INTERNAL AUDIT SUMMARY OF ACTIVITIES

Noted Finance 1 paper

Audit Committee noted this item on Friday 17 June 2016. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

Decision The Audit Committee noted the report. (Reference: Report by Chief Internal Auditor dated 17 June 2016, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Audit Committee

Executive summary

1.1The objective of the report is to provide a summary of Internal Audit activity and progress during Quarter 1.

1.2Core activities together with a progress update statement are shown below.

 16/17 Audit Plan progress: The Audit plan is currently on track.

 Individual Audits undertaken: 9 audits have been completed during the period. Of these Audits, one is rated as Limited and one is rated as No Assurance.

 Continuous Monitoring Programme Testing: A number of auditable units are subject to continuous testing. Reporting is by exception. Management have responded to previous quarter notifications and there are no outstanding issues. A No Assurance opinion is showing against one area in relation to stock control procedures at an Integrated Equipment store.

 Development Plan: One action point relating to the roll-out of Sharepoint has been rescheduled due to resourcing issues.

 Performance indicators: Current status is green / on track. ARGYLL AND BUTE COUNCIL AUDIT COMMITTEE

STRATEGIC FINANCE 17 JUNE 2016

INTERNAL AUDIT SUMMARY OF ACTIVITIES

2. INTRODUCTION

2.1The objective of the report is to provide an update on Internal Audit activity during Quarter 1 against a number of areas;

 16/17 Audit Plan progress  Individual Audits undertaken  Continuous Monitoring Programme Testing  Internal Audit Development Plan  Performance indicators

Recommendations

3.1The Audit Committee is asked to note the content of the report.

4. DETAIL

4.1The 15/16 Audit Plan was completed subject to the undernoted exceptions.

• Asset Management: Superseded by Audit Scotland Best Value review • Resource Allocation System: Removed due to use of system being discontinued April 2016. • Piers and Harbours: Delayed pending on-going legal activity.

4.2Audits completed to May are detailed in Table 1. At the time of writing there are two Quarter 1 Audits which are in progress and which will be reported to the September meeting of the Committee. These are Oban Airport and Debt Recovery / Write-off Procedures.

Table 1: Summary of Audits performed in Quarter 1 2016/17:

Audit Name Level of No. of High Assurance recommendations Recommendations 2015/16 Townscape Heritage Initiative Substantial 2 0 Capital Contracts Limited 3 1 Disposal of Equipment Substantial 10 1 2016/17 Homecare Contract Substantial 3 0 Compliance Freedom of Information Substantial 3 1 Criminal Justice Substantial 2 0

Project Certification Substantial 2 1

Parking at Council Buildings No Assurance 1 1

Housing and Repair Grants Substantial 4 0

4.3Audits planned for the Quarter 2 16/17 are shown in the table below.

Quarter 2 Strategic Finance Hub North Project Financing Childrens Units Leader and Flag Local Government Benchmarking Framework Procurement Off-contract Purchasing Adult Care Charging Waivers Resource-Link Pool Cars

4.4Internal Audit has received two requests from services to undertake additional compliance testing. The first is assisting Health and Safety staff with an internal assessment exercise in relation to Moving and Handling policies and procedures. The other request is in relation to compliance testing in respect of Keeper of Records requirement. This work will be scheduled into our programme via contingency days.

4.5A number of areas which were previously subject to individual audits now form part of our continuous monitoring programme. These areas are tested on a regular basis and detailed reporting will be by exception to Audit Committee. Standard audit tests are applied relevant to each auditable unit. A follow up process is in place whereby management are advised of findings and where appropriate, requested to take remedial actions. There are currently no outstanding follow-up points arising from previous quarters testing. Table 2 below summarises activity to date outlining issues arising and provides a level of assurance together with follow up detail.

Table 2: Continuous monitoring programme results:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
INTERNAL AUDIT SUMMARY OF ACTIVITIESReport 402 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 11 attended
DJ
David JamiesonPublic, expected
RS
Russell SmithPublic, expected
GS
Grace ScanlinPublic, expected
MC
Martin CaldwellChair, present
MB
Councillor Michael BreslinMember, present
IM
Councillor Iain MacLeanMember, apologies
RT
Councillor Richard TrailMember, present
SH
Sheila HillVice-Chair, apologies
FM
Fiona McCallumSecretary, expected
GF
Graeme ForresterOfficer, expected
AP
Adele Price-WilliamsSecretary, expected

On this subject at Argyll and Bute

Search all
  1. INTERNAL AUDIT SUMMARY OF ACTIVITIESThis decision
  2. Internal audit updateNoted
  3. Internal audit report stakeholder engagementDecided
  4. Internal audit report risk managementDecided
  5. Internal audit contractNoted
  6. Internal audit report direct paymentsDecided

More from Argyll and Bute Audit Committee

All decisions
MeetingDecisionOutcome
24 Mar 2017 Internal audit summary of activitiesDecision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March ... Noted Open
24 Mar 2017 Internal audit reportsDecision The Committee noted the contents of the summary report and the detail within each individual report. (Refere... Noted Open
24 Mar 2017 External & internal audit report follow-up 2016 - 2017Decision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March ... Noted Open
24 Mar 2017 Internal audit annual plan 2017 - 2018Decision The Committee agreed and approved the Internal Audit Annual Plan 2017/18 (Reference: Report by Chief Interna... Agreed Open
24 Mar 2017 External audit plan 2017 - 2018Decision The Committee noted the contents of the report. (Reference: Report by Audit Scotland dated March 2017, submi... Noted Open