.e. Project Plan +/- 2 months on agreed completion and Project Budget +/- 5% of agreed budget subject to a minimum of £50,000.
4. DETAILS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv...
Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.