AUDIT COMMITTEE DEVELOPMENT PLAN

Noted Finance 3 papers

Audit Committee noted this item on Friday 11 March 2016. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

Decision The Committee; i) noted the report and updated 2015/2016 Audit Committee Development Plan; ii) discussed the potential content of protocols to enhance the effectiveness of the Committee and its meetings; iii) noted the Vice Chair and the Chief Internal Auditor would discuss how further effectiveness activity would best benefit the Committee’s changing membership; and iv) approved the removal of action points showing as complete. (Reference: Report by Vice Chair, Audit Committee dated March 2016, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Audit Committee

Executive summary

1.1This report provides a progress update in respect of the Audit Committee Development Plan action points. The plan is a rolling document and is underpinned by effectiveness session activity.

1.2A number of new action points were identified during the Committee’s September 2015 effectiveness session and these have been added to the development plan. Where action points are recurring, dates have been updated accordingly

1.3Action point 1 in relation to developing links between Audit and Scrutiny was previously rescheduled for March 2016. A meeting between respective chairpersons has taken place and a protocol has been agreed. Appendix 1 shows a note from the Audit Committee chairperson.

1.4Action point 7, Sharepoint overview has been rescheduled due to workload commitments and staff absence. Appendix 2 shows the updated Development plan.

Recommendations

2.11) Members to note report and updated of 15/16 Audit Committee development plan.

2) Members to approve removal of actions points showing as complete.

3 CONCLUSION

3.1The Audit Committee development plan is a working document and is underpinned by effectiveness session activity. All current action points are either complete, on track or not scheduled.

4. IMPLICATIONS

4.1Policy –.None

4.2Financial – None directly however potential resource implication of additional internal audit work which may be offset by reduced external audit fee. 4.3 Personnel – None

4.4Equal Opportunities – None

4.5Legal – None.

4.6Risk – None

4.7Customer Service – None.

SHEILA HILL VICE CHAIR AUDIT COMMITTEE

For further information contact: Kevin Anderson, Tel 01369 708505 [email protected]

Appendix 1- Scrutiny Links note from Chair Appendix 2 - Audit Committee Development Plan

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
AUDIT COMMITTEE DEVELOPMENT PLANReport 51 KB DownloadRead as text
PDF
_ Audit Committee Development Plan Note Scrutiny LinksAppendix 1 57 KB Download
PDF
. Audit Committee Development planAppendix 2 57 KB Download

At this meeting

Whole meeting

Who was there

4 of 13 attended
DJ
David JamiesonPublic, expected
RS
Russell SmithPublic, expected
GS
Grace ScanlinPublic, expected
MC
Martin CaldwellChair, present
MB
Councillor Michael BreslinMember, present
IM
Councillor Iain MacDonaldMember, apologies
RT
Councillor Richard TrailMember, present
SH
Sheila HillVice-Chair, present
FM
Fiona McCallumSecretary, expected
IM
Councillor Iain MacLeanMember, expected
SM
Shona MarshallSecretary, expected
GF
Graeme ForresterOfficer, expected

All 13 on the meeting page

On this subject at Argyll and Bute

Search all
  1. AUDIT COMMITTEE DEVELOPMENT PLANThis decision
  2. Audit & scrutiny committee development planNoted
  3. Audit committee development: action planNoted
  4. Update on internal audit development planNoted
  5. Audit committee development dayNoted
  6. Audit of best value and community planning: issues for policy development groupNoted

More from Argyll and Bute Audit Committee

All decisions
MeetingDecisionOutcome
24 Mar 2017 Internal audit summary of activitiesDecision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March ... Noted Open
24 Mar 2017 Internal audit reportsDecision The Committee noted the contents of the summary report and the detail within each individual report. (Refere... Noted Open
24 Mar 2017 External & internal audit report follow-up 2016 - 2017Decision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March ... Noted Open
24 Mar 2017 Internal audit annual plan 2017 - 2018Decision The Committee agreed and approved the Internal Audit Annual Plan 2017/18 (Reference: Report by Chief Interna... Agreed Open
24 Mar 2017 External audit plan 2017 - 2018Decision The Committee noted the contents of the report. (Reference: Report by Audit Scotland dated March 2017, submi... Noted Open