MR JAMES BLACK: SITE FOR THE ERECTION OF 5 DWELLING HOUSES: THE PADDOCK, ARDOCH ESTATE, ARDOCH (REF: 16/03231/PPP)
AgreedPlanning5 papers
Planning, Protective Services and Licensing Committee agreed this item on Wednesday 26 April 2017. Below is the council's own wording, with the papers it was decided on.
Decision The Committee agreed to hold a local pre determination hearing. (Reference: Report by Head of Planning and Regulatory Services dated 7 April 2017, Supplementary Report number 1 dated 21 April 2017, Supplementary Report number 2 dated 24 April 2017 and Supplementary Report number 3 dated 25 April 2017, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Planning, Protective Services and Licensing Committee
Argyll and Bute Council Development and Infrastructure Services
Delegated or Committee Planning Application Report and Report of handling as required by Schedule 2 of the Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2013 relative to applications for Planning Permission or Planning Permission in Principle ____________________________________________________________________________
Reference No: 16/03231/PPP
Planning Hierarchy: Local Application
Applicant: [name removed]: Site for the erection of 5 dwellinghouses
Site Address: The Paddock, Ardoch Estate, Ardoch ____________________________________________________________________________
DECISION ROUTE
Local Government Scotland Act 1973 ____________________________________________________________________________
(A) THE APPLICATION
(i) Development Requiring Express Planning Permission
Erection of 5 dwellinghouses; Construction of private access. Installation of private sewage treatment plant
(ii) Other specified operations
Connection to public water supply. ____________________________________________________________________________
(B) RECOMMENDATION:
It is recommended that, subject to a discretionary hearing, planning permission in principle be approved subject to conditions. ____________________________________________________________________________
(C) HISTORY:
C.8534 – Erection of 14 dwellinghouses and formation of access – Refused, appeal dismissed following public enquiry 30 August 1990. Erection of 6 dwellinghouses and formation of access – Refused 9 November 2000 Erection of 6 dwellinghouses – Refused 1 October 2002 and appeal dismissed ____________________________________________________________________________
(D) CONSULTATIONS:
Council’s Roads Engineer (dated 23/12/16 and 10/02/17): No objections subject to conditions. Scottish Water (dated 2/4/16): No objection.
Scottish Gas Network (dated 18/1/17): On the mains record our low/medium/intermediate pressure gas main is near your site. There should be no mechanical excavations taking place above or within 0.5m of a low/medium pressure system or above or within 3.0m of an intermediate pressure system. You should, where required confirm the position using hand dug trial holes.
Scottish Environment Protection Agency (dated 16/12/16): No objection.
Council’s Flood Risk Assessor (dated 03/01/17): No objections subject to conditions. These include no housing development located below the 4.5m AOD contour line, finished floor levels to be at least 5.2 AOD and SuDS.
Council’s Biodiversity Officer (dated 23/01/17): The site is a mosaic of dry and wet habitats set between the railway line and the A814. Request that an ecological survey with a focus on the ornithological and wetland interest of the Reed-bed habitat is carried out at the optimum time of the year by a suitably qualified person. If the recommendation is to approve then also request a detailed Landscaping Planting Plan and Habitat Management Plan for the reed-bed and other areas deemed to be suitable for wildlife (to reflect ecological report) are submitted.
West of Scotland Archaeology Service (dated 21/12/16): The site is too low lying to hold much archaeological potential.
Cardross Community Council (dated 09/1/17): Yet again there exists confusion in the Planning Law Framework in that twice this area has been refused planning permission and a third application to be included in the Local Development Plan approved. After Local Authority public hearings and PPS&L Committee decisions not being recognised by the Reporter, now this area is incorporated into the Local Development Plan and removed from the greenbelt for housing.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning, Protective Services and Licensing Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.