Decision The Harbour Board noted the content of the report including the planned steps as identified in section 5.4: 1) User Group meetings at four main ports have now been arranged for April and a programme of meetings going forward is to be agreed; 2) Work on compilation of appendices to the SMS document for main piers and harbours to continue; 3) Once documentation has been produced for the main piers and harbours, a similar exercise will be carried out for the less strategic ports; and 4) Following the initial ‘User Groups’ for all main ports, further meetings at lesser ports are to be arranged. (Reference: Report by Executive Director – Development and Infrastructure Services dated 17 March 2016, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report provides a further update on ongoing initiatives to ensure compliance with the Port Marine Safety Code (PMSC); it follows on from last report presented to the Harbour Board in January of this year.
1.2The PMSC applies to all harbour authorities in the UK that have statutory powers and duties; it establishes the principle of a national standard for every aspect of port marine safety; it sets out to enhance safety for those who use or work in our ports. The Council is responsible for 41 marine structures; of these, 7 are considered to be Statutory Harbour Authorities:- Campbeltown, Dunoon, Oban, Rothesay, Craignure, Port Askaig and Carradale. The Code is not statutory, but it has a relevance and moral force that means it is obligatory.
1.3Argyll & Bute Council appointed Marico Marine to provide an independent Designated Person (DP) service, as described in the PMSC. The DP has highlighted a need to undertake a number of specified works that have been identified through recent audits. The status of actions arising from the recent audits is provided in the appendix to this report; this provides details of works required to be carried out in order to complete the SMS document and ‘close-out’ audit findings.
1.4A draft Safety Management System (SMS) document has been produced and work is progressing to ensure full compliance with the PMSC. Additional resources are being allocated to assist with the timely completion of this task.
1.3User Group meetings are being arranged at all main ports to take place in April.
1.4The new database using specialist marine software (Marni’s) has been set up at all our main ports and further training to all harbourmasters is to be provided in April.
Recommendations
2.1That Members note this report and, in particular, the planned ‘next steps’ identified in section 5.4 of this report.
1 ARGYLL AND BUTE COUNCIL ARGYLL AND BUTE HARBOUR BOARD
DEVELOPMENT AND INFRASTRUCTURE SERVICES 7 APRIL 2016
PORT MARINE SAFETY CODE UPDATE
2.0INTRODUCTION
2.1This report provides a further update on ongoing initiatives to ensure compliance with the Port Marine Safety Code; it follows on from last report presented to the Harbour Board in January of this year.
2.2It was explained in previous reports that the Council has appointed ‘Marico Marine’ to provide an independent “Designated Person” (DP) service, as described in the Port Marine Safety Code (PMSC), on a three year contract which expires in December 2017. The PMSC states that each harbour authority must appoint an individual as the DP to provide independent assurance to the duty holder that the marine safety management system is working effectively; it describes the DP as ‘independent’, with direct access to the Board. Prior to cessation of the existing contract, the position of DP will be re-tendered.
3.1That Members note this report and, in particular, the planned ‘next steps’ identified in section 5.4 of this report.
Background
4.1As a ‘Statutory Harbour Authorities’ (SHA), the Council has specific obligations set out in national legislation (notably the Harbours Act 1964). All SHAs are subject to the Port Marine Safety Code (PMSC). The Code is not statutory, but it has relevance and moral force that means it is obligatory.
4.2In order to comply with the Code, the Council must develop and operate an effective marine ‘Safety Management System’ (SMS). Each harbour authority must appoint a DP to provide independent assurance directly to the “Duty Holder” that the marine Safety Management System (SMS) is working effectively. Their main responsibility is to determine, through assessment and audit, the effectiveness of the Marine SMS in overall compliance with the Code.
2 5.0 DETAIL
5.1Audits have now been carried out by the Council’s DP at the following locations:-
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Argyll and bute harbour board workplanDecision The Argyll and Bute Harbour Board noted the content of the workplan. (Reference: Argyll and Bute Harbour Boa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.